PCATP ALE key terms
PCATP ALE · Get comfortable with the vocabulary.
- Setback
- Related: Floor Area Ratio, Building Line
The minimum horizontal distance a building must be kept from a property line, street edge, or other boundary, fixed by zoning rules to protect light, air, privacy, and fire access.
- Floor Area Ratio (FAR)
- Related: Setback, Ground Coverage
The ratio of a building's total covered floor area to the area of the plot on which it stands. Regulators use it to cap development bulk independently of plot size.
- Ground Coverage
- Related: Floor Area Ratio (FAR), Setback
The percentage of a plot that may be covered by a building footprint when viewed from above. It controls open space and daylight at ground level rather than total built volume.
- Building Line
- Related: Setback, Right of Way
A line drawn on a development plan beyond which no structure may project toward the street. It may sit behind the property line and differs from the setback in being a fixed control line.
- Right of Way (ROW)
- Related: Building Line, Easement
The strip of land reserved for a road, footpath, or utility corridor, measured between property lines. Its width sets the space available for carriageway, verges, and services.
- Easement
- Related: Right of Way, Title Deed
A legal right to use another person's land for a specific limited purpose, such as drainage, access, or running services, without owning it. It binds later owners of the land.
- Title Deed
- Related: Easement, Mutation
The registered legal document proving ownership of land or property and recording the owner's name and the rights and encumbrances attached to it. It is the basis for verifying ownership before purchase.
- Mutation
- Related: Title Deed, Land Use Zoning
The official updating of land revenue or ownership records after a sale, inheritance, or gift so that the register names the current owner. It transfers record entries, not title itself.
- Land Use Zoning
- Related: Ground Coverage, Mutation
The division of land by a planning authority into districts with permitted uses, such as residential, commercial, industrial, or agricultural, together with density and height controls. It directs growth and separates incompatible activities.
- Master Plan
- Related: Land Use Zoning, Urban Renewal
A long-range statutory or policy document that sets the broad pattern of land use, transport, housing, and services for a town over roughly twenty years, guiding detailed local plans and development approvals.
- Urban Renewal
- Related: Master Plan, Adaptive Reuse
The planned redevelopment or rehabilitation of deteriorated urban areas through clearance, upgrading, or adaptive reuse, usually combined with improved infrastructure and relocation of affected residents.
- Adaptive Reuse
- Related: Urban Renewal, Embodied Carbon
Giving a new use to an existing building while retaining its significant structure or character, such as converting a warehouse into housing. It reduces demolition waste and often preserves heritage value.
- Embodied Carbon
- Related: Life Cycle Assessment, Adaptive Reuse
The total greenhouse gas emissions associated with extracting, manufacturing, transporting, installing, maintaining, and disposing of building materials over a building's life. It excludes emissions from operating the building.
- Life Cycle Assessment (LCA)
- Related: Embodied Carbon, Thermal Transmittance
A structured method of estimating environmental impacts of a building or material across its whole life, from raw material extraction through use to end of life, usually reported per functional unit.
- Thermal Transmittance (U-value)
- Related: Life Cycle Assessment (LCA), Passive Design
A measure of how readily heat passes through a building element, expressed in watts per square metre per kelvin. Lower values mean better insulation and are capped by energy codes.
- Passive Design
- Related: Thermal Transmittance (U-value), Daylight Factor
Design that uses orientation, shading, mass, insulation, and natural ventilation to keep indoor conditions comfortable with minimal mechanical energy. It is decided early, since later changes are costly.
- Daylight Factor
- Related: Passive Design, Glare
The ratio of illuminance at a point indoors to the simultaneous illuminance on an unobstructed outdoor horizontal surface, expressed as a percentage under overcast sky conditions. It indicates how well a space is naturally lit.
- Glare
- Related: Daylight Factor, Coefficient of Performance
Visual discomfort or loss of detail caused by luminance within the field of view far brighter than the surroundings, or by excessive contrast. It is controlled by shading, diffusing, and limiting brightness ratios.
- Coefficient of Performance (COP)
- Related: Glare, Rainwater Harvesting
The ratio of useful heating or cooling delivered by a heat pump or chiller to the energy it consumes, measured at stated conditions. Higher values indicate more efficient equipment.
- Rainwater Harvesting
- Related: Coefficient of Performance (COP), Fire Resistance Rating
The collection, storage, and use of rainwater from roofs or other surfaces for non-potable needs or groundwater recharge, reducing demand on mains supply and stormwater runoff.
