PRINCE2 Agile Foundation flashcards
PRINCE2 Agile Foundation · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Agile Manifesto values
- Four value pairs preferring the left item: individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; responding to change over following a plan.
- Empiricism
- The agile principle that decisions rest on observation and experience: work is inspected frequently and adapted, rather than executed exactly as a long-term plan predicted.
- Iterative and incremental delivery
- Delivering a product in repeated cycles, each producing a usable increment that builds on the previous one, so feedback can be applied before the next cycle begins.
- Timebox
- A fixed period of time that is not extended; if the work cannot be completed within it, scope is reduced instead of the deadline being moved.
- Push versus pull
- In a push system work is released according to a forecast; in a pull system new work starts only when downstream capacity is free, controlled by WIP limits.
- When agile is appropriate
- Situations with unclear or changing requirements, a high rate of change, a need for early value and an available, engaged customer who can give frequent feedback.
- PRINCE2 Agile blend
- PRINCE2 supplies governance through principles, themes, processes and roles; agile supplies delivery behaviours and techniques. Neither is discarded; both are tailored together.
- Fixed time, cost, flexible scope
- At project level PRINCE2 Agile fixes time and cost, protects the level of quality, and treats scope as the variable that flexes within agreed tolerances.
- Be on time, hit deadlines
- A core PRINCE2 Agile message: timeboxes and deadlines are protected, quality is protected, and it is scope that is reduced to fit the fixed time.
- Sufficient documentation
- PRINCE2 Agile still requires management products but tailors them to be as light as possible, just enough to support decisions within the timebox.
- Management by exception in agile
- The project board sets tolerances; the team and product owner then make day-to-day decisions and escalate only when a tolerance is forecast to be breached.
- MoSCoW prioritisation
- Requirements are ranked Must, Should, Could and Won't have this time. Musts are limited to about 60 per cent of effort so contingency remains for lower priorities.
- Scrum framework
- Three roles (Product Owner, Scrum Master, Development Team), three artefacts (Product Backlog, Sprint Backlog, Increment) and five events built around Sprints of one month or less.
- Sprint Review
- A Scrum event at the end of a Sprint where the team demonstrates the completed increment to stakeholders and collects feedback that feeds the product backlog.
- Sprint Retrospective
- A Scrum event held after the Sprint Review where the team inspects its own way of working and agrees improvements to apply in the following Sprint.
- Kanban core practices
- Visualise the workflow, limit work in progress, manage flow, make policies explicit, implement feedback loops and improve collaboratively.
- Little's Law
- Average cycle time equals work in progress divided by throughput; increasing WIP without increasing throughput makes each item take longer to finish.
- Cumulative flow diagram
- A chart showing how many items sit in each workflow state over time; widening bands expose where work is piling up and where the bottleneck lies.
- Lean Startup cycle
- Build a minimum viable product, measure the real customer response to it, learn from that evidence, then decide whether to pivot or persevere.
- Minimum viable product
- The smallest version of a product that allows a team to run the build-measure-learn loop and gain validated learning with the least possible effort.
- Seven PRINCE2 principles
- Continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, and tailor to suit the project.
- Manage by stages in agile
- A management stage may cover one or more timeboxes or a release; stage boundaries are aligned with release or sprint boundaries and planned accordingly.
- Definition of done
- An agreed checklist that an increment must satisfy before it is considered complete; it applies the PRINCE2 quality theme at team level and protects quality.
- Focus on products with agile
- Product descriptions state purpose, composition and quality criteria; in agile they are written at a high level and supplemented by acceptance criteria and the definition of done.
- Business case theme in agile
- Value and benefits are reviewed at stage boundaries; early releases deliver benefit sooner and provide evidence to support a decision to pivot or stop.
- Highlight report in agile
- A progress-theme report sent to the project board at the end of each timebox or stage, summarising achievement, forecast, issues and the status of tolerances.
- Five agile behaviours
- Transparency, collaboration, rich communication, self-organisation and exploration are the behaviours PRINCE2 Agile expects from everyone involved in the project.
- Self-organisation
- The team decides how the work is done within agreed boundaries, while management sets what is needed, why it is needed and the tolerances.
- Rich communication focus area
- Favour face-to-face, visual and frequent communication such as co-location, workshops and information radiators, rather than lengthy written reports.
- Frequent releases focus area
- Deliver usable increments to the customer as early and often as is sensible, because each release provides a point for feedback and benefit realisation.
- Agilometer
- A tool with six sliders assessing how suitable a project is for agile working, covering factors such as flexibility, customer involvement, frequent delivery, acceptance of agile and collaboration.
- Agilometer usage
- It is completed during start-up and reviewed at stage boundaries; a low score on any slider shows where tailoring or mitigation is required.