PRINCE2 7 Foundation study materials
PRINCE2 7 Foundation study resources

PRINCE2 7 Foundation flashcards

PRINCE2 7 Foundation · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project definition
A project is a temporary organization created to deliver one or more business products according to an agreed business case, and it introduces change.
Project versus business as usual
Projects are temporary and deliver change, while business as usual is ongoing operational work that maintains existing products and services.
PRINCE2 method structure
PRINCE2 integrates principles, people, practices and processes; it is a flexible method tailored to the project context rather than a rigid sequence of prescribed tasks.
Project context factors
Project context includes organizational strategy, governance, stakeholders, constraints, delivery approach, risk, scale and the external environment in which the project operates.
Continued business justification
A PRINCE2 principle requiring a project to have a justifiable reason to start and to remain justified throughout, with the business case reviewed and updated.
Learn from experience principle
A PRINCE2 principle requiring lessons to be sought, recorded and acted upon throughout the project, not only at closure, to improve performance.
Defined roles principle
A PRINCE2 principle requiring roles, responsibilities and relationships to be defined and agreed so that accountability and decision-making are clear.
Manage by exception
A PRINCE2 principle where tolerances are set for objectives and management action is taken only when a forecast exceeds those delegated limits.
Focus on products
A PRINCE2 principle requiring the project to define and agree products, their quality criteria and acceptance criteria before work is authorized.
PRINCE2 People element
The People element addresses behaviours, relationships and communication needed to lead change, lead teams and collaborate with stakeholders throughout a project.
Stakeholder collaboration
Collaborating with stakeholders involves identifying them, understanding their interests and influence, planning engagement and maintaining communication appropriate to their needs.
Team leadership
Project leadership creates a clear purpose, builds trust, supports collaboration and enables people to take responsibility for delivering agreed products and outcomes.
Communication planning
Communication planning defines what information each audience needs, when and how it will be provided, and how feedback will be obtained and handled.
Emotional intelligence
Emotional intelligence is the ability to recognize and manage one's own emotions and understand others' feelings, supporting constructive relationships and effective stakeholder engagement.
Business case practice
The business case practice establishes mechanisms to judge whether the project is desirable, viable and achievable, and to keep the business case updated.
Organizing practice
The organizing practice defines the project's roles, responsibilities, accountability and relationships, including the project board, project manager and team roles.
Plans practice
The plans practice provides a common framework for planning at project, stage and team levels, including product-based planning and exception plans when tolerances are forecast to be exceeded.
Quality practice
The quality practice defines quality planning, quality control and quality assurance, using product descriptions, quality criteria, reviews and a quality register.
Risk practice
The risk practice manages uncertainty through a risk management approach, risk register, risk appetite and tolerance, and planned responses to threats and opportunities.
Issues practice
The issues practice captures and manages requests for change, off-specifications and problems, using an issue register, issue reports and change control.
Starting up a project
The SU process ensures prerequisites are met, appoints the project board and manager, captures lessons and prepares the project brief and initiation stage plan.
Directing a project
The DP process enables the project board to authorize initiation, the project, stage or exception plans and closure, and to give ad hoc direction.
Initiating a project
The IP process establishes baselines and management approaches, prepares the project initiation documentation and enables the project board to authorize the project.
Controlling a stage
The CS process authorizes work packages, monitors progress, manages issues and risks, reports progress and escalates exceptions to the project board.
Managing product delivery
The MP process covers accepting, executing and delivering a work package, with the team manager ensuring products meet agreed quality criteria.
Managing a stage boundary
The SB process reviews the stage, updates the project plan and business case, prepares the next stage plan and requests project board authorization.
Closing a project
The CP process confirms product acceptance, reviews benefits and lessons, prepares closure and hands over products and responsibilities.
Tailoring PRINCE2
Tailoring applies PRINCE2 appropriately to the project's scale, complexity, risk, organization and delivery approach while retaining all seven principles.
Tailoring management products
PRINCE2 management products can be combined, simplified or adapted; the project should record which products are required and how they will be used.
Tailoring roles
PRINCE2 roles can be combined or shared in smaller projects, but accountability must remain clear and project board responsibilities must not be bypassed.
Tailoring and principles
Tailoring may change practices, processes, roles and documentation, but it must not remove or weaken the seven PRINCE2 principles.
Tailoring documentation
Tailoring decisions should be documented, agreed by the project board and reflected in the project initiation documentation and management approaches.