PRINCE2 Agile Foundation · Put your knowledge to work in context.

All case studies

Coastal Trust: a low Agilometer score that is not a 'no'

Coastal Trust is merging the patient-record systems of two hospitals. Five delivery teams work in two-week sprints, each with a product owner drawn from clinical staff. Clinical safety is critical: the trust's safety officer must approve anything touching medication data, and she has said publicly that 'agile means no documentation and no audit trail'. Three separate committees currently approve any screen change, and the average decision takes four weeks. The Agilometer assessment scored flexibility on what is delivered as low (statutory data fields are fixed), collaboration as medium, ability to work iteratively and incrementally as high, ease of making decisions as low, and acceptance of agile as low.

1. The programme director reads the assessment as 'agile is not suitable here'. How should the Agilometer results actually be used, and what is your recommendation?

Read the worked answer
  • The Agilometer is a tailoring diagnostic, not a go/no-go gate. A low score does not mean 'do not use agile'; it means 'this is where agile needs support and where PRINCE2 control should be firmer'. Its output feeds the tailor-to-the-environment principle.
  • Read the profile rather than the total. Ability to work iteratively and incrementally is high, so the delivery approach itself is workable. The weak scores are about decision-making and acceptance - organisational, not technical - and those are things the project manager can influence.
  • Recommendation: agile delivery inside a deliberately stronger PRINCE2 wrapper. Formal stage boundaries with evidence, a definition of done that includes clinical safety review, delegated decision-making within published tolerances, and manage by exception for anything outside them.
  • Treat fixed statutory fields and audit requirements as fixed, non-negotiable requirements rather than something to 'flex'. Low flexibility there is correct and should be stated as such.
  • Re-assess at each stage boundary. If decision-making and acceptance are still low at month six, that is real data for the board about organisational blockers - not a reason to abandon the approach.

2. Which two actions would you take to improve the weakest scores, and what would you deliberately not change?

Read the worked answer

Decision-making (fastest payoff)

  • Replace the three committees with one decision forum with named decision-makers and published tolerances. Anything within tolerance is delegated to the product owner; the forum commits to a stated timebox, for example five working days. Anything outside tolerance escalates to the board through manage by exception.
  • Publish the decision log so slow decisions become visible as a queue, not as an unexplained delay.

Acceptance

  • Invite the safety officer into the loop: sprint reviews, plus a short weekly session. Show her the safety evidence produced every sprint rather than a document at the end.
  • Co-write the safety elements of the definition of done with her, so it is her standard, and give her a veto at the review rather than a signature at the end.

What not to change

  • The statutory fields, the audit trail and the safety approval itself. Resisting those would confirm her worst fears and destroy credibility; the argument is about how the controls are applied, not whether they exist.

3. How do PRINCE2 Agile behaviours and rich communication address the safety officer's concerns concretely?

Read the worked answer
  • Transparency. Publish the board, the definition of done, the safety checks performed per increment and the defects found - including the bad news. Her fear is hidden work, so make the work visible. A team that hides a failed safety test to protect its velocity has broken the method, not just the relationship.
  • Collaboration. Put her inside the delivery loop rather than in an approval queue: review attendance and a standing weekly session. That is a different relationship from 'submit and wait four weeks'.
  • Rich communication. Use visual, face-to-face artefacts - an information radiator showing safety-critical items and the evidence attached to each - instead of a status report. Rich communication is a focus area precisely because it beats written status in high-ambiguity, high-consequence settings.
  • Reframe documentation as sufficient, not exhaustive. Agile produces more usable audit evidence in most cases: review records, adherence to the definition of done, test evidence per increment, decision logs. The 200-page specification nobody reads is not the audit trail; the evidence is.
  • Show, don't assert. Invite her to a sprint review in the first four weeks and let the artefacts argue.