- Fire Resistance Rating
- Related: Compartmentation, Means of Escape
The period, in minutes or hours, for which a building element resists fire exposure while retaining stability, integrity, and insulation, as established by standard fire testing. It governs compartmentation and escape protection.
- Compartmentation
- Related: Fire Resistance Rating, Means of Escape
The subdivision of a building into fire-tight zones by rated walls, floors, and doors so that fire and smoke are held in the zone of origin long enough for occupants to escape.
- Means of Escape
- Related: Compartmentation, Occupant Load
The continuous protected route from any point in a building to a place of safety outside, made up of exit access, exits, and discharge, sized for the occupant load it serves.
- Occupant Load
- Related: Means of Escape, Sanitary Fixture Ratio
The number of people a floor, room, or building is expected to hold, calculated from floor area and use type. It sets exit widths, stair numbers, and sanitary fixture counts.
- Sanitary Fixture Ratio
- Related: Occupant Load, Plumbing Stack
The required number of water closets, washbasins, and other fittings per number of occupants or floor area for a given building use, set by building bye-laws to ensure adequate provision.
- Plumbing Stack
- Related: Sanitary Fixture Ratio, Rainwater Harvesting
A vertical pipe carrying soil or waste water down through a building to the drainage system, usually vented to maintain air pressure and protect trap seals.
- Slump Test
- Related: Water-Cement Ratio, Cube Test
A field test in which fresh concrete placed in a standard cone is allowed to settle, and the drop of the top is measured to indicate workability and consistency before placing.
- Water-Cement Ratio
- Related: Slump Test, Cube Test
The mass of water divided by the mass of cement in a concrete mix. Lowering it raises strength and durability but reduces workability, so it is balanced against admixtures.
- Cube Test
- Related: Slump Test, Water-Cement Ratio
A laboratory compression test on standard concrete cubes cured for set periods, usually 7 and 28 days, to confirm that the mix achieves its specified characteristic strength.
- Bending Moment
- Related: Shear Force, Effective Span
The internal turning effect at a section of a beam or slab caused by loads acting at a distance, producing tension on one face and compression on the other. It governs reinforcement placement.
- Shear Force
- Related: Bending Moment, Effective Span
The internal force acting across a section of a structural member that tends to slide one part past another. It produces diagonal tension, resisted by stirrups or shear reinforcement.
- Effective Span
- Related: Bending Moment, Shear Force
The distance between the supports of a beam or slab used in structural calculations, taken between centre lines of supports or clear span plus effective depth, whichever is smaller.
- Bill of Quantities (BOQ)
- Related: Measurement Standard, Retention Money
An itemized schedule listing measured quantities of work with descriptions, prepared from drawings so that tenderers price the same scope on a common basis for comparison.
- Measurement Standard
- Related: Bill of Quantities (BOQ), Variation Order
A published set of rules for how building work is measured and described, such as which deductions apply to openings, so that quantities in a bill are consistent and checkable.
- Variation Order
- Related: Bill of Quantities (BOQ), Retention Money
A written instruction issued under a contract authorizing a change to the scope, quantity, or timing of work, with its cost and time effects valued under the contract's variation provisions.
- Retention Money
- Related: Variation Order, Defects Liability Period
A percentage withheld from interim payments and held by the employer as security for defects, released in stages, commonly half at practical completion and the balance after the defects liability period.
- Defects Liability Period
- Related: Retention Money, Practical Completion
A stated period after practical completion during which the contractor must return and rectify defects notified by the employer at no extra cost, before final payment and release of retention.
- Practical Completion
- Related: Defects Liability Period, Retention Money
The stage at which the works are substantially finished and fit for their intended use, apart from minor items, triggering handover, the defects period, and release of part retention.
- Professional Indemnity Insurance
- Related: Conflict of Interest, Duty of Care
Cover protecting an architect against claims for financial loss arising from negligent design, advice, or certification, usually written on a claims-made basis with a stated retroactive date.
- Conflict of Interest
- Related: Professional Indemnity Insurance, Duty of Care
A situation where a professional's personal, financial, or other interest could improperly influence judgement on a client's project, requiring disclosure and often withdrawal from the decision.
- Duty of Care
- Related: Professional Indemnity Insurance, Conflict of Interest
The legal obligation of a professional to exercise reasonable skill and care toward those who may foreseeably be harmed by the work, including clients and, in some cases, later users.