PMI-SP · Get comfortable with the vocabulary.

Schedule Strategy

The high-level approach an organization chooses for building, maintaining, and using project schedules, covering the selected method, tools, level of detail, review cadence, and governance expectations.

Related: Scheduling Method, Schedule Governance, Schedule Management Plan
Scheduling Method

The specific technique or rule set, such as critical path method or critical chain, used to calculate activity dates and float inside a schedule model.

Related: Schedule Strategy, Critical Path Method, Schedule Model
Schedule Management Plan

A document that defines how the schedule will be developed, monitored, controlled, and communicated, including formats, roles, thresholds, and reporting frequency.

Related: Schedule Strategy, Schedule Baseline, Communications Management Plan
Schedule Governance

The roles, decision rights, review gates, and audit practices an organization uses to approve, change, and assure the quality of project schedules.

Related: Schedule Strategy, Schedule Change Control, Schedule Health Check
Enterprise Environmental Factors

Conditions outside the project team's control, such as organizational culture, market conditions, and available software, that influence how a schedule is built and used.

Related: Organizational Process Assets, Scheduling Method
Organizational Process Assets

The organization's stored knowledge and standard processes, including templates, historical schedules, policies, and lessons learned, that shape scheduling decisions.

Related: Enterprise Environmental Factors, Lessons Learned
Schedule Model

A dynamic representation of the project plan that combines activities, logic, durations, resources, and calendars, and which yields calculated dates and float when processed by a scheduling tool.

Related: Scheduling Method, Schedule Baseline, Critical Path Method
Critical Path Method

A scheduling technique that calculates early and late dates for every activity and identifies the longest path through the network, which sets the shortest possible project duration.

Related: Total Float, Forward Pass, Backward Pass
Critical Chain Method

A scheduling technique that removes float from individual activities and aggregates it into buffers that protect the project completion date from uncertainty and resource contention.

Related: Critical Path Method, Schedule Model
Precedence Diagramming Method

A technique for building a network of activities drawn as nodes connected by arrows that show logical relationships, supporting several relationship types and lags.

Related: Lag, Schedule Model
Lag

A planned waiting period inserted between a predecessor and a successor activity to reflect a real constraint, such as curing time or a required approval.

Related: Precedence Diagramming Method, Schedule Model
Milestone

A significant point or event in the project that has zero duration and marks completion of a deliverable, an approval, or a phase boundary.

Related: Schedule Model, Schedule Baseline
Rolling Wave Planning

An iterative planning approach in which near-term work is scheduled in detail while more distant work stays at a summary level until better information becomes available.

Related: Schedule Model, Milestone
Schedule Baseline

The approved version of the schedule model against which actual progress and performance are compared, changed only through formal change control.

Related: Schedule Change Control, Performance Measurement Baseline
Total Float

The amount of time an activity can be delayed from its early dates without delaying the project finish date.

Related: Free Float, Critical Path Method
Free Float

The amount of time an activity can be delayed without delaying the early start of any of its successors.

Related: Total Float, Forward Pass
Forward Pass

A network calculation that moves from project start toward project finish to establish early start and early finish dates for each activity.

Related: Backward Pass, Total Float
Backward Pass

A network calculation that moves from project finish toward project start to establish late finish and late start dates, from which float values are derived.

Related: Forward Pass, Total Float
Resource Leveling

A technique that adjusts start and finish dates to resolve resource over-allocation or to respect resource limits, which frequently extends the project duration.

Related: Critical Path Method, Schedule Model
Fast Tracking

A schedule compression technique that overlaps activities normally done in sequence, shortening duration but increasing the risk of rework and coordination problems.

Related: Crashing, Critical Path Method
Crashing

A schedule compression technique that adds resources, overtime, or extra shifts to critical path activities to shorten duration, usually at additional cost.

Related: Fast Tracking, Critical Path Method
Schedule Variance

A measure of schedule performance calculated as earned value minus planned value, showing in cost terms whether work is ahead of or behind the plan.

Related: Schedule Performance Index, Variance Analysis
Schedule Performance Index

Earned value divided by planned value, expressing how efficiently schedule work is being accomplished; a result below one indicates slower than planned progress.

Related: Schedule Variance, Schedule Forecast
Performance Measurement Baseline

The approved, time-phased scope, schedule, and budget against which project execution is measured, formed from the scope, schedule, and cost baselines.

Related: Schedule Baseline, Schedule Variance
Variance Analysis

Comparing planned dates, durations, or work content with actual results to understand why performance deviated and to decide whether corrective action is needed.

Related: Schedule Variance, Schedule Forecast
Schedule Forecast

An estimate of future activity dates or the project completion date, derived from current progress, remaining work, and expected performance.

Related: Data Date, Schedule Performance Index, Variance Analysis
Data Date

The point in time at which the schedule's status is recorded, separating work already performed from work still planned.

Related: Schedule Forecast, Out-of-Sequence Progress
Out-of-Sequence Progress

A condition in which an activity reports progress or completion before its predecessor has finished, which can distort float values and forecasts if left unresolved.

Related: Data Date, Schedule Health Check
Schedule Change Control

The formal process for reviewing, approving, documenting, and communicating modifications to the schedule baseline or to approved schedule data.

Related: Schedule Baseline, Schedule Governance, Re-baselining
Schedule Health Check

A structured review of a schedule model's quality attributes, such as logic links, missing durations, excessive constraints, and float distribution, to confirm the forecast can be trusted.

Related: Schedule Governance, Out-of-Sequence Progress
Re-baselining

The formally authorized replacement of the schedule baseline, usually after a significant scope or strategy change, and used only with proper approval.

Related: Schedule Baseline, Schedule Change Control
Schedule Closeout

The process of finalizing the schedule at project or phase end, confirming all activities are complete or transferred, and archiving records for future use.

Related: As-Built Schedule, Lessons Learned
As-Built Schedule

A record version of the schedule that shows the actual dates and sequence in which work was performed, kept for analysis and historical reference.

Related: Schedule Closeout, Lessons Learned
Lessons Learned

Documented insights about scheduling practices that helped or hindered the project, captured so future teams can repeat successes and avoid mistakes.

Related: Organizational Process Assets, Schedule Closeout
Stakeholder Register

A record identifying project stakeholders along with their interests, influence, and information needs, used to decide who receives which schedule information.

Related: Communications Management Plan, Schedule Dashboard
Communications Management Plan

A document that defines who receives schedule information, in what format, how often, and through which channel, including escalation paths for schedule issues.

Related: Stakeholder Register, Schedule Narrative, Schedule Management Plan
Schedule Narrative

A written summary that accompanies a schedule report and explains major changes, variances, assumptions, and upcoming risks in plain language for readers.

Related: Schedule Dashboard, Variance Analysis
Schedule Dashboard

A visual summary of key schedule metrics and status indicators, designed so executives and other stakeholders can grasp schedule health quickly.

Related: Schedule Narrative, Stakeholder Register
Schedule Review Meeting

A recurring session where the project team and stakeholders examine current schedule status, discuss variances and risks, and agree on actions and updates.

Related: Schedule Narrative, Schedule Change Control