PRINCE2 7 Foundation study materials
PRINCE2 7 Foundation study resources

PRINCE2 7 Foundation cheat sheet

PRINCE2 7 Foundation · Keep the key ideas within reach.

Quick reference

Projects and the PRINCE2 project context

  • A project is a temporary organization created to deliver one or more business products according to an agreed business case.

  • Projects are characterized by change, temporary duration, uniqueness, cross-functional involvement and uncertainty.

  • Business as usual is ongoing operational work that maintains existing products and services; projects deliver change and then hand over.

  • PRINCE2 integrates principles, people, practices and processes, and it is tailored to the project context.

  • Project context includes organizational strategy, governance, stakeholder expectations, constraints, delivery approach, risk and scale.

  • PRINCE2 recognizes business, user and supplier stakeholder interests; the business case should balance them.

  • Project management is planning, delegating, monitoring and controlling all aspects of the project and motivating those involved to achieve objectives.

  • A project's objectives cover time, cost, quality, scope, benefits and risk; tolerances are set for these.

Quick reference

PRINCE2 principles

  • PRINCE2 has seven principles: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, and tailor to suit the project environment.

  • Principles are universal, self-validating and empowering; they must be applied for a project to be managed according to PRINCE2.

  • Continued business justification requires a justifiable reason to start and evidence that the project remains justified.

  • Learn from experience requires lessons to be sought, recorded and acted upon throughout the project.

  • Defined roles and responsibilities require roles, responsibilities and relationships to be agreed and understood.

  • Manage by stages requires at least two management stages: an initiation stage and at least one further stage.

  • Manage by exception sets tolerances for objectives and escalates only when forecast performance exceeds delegated limits.

  • Focus on products requires products, quality criteria and acceptance criteria to be defined before work is authorized.

  • Tailor to suit the project environment adapts the method to scale, complexity, risk and organizational context.

Quick reference

People

  • People is a PRINCE2 element that addresses behaviours, relationships and communication in projects.

  • Effective stakeholder collaboration includes identifying stakeholders, analysing interests and influence, planning engagement and maintaining communication.

  • Communication planning defines audiences, information needs, timing, channels, responsibilities and feedback mechanisms.

  • Project leadership creates purpose, builds trust, supports collaboration and enables accountability.

  • Emotional intelligence supports self-awareness, empathy and relationship management in project teams.

  • Change affects people; successful change requires clear purpose, engagement and support for those affected.

  • Team effectiveness depends on clear roles, shared objectives, appropriate skills and constructive working relationships.

  • Culture, values and behaviour influence how teams communicate, make decisions and respond to change.

Quick reference

PRINCE2 practices

  • The seven practices are business case, organizing, plans, quality, risk, issues and progress.

  • Business case practice judges whether the project is desirable, viable and achievable and keeps the business case updated.

  • Organizing practice defines roles, responsibilities, accountability and relationships, including project board and team roles.

  • Plans practice provides project, stage and team plans; product-based planning defines products before activities.

  • Quality practice covers quality planning, quality control and quality assurance, using product descriptions and a quality register.

  • Risk practice uses a risk management approach, risk register, risk appetite, tolerances and responses to threats and opportunities.

  • Issues practice manages requests for change, off-specifications and problems through an issue register and change control.

  • Progress practice uses tolerances, checkpoints, highlight reports, end stage assessments and exception reports.

  • Practices are tailored to the project; management products can be combined or simplified if the principles are maintained.

Quick reference

PRINCE2 processes

  • PRINCE2 has seven processes: starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing a stage boundary and closing a project.

  • Starting up a project ensures prerequisites, appoints the project board and project manager, captures lessons and prepares the project brief.

  • Directing a project enables the project board to authorize initiation, the project, stage or exception plans and closure.

  • Initiating a project establishes baselines and management approaches and prepares the project initiation documentation.

  • Controlling a stage authorizes work packages, monitors progress, manages issues and risks, and escalates exceptions.

  • Managing product delivery covers accepting, executing and delivering work packages to agreed quality criteria.

  • Managing a stage boundary reviews the stage, updates the project plan and business case, and prepares the next stage plan.

  • Closing a project confirms product acceptance, reviews benefits and lessons, and prepares handover and closure.

  • Process activities transform inputs into outputs; they can be tailored, but the principles must still be applied.

Quick reference

Tailoring PRINCE2 to the project environment

  • Tailoring is the PRINCE2 principle that adapts the method to the project environment.

  • Tailoring considers scale, complexity, risk, duration, organizational standards, stakeholders and delivery approach.

  • Tailoring may change practices, processes, roles, terminology and management products.

  • Tailoring must not remove or weaken any of the seven PRINCE2 principles.

  • Management products can be combined, simplified or adapted; the project records which products are required.

  • Roles can be combined or shared in smaller projects, but accountability and project board responsibilities remain.

  • Tailoring decisions are documented, agreed by the project board and reflected in the project initiation documentation.

  • Agile delivery can be tailored with timeboxes, prioritized requirements and iterative development while retaining PRINCE2 governance.