HEO Tower Crane NC III flashcards
HEO Tower Crane NC III · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Wire rope discard criteria
- Replace running rope when broken wires exceed 10 in any 6d length or 5 in any 30d length for a single lay, or when kinks, bird-caging, or severe corrosion are present.
- Hook throat opening limit
- Discard a hook when the throat opening has increased more than 15 percent, wear exceeds 10 percent of the original dimension, or the hook is bent or twisted more than 10 degrees.
- Sling angle tension formula
- Tension per leg equals load divided by (number of legs × sine of the angle from horizontal). At 30 degrees each leg carries the full load; at 60 degrees, 0.58 of it.
- Choked hitch derating
- A choked (choker) hitch reduces wire rope sling capacity by roughly 20 percent compared with a vertical hitch, because the rope is bent around itself and the load.
- Ground bearing pressure
- Pad pressure equals total crane ground load divided by total pad area. Compare the result with the geotechnical allowable bearing pressure before setting up outriggers or a crane base.
- Overhead line clearance
- Maintain at least 3 m clearance from power lines up to 50 kV, with greater distances for higher voltages, and use goalposts or barriers to prevent contact.
- Mast verticality tolerance
- Tower crane mast verticality is typically checked to 1/1000 of height, with a maximum deviation specified in the manufacturer's manual, commonly 200 to 300 mm at the top.
- Erection sequence order
- Typical order: foundation check, mast sections, slewing unit, cab, jib and counter-jib, counterweights and ballast, wiring and limit switch commissioning, then load test.
- Free-standing height limit
- The manufacturer sets a maximum free-standing height; beyond it the crane must be tied to the building with wall ties at specified intervals and calculated tie forces.
- Climbing operation wind limit
- Jacking or climbing is stopped when wind exceeds the manufacturer's limit, commonly 10 to 13 m/s, and no personnel may remain on the jib during the climb.
- Ballast and load chart link
- Counterweight and ballast must match the load chart configuration exactly; changing ballast changes the rated moment and invalidates the chart used for lifting.
- Post-erection load test
- After erection or climbing, a competent person load-tests the crane and verifies the load moment limiter and all limit switches before handover to service.
- Load moment limiter function
- The LML compares actual load moment (load × radius) with the rated moment and stops hoisting or boom-out at the limit; it must never be bypassed.
- Slewing side-load effect
- Slewing a suspended load creates centrifugal and side forces on the jib; keep slewing slow, keep the load below the jib, and avoid combined motions unless permitted.
- Anti-two-block device
- The anti-two-block device prevents the hook block from contacting the jib tip; it must be function-tested before each shift and the hoist limit must stop before contact.
- Shock loading risk
- Sudden pick-up or snatching a load can multiply the static load several times; take up slack slowly and use soft-start on the hoist to avoid overload.
- Personnel platform lift rule
- Lifting people is allowed only with a certified personnel platform, a written risk assessment, and an authorized permit; never lift a person on the hook or slings.
- Emergency stop hand signal
- Both arms raised with palms forward is the emergency stop signal; anyone on site may give it, and the operator must stop immediately regardless of who signals.
- Single designated signaler
- Only one designated signaler gives commands to a crane operator, except that any person may give an emergency stop at any time to prevent injury or damage.
- Radio lift protocol
- Identify crane and station, use short clear phrases, acknowledge every command, and confirm the load is clear before slewing or travelling.
- Loss of communication rule
- If radio or visual contact is lost, the operator stops and holds the load until contact is restored or the load is landed under a pre-agreed procedure.
- Blind lift arrangement
- When the operator cannot see the load, a signaler at the load position relays commands, and the lift plan states who signals and on which radio channel.
- Rated capacity definition
- Rated capacity is the lesser of the load chart value at the working radius and the structural or rigging limit; it already accounts for hook block and slings where stated.
- Working radius measurement
- Working radius is the horizontal distance from the slewing center to the centerline of the hook; increasing radius reduces capacity as the moment arm grows.
- Load moment formula
- Load moment in tonne-metres equals load in tonnes multiplied by radius in metres; the crane's rated moment is fixed for a given configuration.
- Net payload calculation
- Net payload equals the chart capacity at radius minus the weight of hook block, slings, and lifting beam. Example: 5 t chart minus 0.6 t rigging gives 4.4 t.
- Critical lift threshold
- A lift is critical when it exceeds 75 percent of chart capacity, involves tandem cranes, passes over occupied areas, or uses unusual rigging; it needs an engineered plan.
- Hierarchy of controls
- Controls rank from elimination, substitution, engineering controls, and administrative controls down to PPE, which is the last line of defense.
- Thorough examination interval
- Lifting equipment requires periodic thorough examination by a competent person, commonly every 6 or 12 months depending on equipment type and jurisdiction, separate from daily checks.
- Lockout tagout purpose
- LOTO isolates electrical, hydraulic, and gravitational energy before maintenance, with locks and tags applied and energy verified absent before work begins.
- Brake holding test
- Test the hoist brake by lifting a test load slightly and holding it, checking for drift; the brake must hold the rated load without slipping.
- Crane shutdown procedure
- Land and secure the load, park the jib in the specified position, apply the slewing brake, switch off power, lock the cab, and record the shutdown in the log.