PRINCE2 7 Foundation key terms

PRINCE2 7 Foundation · Get comfortable with the vocabulary.

Project

A temporary organization, with a defined start and end, that is created to deliver one or more business products in line with an agreed business case.

Related: Programme, Business case, Project board
Programme

A group of related projects and other work managed together in a coordinated way to achieve outcomes and benefits that could not be realized if each project were managed separately.

Related: Portfolio, Project
Portfolio

The collection of an organization's projects, programmes and other work, managed together so the organization can prioritize investment, balance risk and allocate finite resources across that work.

Related: Programme, Project environment
Project environment

The internal and external surroundings in which a project operates, including strategy, culture, governance, stakeholders, technology, regulation and market conditions, all of which influence how the project is run.

Related: Tailoring, Portfolio
Continued business justification

The principle that a project must have a documented, valid reason to continue, and that this justification is reviewed and re-confirmed at every decision point rather than assumed to remain true.

Related: Business case, Manage by exception
Learn from experience

The principle that teams seek out and apply knowledge from earlier work and from their own project, taking time to reflect and feed lessons into decisions throughout.

Related: Lessons log, Managing a stage boundary
Defined roles and responsibilities

The principle that every project must have a clear, agreed structure of roles, with responsibilities and decision rights understood and used, matched to the project's size and complexity.

Related: Project board, Project manager
Manage by exception

The principle of delegating authority within pre-agreed tolerances so that only deviations beyond those limits are escalated to the next management level for a decision.

Related: Tolerance, Exception
Focus on products

The principle that the project defines and agrees what it must deliver, including its products, quality criteria and scope, before planning the activities needed to create them.

Related: Product description, Work package
Tailor to the environment

The principle that PRINCE2 is adapted in depth and rigour to suit the project's size, complexity, risk, importance and its organizational and commercial setting.

Related: Tailoring, Delivery approach
Stakeholder

Any individual, group or organization with an interest in, influence over, or exposure to the project's activities and outcomes, whether that interest is positive, negative or neutral.

Related: Stakeholder engagement, Communication management approach
Stakeholder engagement

The planned work of identifying stakeholders, analysing their interests and influence, and communicating with and involving them so they support the project and its outcomes.

Related: Stakeholder, Communication management approach
Leadership

The behaviour of influencing, motivating and enabling people to commit to and deliver project objectives, providing direction and support rather than only administering tasks and paperwork.

Related: Stakeholder engagement, Project manager
Communication management approach

A management product that sets out who needs project information, what they need, when and in what form it will be provided, and who is responsible for sending it.

Related: Stakeholder engagement, Stakeholder
Business case

A practice and its key management product: the practice establishes whether the project is desirable, viable and achievable, and the product records the reasons for the project and the justification for continued investment.

Related: Continued business justification, Executive, Benefits management approach
Benefits management approach

A management product that defines how and when the project's benefits will be measured, who is responsible for each, and how outcomes will be reviewed after the project closes.

Related: Business case, Senior user
Project board

The accountable management group for the project, made up of the executive, senior users and senior suppliers, which directs the project, takes key decisions and authorizes each stage.

Related: Executive, Senior user, Senior supplier
Executive

The single owner of the business case on the project board, accountable for the project's justification and overall direction and for ensuring it delivers the intended outcomes.

Related: Business case, Project board
Senior user

A project board role representing those who will use the project's products, specifying their needs and expected benefits and monitoring that the delivered solution meets them.

Related: Business case, Benefits management approach
Senior supplier

A project board role representing the parties who build the products, accountable for the technical and commercial feasibility of what is delivered and for committing supplier resources.

Related: Work package, Project board
Project manager

The role responsible for the day-to-day management of the project within the tolerances set by the project board, planning the work, allocating it and reporting progress.

Related: Work package, Highlight report, Tolerance
Tolerance

The agreed amount of deviation permitted from planned targets for time, cost, scope, quality, benefits and risk before the deviation must be reported as an exception.

Related: Exception, Manage by exception
Exception

A situation where it becomes clear that planned targets or the project's business justification will be, or may be, breached beyond agreed tolerances, requiring escalation for a decision.

Related: Exception plan, Tolerance
Management stage

A section of the project for which the project board authorizes work and funds in advance, and at the end of which progress and continued justification are reviewed.

Related: Controlling a stage, Managing a stage boundary
Exception plan

A plan produced to replace the remainder of a stage or project plan after an exception, showing how the work will recover to agreed tolerances and submitted for board approval.

Related: Exception, Managing a stage boundary
Product description

A statement of the purpose, composition, quality criteria, quality methods and source of a single product, used to plan and control the work needed to create it.

Related: Acceptance criteria, Work package
Acceptance criteria

The measurable conditions that the project's final products must satisfy for the users and the business to accept them as fit for purpose.

Related: Product description, Project brief
Lessons log

A running record of lessons identified during the project, together with the actions taken in response, used to inform current decisions and summarized for others later.

Related: Learn from experience
Risk register

The record of identified risks, each with its cause, potential effect, assessment, owner and planned response, kept up to date throughout the project.

Related: Issue register
Issue register

The record of issues raised on the project, showing for each its description, severity, owner, current status and the corrective action or change decided.

Related: Exception, Risk register
Project brief

The short document produced while starting up a project that sets out the project's purpose, outline business case, project product description and delivery approach, and is used to authorize initiation.

Related: Project initiation documentation, Business case
Project initiation documentation

The document produced during initiating a project that brings together the project's justification, scope, products, plans, approaches and governance arrangements, forming the basis for board authorization.

Related: Project brief, Business case
Work package

An instruction from the project manager to a team describing the products to be produced, the constraints, tolerances, quality checks and reporting required for a defined piece of work.

Related: Product description, Checkpoint report
Highlight report

A report from the project manager to the project board at agreed intervals, summarizing progress during a stage against the stage plan, together with forecasts, risks and issues.

Related: Controlling a stage, Project board
Checkpoint report

A regular progress report from a team manager to the project manager describing work completed, products and quality checks done, and any issues or deviations from the work package.

Related: Work package, Highlight report
Controlling a stage

The process in which the project manager directs and monitors the work within a stage, authorizing work packages, dealing with issues and reporting progress to the board.

Related: Management stage, Highlight report
Managing a stage boundary

The process in which the project manager prepares the next stage, reviews the current stage's performance and continued justification, and seeks board approval to proceed.

Related: Management stage, Exception plan
Tailoring

The deliberate adaptation of PRINCE2's practices, processes and management products, including their use, depth and formality, to fit a project's situation while keeping the principles intact.

Related: Tailor to the environment, Delivery approach
Delivery approach

The approach chosen for creating the project's products, such as a predictive, agile or hybrid way of working, selected according to the nature of the solution and the environment.

Related: Tailoring, Project brief