PRINCE2 Principles

  • There are exactly seven principles, and they apply to every PRINCE2 project regardless of scale, type, or delivery approach.

  • Continued business justification: a project must have a justifiable reason to start and that justification must remain valid and documented throughout.

  • Learn from experience: lessons are sought, recorded, and acted upon at the start, during each stage, and at project closure rather than only at the end.

  • Defined roles and responsibilities: every project has a defined organisation structure with agreed roles, accountabilities, and a documented project management team.

  • Manage by stages: the project is planned, monitored, and controlled on a stage-by-stage basis, with at least two management stages (initiation plus delivery).

  • Manage by exception: tolerances are set for time, cost, scope, quality, risk, and benefit, and management intervention occurs only when a tolerance is forecast to be exceeded.

  • Focus on products: the project is driven by the definition and delivery of products, with each product described by quality criteria and a product description.

  • Tailor to suit the project environment: the method is adapted to the project's size, complexity, importance, capability, and risk, but the principles themselves are never tailored away.

Quick reference

PRINCE2 Themes

  • Seven themes: Business Case, Organisation, Quality, Plans, Risk, Change, and Progress; each theme is applied continuously across all processes.

  • Business Case theme uses the business case document, the benefits management approach, and outputs/outcomes/benefits distinction; the senior user is accountable for benefits realisation.

  • Organisation theme defines three project interests (business, user, supplier) and four management levels: corporate/programme, directing, managing, and delivering.

  • Quality theme uses the quality management approach, product descriptions, the quality register, and the plan-do-check-act cycle of quality planning, assurance, and control.

  • Plans theme defines three plan types: project plan, stage plan, and team plan; exception plans are produced when tolerances are forecast to be exceeded.

  • Risk theme follows the risk management approach and a procedure of identify, assess, plan, implement, and communicate; risk is assessed by probability and impact.

  • Change theme uses the change control approach, issue register, change budget, and configuration management (identification, control, status accounting, verification).

  • Progress theme compares actual against planned performance using baselines, tolerance, management by exception, and progress reports (checkpoint, highlight, end stage, end project).

Quick reference

PRINCE2 Processes

  • Seven processes: Starting up a Project, Directing a Project, Initiating a Project, Controlling a Stage, Managing Product Delivery, Managing a Stage Boundary, Closing a Project.

  • Starting up a Project creates the project mandate, project brief, and daily log, and appoints the project management team before initiation.

  • Directing a Project is owned by the Project Board and runs throughout; it authorises initiation, each stage, exception responses, and project closure.

  • Initiating a Project produces the project initiation documentation (PID), which includes the business case, plans, controls, and the project approach.

  • Controlling a Stage covers authorising work packages, monitoring and reporting, handling issues and risks, and reviewing stage status.

  • Managing Product Delivery is the supplier-side process that accepts, executes, and delivers work packages and reports completion.

  • Managing a Stage Boundary produces the end stage report and next stage plan, and is triggered before each new stage except the first.

  • Closing a Project confirms acceptance of products, reviews benefits, and produces the end project report and lessons report.

Quick reference

PRINCE2 Project Environment and Tailoring

  • Tailoring is mandatory under the tailor-to-suit principle; the project manager records tailoring decisions in the project initiation documentation.

  • Tailoring factors include project size, complexity, importance, team capability, and risk; the level of tailoring is agreed with the Project Board.

  • A project is a temporary organisation created to deliver one or more business products according to an agreed business case; it is distinct from business-as-usual.

  • Projects may exist within a programme or a portfolio; in a programme context, the programme provides the project mandate and may set tolerances.

  • The project manager's role is defined by the Project Board; in a small project these roles may be combined, but the three project interests must still be represented.

  • Commercial customers and suppliers may be involved; a customer/supplier context affects the business case, contracts, and the supplier's role in the organisation.

  • Agile and other delivery approaches can be used with PRINCE2; the method is delivery-agnostic and can be tailored to iterative or incremental delivery.

  • Projects have four levels of management (corporate/programme, directing, managing, delivering); tailoring determines how much of the method is applied at each level.