HEO Tower Crane NC III study plan
HEO Tower Crane NC III · Give each week a clear focus.
8 weeks · About 7 hours per week
Pre-operation inspection, rigging, and site preparation & Occupational safety, health, and environmental regulations
List every pre-operation inspection item for a tower crane (structure, wire rope, hook block, limit switches, brakes, anemometer, earthing) from memory, then verify against a manufacturer manual and mark gaps
Demonstrate and narrate a full daily inspection walk-around in under 15 minutes, calling out each check and its reject criteria
Identify and correctly name 10 rigging components (sling types, shackles, hooks, master links, turnbuckles) and state their inspection rejection points
Summarize the OSH requirements that govern crane operation on site, including PPE, permit-to-work, and exclusion zone rules, in a one-page note
Your checkpoint
A completed daily inspection checklist with rejection criteria and a signed self-audit of one narrated walk-around (pass/fail per item)
Pre-operation inspection, rigging, and site preparation & Safe lifting operations and load control
Compute tension in each leg of a two-leg and four-leg sling at 30, 45, and 60 degrees from horizontal, and explain why the angle factor changes capacity
Select rigging for three given loads (symmetrical, off-centre, and sharp-edged) and justify sling type, protection, and number of legs
Describe how to verify the load's weight and centre of gravity before lift, including using markings, shipping documents, and trial lift
State the hand and radio signals used for hoist, lower, slew, trolley, stop, and emergency stop, and practise them until recall is automatic
Your checkpoint
A rigging calculation worksheet with three worked sling-angle problems and a written rigging selection for three loads, all checked against reference tables
Safe lifting operations and load control & Signals, communication, and team coordination
Explain the sequence of a safe lift from pre-lift briefing to load landing, including trial lift, tag lines, and slew/trolley coordination
Identify the causes and prevention of load swing, and describe how to control a swinging load without shock loading the crane
Run a mock pre-lift briefing covering roles of operator, rigger, signalman, and banksman, and record who confirms what
Practise radio communication using standard phrases (clear, stand by, hoist slow, stop) and eliminate ambiguous words from your script
Your checkpoint
A written lift sequence and pre-lift briefing script for one representative lift, plus a self-scored signal and radio drill log with at least 20 correct responses
Load charts, lifting plans, and capacity calculations & Safe lifting operations and load control
Read a tower crane load chart and extract rated capacity for five combinations of radius, jib configuration, and hoist line (single vs double reeve)
Calculate net capacity by deducting hook block, slings, and any jib attachments from rated capacity, and flag lifts where net capacity is exceeded
Explain the effect of wind, out-of-service condition, and travel/erection states on chart values, and state the wind speed at which lifting must stop per the manual
Draft a simple lifting plan for a load near 80% of chart capacity, including radius, weight, rigging, ground bearing, and exclusion zone
Your checkpoint
A load chart exercise set with five capacity look-ups and deductions, all correct, plus a one-page lifting plan reviewed against a checklist
Tower crane setup, erection, and dismantling support & Pre-operation inspection, rigging, and site preparation
Describe the sequence of tower crane erection: foundation and base checks, mast section installation, climbing, slew unit, jib and counter-jib assembly, and counterweight placement
List the roles and responsibilities of the erection supervisor, riggers, and operator during erection and dismantling, and state who authorizes each step
Identify ground bearing and foundation requirements, including the need for a documented bearing capacity check and proper drainage
Explain the tie-in/anchor procedure and the checks performed before, during, and after climbing
Your checkpoint
A step-by-step erection and dismantling sequence diagram or table with responsible role and hold point at each step
Load charts, lifting plans, and capacity calculations & Tower crane setup, erection, and dismantling support
Recalculate capacity for a crane after a configuration change (jib length, reeving, or counterweight) and explain why the chart must be re-read
Produce a lifting plan for a tandem or critical lift, including load share calculation and communication protocol
Explain the purpose and content of the crane's documentation pack: load chart, manual, inspection records, and operator certification
Identify common causes of tower crane collapse or overload incidents and the control that prevents each
Your checkpoint
A revised lifting plan for a configuration-changed crane with recalculated capacity and a written list of at least six failure causes with matching controls
Occupational safety, health, and environmental regulations & Basic maintenance, troubleshooting, and shutdown procedures
Summarize the regulatory duties for crane operation, inspection intervals, and record keeping, and list the documents an operator must be able to produce on request
Describe the daily and periodic maintenance tasks within operator scope (lubrication points, rope inspection, brake check, limit switch test) and what must be escalated to a technician
Explain the out-of-service and shutdown procedure, including parking the crane, isolating power, and securing the jib in wind
Outline emergency response for power failure, brake failure, fire, and a load left suspended
Your checkpoint
A maintenance and shutdown checklist plus a one-page emergency response card covering four scenarios
Pre-operation inspection, rigging, and site preparation & Safe lifting operations and load control & Load charts, lifting plans, and capacity calculations
Complete a full timed mock assessment covering inspection, rigging, signal recall, and two capacity calculations, and score it against the pass criteria
Re-study your three weakest areas identified by the mock and write a short correction note for each
Deliver a complete, verbalized lifting operation from inspection through landing, as if examined, and self-assess against a rubric
Confirm exam-day logistics, permitted materials, and identification requirements
Your checkpoint
A scored mock assessment result with a remediation note for every missed item and a signed readiness statement
Milestones
Week 2: Can perform a full daily inspection walk-around and calculate sling leg tension at three angles without notes, scoring at least 90% on a self-made quiz
Week 4: Correctly extracts and deducts capacity for five load chart scenarios and produces a lifting plan that passes a 10-point checklist with no critical errors
Week 6: Explains erection and dismantling sequence with hold points, and recalculates capacity after a configuration change with full marks
Week 8: Scores at least 85% on the timed mock assessment with no critical safety errors in the verbalized lift