Architectural Design and Site Planning

  • Site analysis precedes design: record solar orientation, prevailing wind, topography, drainage, vegetation, noise sources, and access before fixing building form.

  • Solar geometry rule: in the northern hemisphere the sun is due south at solar noon; a south-facing facade receives maximum insolation at winter solstice and is easiest to shade at summer solstice.

  • Setback is the minimum horizontal distance from the property line to the building line; it is fixed by zoning bylaw, not by the architect.

  • Floor Area Ratio (FAR) = total gross floor area ÷ plot area; Coverage = footprint area ÷ plot area; both are capped by zoning.

  • Building height is measured per local bylaw - commonly to the mean roof level or to the top of the parapet, not to the highest point of a pitched roof.

  • Universal access: a 1:12 ramp slope is the usual maximum for unassisted wheelchair use; 1:20 or flatter is preferred where space permits.

  • Means-of-egress travel distance and dead-end corridor limits are set by the local building code; verify the governing edition before layout.

  • Cross-ventilation requires inlet and outlet openings on opposite or adjacent walls; single-sided ventilation is markedly less effective.

Quick reference

Building Construction

  • Concrete cover to reinforcement is specified by exposure class; cover protects against carbonation and chloride ingress, so it is a durability requirement, not a finish allowance.

  • Concrete cube strength is tested at 7 and 28 days; 28-day characteristic strength is the design value used in structural calculations.

  • Water-cement ratio governs both strength and permeability: lower w/c gives higher strength and lower permeability, offset by reduced workability.

  • Brick masonry in English bond alternates header and stretcher courses; Flemish bond alternates header and stretcher within each course.

  • Cavity walls require wall ties at spacing set by code and weep holes at the base of the outer leaf to drain moisture.

  • Damp-proof course (DPC) blocks rising moisture in walls; damp-proof membrane (DPM) performs the same role under a ground slab.

  • A lintel spans an opening and carries the load above it; the usual allowance is a 45-degree load triangle up to the lintel level.

  • Formwork striking times depend on member type and curing temperature; slabs and beams are struck later than vertical faces.

Quick reference

Materials and Structures

  • Bending moment for a simply supported beam under uniformly distributed load w over span L: M = wL²/8; maximum deflection for the same case: δ = 5wL⁴/(384EI).

  • Section modulus S = I/c; bending stress σ = M/S. Increasing depth raises I and S far faster than increasing width.

  • Slenderness ratio λ = effective length ÷ radius of gyration; buckling capacity falls as λ rises.

  • Euler buckling load P_cr = π²EI/(KL)², where K depends on end restraint (0.5 fixed-fixed, 0.7 fixed-pinned, 1.0 pinned-pinned, 2.0 cantilever).

  • Steel is strong in tension and compression but needs restraint against lateral-torsional buckling; concrete is strong in compression and weak in tension, hence reinforcement.

  • Thermal expansion must be accommodated with movement joints; the coefficient of thermal expansion of steel is roughly 12 × 10⁻⁶ per °C.

  • Timber strength depends on grain direction: parallel-to-grain strength is far higher than perpendicular; design values are modified for duration of load and moisture content.

  • Poisson's ratio relates lateral to axial strain; for concrete and steel it is approximately 0.2 and 0.3 respectively.

Quick reference

Building Services

  • Water supply pressure in a building falls with height and friction; a break tank and booster pump set are used where mains pressure is insufficient for the topmost outlets.

  • Plumbing traps retain a water seal (commonly 50-75 mm) to block sewer gas; the seal is lost by siphonage, evaporation, or back-pressure.

  • A vent pipe equalizes pressure in the drainage stack and prevents trap seal loss; it must terminate above roof level.

  • Electrical: total connected load is summed with diversity applied to derive maximum demand; protective device rating must not exceed cable current-carrying capacity.

  • Earthing and residual-current protection are separate safeguards: earthing provides a fault path, RCD detects imbalance and disconnects.

  • Lift traffic design uses handling capacity and interval; a common design target is to move a set percentage of the building population in five minutes.

  • Fire detection zones should broadly follow floor plates so that a fire alarm indicates a searchable area, not an entire tower.

  • HVAC duct sizing by equal friction method keeps static pressure loss per unit length constant along the main run.

Quick reference

Environmental Control and Sustainability

  • Thermal transmittance U is the reciprocal of total thermal resistance: U = 1/R_total; lower U means better insulation.

  • Psychrometric chart: dry-bulb temperature on the horizontal axis, moisture content on the vertical; comfort zone lies between them, bounded by humidity limits.

  • Effective temperature combines dry-bulb, humidity, and air movement into a single comfort index.

  • Passive design priority: reduce load first (orientation, shading, insulation), then size systems - never size plant before load reduction.

  • Daylight factor = internal illuminance ÷ simultaneous external horizontal illuminance under overcast sky, expressed as a percentage.

  • Embodied carbon is the emissions associated with materials and construction; operational carbon is emissions during use. Whole-life carbon sums both.

  • Rainwater harvesting sizing depends on catchment area, rainfall depth, and demand; storage volume is set by the dry-period demand, not annual rainfall.

  • Green roof benefits include stormwater attenuation, reduced heat island effect, and additional insulation, but require structural load allowance for saturated soil.

