Warehouse Expansion With an Unclear WBS
You are the project manager for an 18-month, $8.5M warehouse expansion of 120,000 square feet. The WBS was developed by the general contractor and omits site utility relocation, which is now on the critical path. A permit delay has consumed 10 days of the 15-day schedule contingency, and the cost baseline shows 12% of contingency used at 30% physical completion. The client requests a change to add a second loading dock, estimated at $350,000 and six weeks of work. The sponsor wants to 'make it happen' without extending the completion date. The contractor has offered to fast-track electrical and HVAC work, but those activities currently have a finish-to-start dependency and a two-week lag for inspection. You have a change control board meeting in five days.
1. Evaluate the WBS omission and its implications for the scope, schedule, and cost baselines. Recommend corrective action.
Read the worked answer
The WBS is incomplete because site utility relocation is missing. That is not a minor planning oversight; it is scope that must be performed and is now on the critical path. The implications are serious: the scope baseline does not reflect all required work, the schedule baseline is invalid because a critical activity is absent, and the cost baseline may understate the true budget. The permit delay consuming 10 of 15 schedule contingency days also shows the contingency was sized without this risk.
Corrective action should be deliberate:
- Perform a WBS completeness review with the contractor, client, and key trades, using a checklist of site works, permits, utilities, and commissioning.
- Add utility relocation as a work package with dependencies, duration, cost, and acceptance criteria.
- Route the change through the change control board: impact analysis on scope, schedule, cost, quality, and risk; then update baselines only if approved.
- Revisit the risk register to add utility and permit risks, and reassess remaining contingency.
The project manager should not simply absorb the omission into existing contingency without documenting it. That would hide a baseline defect and reduce transparency for the sponsor.
2. The sponsor demands no schedule extension for the added loading dock. Analyze at least two schedule compression options and recommend one with justification.
Read the worked answer
The added dock requires $350,000 and six weeks, while only five days of schedule float remain before the current completion date. The sponsor's demand must be tested against schedule reality.
Option 1: Fast-track electrical and HVAC work. The contractor proposes overlapping activities that currently have a finish-to-start dependency and a two-week inspection lag. This can compress the schedule, but it increases rework risk and may create inspection conflicts. If inspection is mandatory before the next activity, removing the lag without an approved alternative is risky.
Option 2: Crash the dock work by adding resources or shifts. This could shorten the six-week duration, but it adds cost and may be constrained by site access and trade availability. It is more controllable than eliminating inspection lags.
Recommendation: Combine targeted crashing on the dock's critical activities with limited fast-tracking only where the inspection authority agrees to a phased inspection. Do not promise the original date without a schedule risk analysis showing the probability of completion. Present the sponsor with three choices: accept a revised date, approve additional funding for crashing, or defer a lower-priority scope item. The project manager should not simply agree to an impossible constraint.
3. Interpret the contingency usage and propose how to update cost forecasts, including the change control steps for the loading dock.
Read the worked answer
Using 12% of contingency at 30% physical completion is a warning sign, especially with the utility omission now on the critical path. Contingency is being consumed faster than work is being completed, which suggests the original estimate missed known work or that risks are materializing early. The remaining contingency may be insufficient for the loading dock, permit delays, and normal completion risks.
To update forecasts, I would calculate an independent estimate at completion using actual costs plus a revised estimate for remaining work, including utility relocation and the dock. Compare this with earned value indicators, but do not rely on a single index. Then prepare a change request for the dock with cost, schedule, quality, and risk impacts.
The change control steps are: submit the request with the impact analysis; review at the change control board; obtain a decision on funding and schedule; if approved, update the cost and schedule baselines and communicate the change. If not approved, document the rejection and continue against the existing baseline. The forecast should also show the remaining contingency separately so the sponsor can see the exposure rather than a single blended number.