PRINCE2 Foundation (PRINCE2) flashcards
PRINCE2 Foundation · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Continued business justification
- A PRINCE2 principle requiring that a project has a documented, justifiable reason to start and that this justification is reviewed and remains valid throughout the project's life.
- Manage by exception
- A PRINCE2 principle in which tolerances for time, cost, scope, quality, risk, and benefit are agreed upfront, and management intervenes only when a tolerance is forecast to be exceeded.
- Focus on products
- A PRINCE2 principle stating that the project is directed by the definition and delivery of products, each described by a product description with quality criteria and acceptance requirements.
- Tailor to suit
- A PRINCE2 principle requiring the method to be adapted to the project's size, complexity, importance, capability, and risk, while the seven principles themselves are never tailored away.
- Learn from experience
- A PRINCE2 principle requiring lessons to be sought, recorded, and acted upon at the start, during each stage, and at closure, rather than only at the end of the project.
- Defined roles and responsibilities
- A PRINCE2 principle requiring an agreed project management team structure with clear accountabilities for each role, documented in the project initiation documentation.
- Manage by stages
- A PRINCE2 principle requiring the project to be planned, monitored, and controlled stage by stage, with a minimum of two management stages and decision points between them.
- Business Case theme
- The PRINCE2 theme covering how the business justification is developed and maintained, using the business case document and the benefits management approach, with the senior user accountable for benefits.
- Organisation theme
- The PRINCE2 theme defining the project management team structure, the three project interests (business, user, supplier), and the four levels of management from corporate to delivering.
- Quality theme
- The PRINCE2 theme covering quality planning, quality assurance, and quality control, using the quality management approach, product descriptions, and the quality register.
- Plans theme
- The PRINCE2 theme covering the project plan, stage plans, team plans, and exception plans, and how planning supports control and management by exception.
- Risk theme
- The PRINCE2 theme covering the identification, assessment, planning, implementation, and communication of risk, supported by the risk management approach and a risk register.
- Change theme
- The PRINCE2 theme covering change control and configuration management, using the change control approach, issue register, change budget, and configuration item records.
- Progress theme
- The PRINCE2 theme covering monitoring and control of actual versus planned performance, using baselines, tolerances, management by exception, and progress reports.
- Benefits management approach
- A PRINCE2 document defining how and when benefits will be measured and reviewed, who is responsible, and what actions are needed to realise them after project closure.
- Starting up a Project
- The first PRINCE2 process, which creates the project mandate, project brief, and daily log and appoints the project management team before initiation is authorised.
- Directing a Project
- The PRINCE2 process owned by the Project Board that runs throughout the project to authorise initiation, each stage, exception responses, and project closure.
- Initiating a Project
- The PRINCE2 process that produces the project initiation documentation, including the business case, plans, controls, and project approach, before delivery begins.
- Controlling a Stage
- The PRINCE2 process in which the project manager authorises work packages, monitors progress, handles issues and risks, and reviews stage status.
- Managing Product Delivery
- The PRINCE2 process on the supplier side that accepts work packages, executes the work, delivers products, and reports completion to the project manager.
- Managing a Stage Boundary
- The PRINCE2 process that produces the end stage report and next stage plan, and is triggered before each new stage except the first.
- Closing a Project
- The PRINCE2 process that confirms acceptance of products, reviews benefits, and produces the end project report and lessons report.
- Project initiation documentation
- The set of documents produced during Initiating a Project that defines the project, including the business case, plans, controls, and project approach.
- Project mandate
- The trigger for Starting up a Project that provides the initial reason and context for the project, which is refined into the project brief.
- Tailoring in PRINCE2
- The mandatory adaptation of the method to a project's size, complexity, importance, capability, and risk, agreed with the Project Board and recorded in the project initiation documentation.
- Three project interests
- The business, user, and supplier perspectives that must each be represented on the project management team, typically by the executive, senior user, and senior supplier.
- Project versus business-as-usual
- A project is a temporary organisation delivering defined products against an agreed business case, whereas business-as-usual is ongoing operational activity.
- Programme context
- When a project sits within a programme, the programme typically provides the project mandate and may set tolerances and reporting requirements for the project.
- Customer/supplier context
- A project environment in which commercial customers and suppliers are involved, affecting the business case, contracts, and the supplier's role in the project organisation.
- Agile with PRINCE2
- PRINCE2 is delivery-agnostic and can be tailored to iterative or incremental delivery, with stage boundaries and product descriptions supporting agile ways of working.
- Four levels of management
- Corporate or programme, directing, managing, and delivering; tailoring determines how much of the method is applied at each level.
- Project Board composition
- The Project Board comprises the executive, senior user, and senior supplier, collectively accountable for the project's success and for authorising stages and closure.