Quick reference

Professional Practice

  • The architect's standard scope covers design, production information, and periodic site inspection; full-time supervision is a separate service and must be agreed in writing.

  • Fees are commonly computed as a percentage of construction cost, as a lump sum, or on a time basis; the basis and stage payments belong in the appointment agreement.

  • Professional indemnity insurance covers negligent acts, errors, and omissions in the professional service; it does not cover construction defects caused by the contractor.

  • Architect's instruction is the formal mechanism to vary the works; oral instructions should be confirmed in writing within the contract's stated period.

  • A certificate of practical completion transfers risk and possession to the client and starts the defects liability period.

  • Retention is a percentage withheld from each payment, commonly released in two parts: at practical completion and at the end of the defects period.

  • Copyright in the drawings generally remains with the architect; the client receives a licence for the purposes stated in the appointment.

  • Conflict of interest must be declared and managed in writing; acting for both client and contractor on the same project is normally prohibited.

Quick reference

Ethics and Regulations

  • Registration to practise is personal and non-transferable; practising without current registration is an offence under the governing architects' act.

  • The architect's paramount duty is to the public's health, safety, and welfare, which outranks commercial loyalty to the client.

  • Building permit submission typically requires drawings, structural calculations, and a site plan demonstrating compliance with zoning and building code.

  • A certificate of occupancy or completion is issued by the authority after inspection; occupation before it is unlawful.

  • Fire safety design rests on three pillars: means of escape, fire resistance of structure, and control of fire spread - plus access for firefighting.

  • Confidential client information may not be disclosed without consent except where required by law or where safety is at risk.

  • Signing or certifying work that the architect has not personally directed or reviewed is a disciplinary offence.

  • Professional conduct rules generally prohibit misleading advertising, fee undercutting by unsafe scope reduction, and undisclosed commissions from suppliers.

Quick reference

Urban Design

  • Urban design operates at the scale between architecture and town planning: block form, street enclosure, public realm, and frontage.

  • Enclosure ratio = building height ÷ street width; ratios around 1:1 to 1:3 produce a comfortable sense of street enclosure.

  • Active frontages place doors, windows, and shopfronts at ground level; blank walls and car parks at grade kill street life.

  • Permeability is measured by the number of route choices; connectivity and cul-de-sac layouts trade off against each other.

  • Transit-oriented development clusters higher density within a walkable radius (commonly 400-800 m) of a station.

  • Legibility, after Kevin Lynch, rests on paths, edges, districts, nodes, and landmarks as the mental image of a city.

  • Eyes on the street (Jane Jacobs) links natural surveillance to safety: overlooking windows and foot traffic deter crime.

  • Universal design in public space covers level changes, tactile paving, seating intervals, and shade along pedestrian routes.

Quick reference

Town Planning and Housing

  • Zoning separates land uses and sets permitted use, density, height, setback, and parking requirements for each zone.

  • Density is expressed as dwelling units per hectare or as plot ratio; both must be checked against the zoning bylaw, not estimated.

  • Land subdivision requires a layout plan showing roads, plots, open space, and services; approval precedes sale of plots.

  • Housing typology ranges from detached and semi-detached through terraced and walk-up flats to high-rise apartments; each has different net-to-gross efficiency.

  • Net residential density counts only residential land; gross density includes roads, open space, and community facilities.

  • Affordable housing obligations are commonly met through inclusionary zoning: a set percentage of units in a development.

  • Master plans are strategic and indicative; zoning or development control regulations are the legally binding instrument.

  • Public participation in plan-making is usually a statutory requirement, with objections heard at an inquiry or hearing stage.

Quick reference

Project Management

  • Critical path method: the critical path is the longest duration path through the network; any delay on it delays completion.

  • Total float = latest finish − earliest finish; float is zero on the critical path and positive elsewhere.

  • Gantt charts show time but not logical dependency; network diagrams show dependency and are used for float analysis.

  • Earned value: CV = EV − AC (cost variance), SV = EV − PV (schedule variance), CPI = EV/AC, SPI = EV/PV.

  • A work breakdown structure decomposes scope into manageable packages; each package should be assignable to one responsible party.

  • Fast-tracking overlaps design and construction to compress time; crashing adds resources to critical activities at extra cost.

  • Design coordination clashes are resolved through a common data environment and federated models before construction information is issued.

  • Risk register records likelihood, impact, owner, and mitigation; risk allocation should follow the party best able to control it.

Quick reference

Contracts and Costing

  • Lump-sum contract fixes price for defined scope; any change is a variation. Re-measurement contracts pay for actual quantities at agreed rates.

  • Bills of quantities are prepared from drawings and measured to a standard method of measurement; they form the basis for tendering.

  • Approximate quantities estimate uses rates per unit of floor area or per bed space and is used only at feasibility stage.

  • Cost plan stages follow design stages: order-of-cost, elemental, and detailed - accuracy improves as design information grows.

  • Variation valuation order: contract rate applies if work is similar; a fair rate is derived if not; dayworks apply for small unforeseen work.

  • Liquidated and ascertained damages are a pre-estimate of the client's loss for delay, not a penalty; they must be genuine.

  • Interim payments are certified at intervals; the certificate is the architect's independent valuation, not the contractor's claim.

  • Final account reconciles the contract sum with all variations, provisional sums, and adjustments after the defects period.