Project vs. operations
A project is a temporary, unique endeavor producing a specific result; operations are ongoing and repetitive. The temporary and unique criteria distinguish projects from routine operational work.
Triple constraint
Scope, time, and cost are interdependent; adjusting one forces compensating changes in at least one other, with quality as the resulting outcome. This shapes all trade-off decisions.
Projectized organization
An organizational structure in which the project manager has full authority over the project and team members report directly to the PM, often co-located, maximizing PM control.
Directive PMO
A project management office type that exercises high control: project managers report to the PMO and the PMO manages projects directly, unlike supportive or controlling PMOs.
Program vs. portfolio
A program groups related projects managed together for shared benefits; a portfolio is a collection of projects and programs selected to achieve strategic organizational objectives.
Project charter
The document that formally authorizes the project and the project manager, issued by the sponsor, containing purpose, measurable objectives, high-level scope, risks, milestones, budget, and authority.
Business case
The document justifying the project investment through cost-benefit analysis, ROI, payback, and strategic alignment. It precedes the charter and is owned by the sponsor.
Assumption log
A project document recording unverified beliefs treated as true for planning purposes. If an assumption proves false, it is typically transferred to the issue log.
Stakeholder register
A document identifying stakeholders with their roles, requirements, expectations, influence, and interest, used to plan engagement and communication approaches for each group.
Power/interest grid
A stakeholder classification tool: high power and high interest are managed closely; high power and low interest are kept satisfied; low power and high interest are kept informed; low/low are monitored.
Engagement assessment matrix
A tool recording each stakeholder's current and desired engagement level across unaware, resistant, neutral, supportive, and leading, highlighting gaps that the engagement plan must close.
Work package
The lowest level of the work breakdown structure, where cost and duration can be reliably estimated and managed; the 8/80 heuristic is a common sizing guide.
Scope creep
Uncontrolled expansion of project scope without approved change control, which erodes schedule and budget; gold plating is a related failure of adding unrequested features.
Critical path
The longest path through the project network, determining the shortest possible project duration. Its total float is zero, so any delay on it delays the whole project.
Total float formula
Total float equals late start minus early start, or late finish minus early finish. It is the schedule flexibility an activity has without delaying the project finish date.
PERT expected duration
Expected duration equals (Optimistic + 4 × Most Likely + Pessimistic) divided by 6; standard deviation equals (Pessimistic − Optimistic) divided by 6, quantifying estimate uncertainty.
Cost performance index
CPI equals earned value divided by actual cost. A value above 1.0 means the project is under budget; below 1.0 means it is over budget for work performed.
Estimate at completion
EAC forecasts total project cost. Using BAC divided by CPI assumes current cost performance continues; ETC equals EAC minus actual cost; VAC equals BAC minus EAC.
Cost of quality
The total cost of conformance (prevention and appraisal) plus nonconformance (internal and external failure). Rework is classified as an internal failure cost.
Risk response strategies
For threats: avoid, transfer, mitigate, escalate, accept. For opportunities: exploit, share, enhance, escalate, accept. Each risk in the register gets an owner and response.
Risk score
A risk register value calculated as probability multiplied by impact, used to rank risks during qualitative analysis and prioritize which risks receive detailed response planning.
Fixed-price contract
A contract type in which the seller bears the cost risk because the price is set; variants include firm-fixed-price, fixed-price with economic price adjustment, and fixed-price incentive fee.
Cost-reimbursable contract
A contract type in which the buyer bears cost risk because the seller is reimbursed allowable costs; variants include cost plus fixed fee, incentive fee, and award fee.
RFP vs. RFQ
A request for proposal asks sellers to propose a solution or approach for complex needs; a request for quotation asks for price on a well-defined item with clear specifications.
Integrated change control
The process of reviewing every change request in writing, analyzing impacts across scope, schedule, cost, quality, and risk, obtaining approval, then updating baselines and logs.
Configuration management
A control process ensuring the correct versions of documents and deliverables are identified, tracked, and approved, preventing unauthorized or outdated versions from being used.
Corrective vs. preventive action
Corrective action realigns future performance after a deviation occurs; preventive action reduces the probability of a future deviation. Defect repair fixes nonconforming product already produced.
Conflict resolution modes
Problem solving (confronting) seeks a win-win outcome and is preferred; forcing, avoiding, accommodating, and compromising are alternatives depending on context and stakes.
Pareto and fishbone
A Pareto chart ranks causes to highlight the vital few contributing most problems; a fishbone (cause-and-effect) diagram organizes possible root causes into categories for analysis.
Lessons learned
Knowledge captured throughout the project about what worked and what did not, archived as organizational process assets to improve future project performance.
Benefits realization
The process of tracking whether expected benefits defined in the business case are actually achieved after project closure, often managed at program or portfolio level.
Post-implementation review
A review conducted at defined intervals after go-live comparing realized benefits and outcomes against the business case, identifying gaps and follow-up actions for the organization.