PRINCE2 Agile Foundation study materials
PRINCE2 Agile Foundation study resources

PRINCE2 Agile Foundation cheat sheet

PRINCE2 Agile Foundation · Keep the key ideas within reach.

Quick reference

Agile concepts and why they are used

  • Agile is a set of behaviours, concepts, frameworks and techniques that enables rapid adaptation to change; it is a mindset rather than a single method.

  • The four Agile Manifesto value pairs (left item preferred) are: individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a plan.

  • The characteristic delivery pattern is short cycles, each producing a usable increment, so that feedback is obtained and applied before the next cycle.

  • Empiricism is the basis of agile decision-making: work is inspected frequently and adapted, rather than executed exactly as a long-range plan predicted.

  • Agile fits best where requirements are unclear or volatile, change is frequent, early value matters and an engaged customer is available.

  • Timeboxing fixes the duration and flexes scope; flow-based working fixes work in progress and lets duration vary.

  • Agile shortens the feedback loop, which reduces the risk of building the wrong product; it does not remove the need for governance, control or documentation.

  • Agility requires discipline: visible information, frequent collaboration and sound technical practices are preconditions, not optional extras.

Quick reference

The PRINCE2 Agile approach: blending PRINCE2 with agile

  • PRINCE2 Agile combines PRINCE2 (principles, themes, processes, roles) as the governance framework with agile as the delivery approach; neither replaces the other.

  • Core messages of PRINCE2 Agile include: be on time and hit deadlines, protect the level of quality, and accept that change happens.

  • Project-level constraints: time and cost are fixed, quality is protected, and scope is the variable that flexes within agreed tolerances.

  • Tailoring is driven by three devices: the agile behaviours, the focus areas, and the Agilometer.

  • Management products are still required but must be 'sufficient' - light enough to be produced and used inside a timebox.

  • Management by exception is retained: the project board sets tolerances and the team proceeds without seeking approval while inside them.

  • Prioritisation replaces detailed up-front specification; Must requirements are limited to roughly 60 per cent of effort so contingency remains.

  • Decision rights are split: the board decides why and how much, the product owner and team decide what next and how.

  • Roles are mapped, not duplicated: existing PRINCE2 roles are supplemented by product owner and Scrum Master type roles within the team.

Quick reference

Agile ways of working, frameworks and techniques

  • Scrum has three roles (Product Owner, Scrum Master, Development Team), three artefacts (Product Backlog, Sprint Backlog, Increment) and five events (Sprint, Sprint Planning, Daily Scrum, Sprint Review, Sprint Retrospective).

  • A Sprint is a timebox of one month or less; the Daily Scrum is a 15-minute event used to inspect progress and adapt the plan for the day.

  • The Sprint Review inspects the product increment with stakeholders; the Sprint Retrospective inspects the team's way of working.

  • Kanban core practices: visualise the workflow, limit work in progress, manage flow, make policies explicit, implement feedback loops and improve collaboratively.

  • Little's Law: average cycle time equals work in progress divided by throughput, so raising WIP without raising throughput lengthens delivery time.

  • A cumulative flow diagram plots the number of items in each workflow state over time; widening bands reveal bottlenecks and growing queues.

  • Lean Startup uses a build-measure-learn loop with a minimum viable product to obtain validated learning, then a decision to pivot or persevere.

  • Timeboxing and flow-based working differ in what is fixed: timeboxing fixes time and varies scope, flow-based working fixes WIP and varies time.

  • Information radiators such as task boards, burn-up and burn-down charts make progress and impediments visible to everyone.

Quick reference

Applying the PRINCE2 principles, themes and processes in an agile context

  • The seven principles are: continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, and tailor to suit the project.

  • Manage by stages: a management stage may cover one or more timeboxes or a release, with stage boundaries aligned to release or sprint boundaries.

  • Manage by exception: tolerances on time, cost, scope, quality, risk and benefits are set by the board and delegated to the team.

  • Focus on products: product descriptions define purpose, composition and quality criteria; the definition of done and acceptance criteria apply them at team level.

  • Business case theme: benefits and value are re-assessed at stage boundaries, and early releases provide evidence for pivot or stop decisions.

  • Organization theme: the project board (executive, senior user, senior supplier), project manager and team manager work alongside product owner and Scrum Master roles.

  • Quality theme: acceptance criteria and the definition of done replace heavyweight quality reviews; quality is protected rather than traded against time.

  • Plans theme: product-based planning is retained, with a release plan at stage level and team or sprint plans covering individual timeboxes.

  • Change theme: change is expected and absorbed by re-prioritising the backlog and flexing scope within the scope tolerance; progress is reported through highlight and checkpoint reports plus burn charts.

Quick reference

Agile behaviours, the focus areas and the Agilometer

  • The five agile behaviours are transparency, collaboration, rich communication, self-organisation and exploration.

  • Transparency means progress, quality and problems are visible and honestly reported, typically through information radiators.

  • Self-organisation means the team decides how the work is done within agreed boundaries, while management sets the what, the why and the tolerances.

  • Focus areas direct tailoring: the Agilometer, requirements, rich communication and frequent releases.

  • Requirements focus area uses MoSCoW prioritisation: Must about 60 per cent of effort or less, Should about 20 per cent, Could about 20 per cent, Won't is out of scope this time.

  • Rich communication focus area favours face-to-face, visual and frequent communication such as co-location, workshops and information radiators.

  • Frequent releases focus area delivers usable increments to the customer as early and often as is sensible; each release is a feedback and benefit point.

  • The Agilometer uses six sliders to assess suitability for agile working; it is completed early and reviewed, and low scores indicate where tailoring or mitigation is required.