Quick reference

Business and Project Management

  • Critical path is the longest sequence of dependent activities through the project network; it sets minimum project duration and has zero total float.

  • Total float = late start - early start = late finish - early finish.

  • CPI = earned value / actual cost; CPI below 1.0 indicates cost overrun. SPI = earned value / planned value; SPI below 1.0 indicates schedule delay.

  • Crashing shortens critical activities by adding resources and cost; fast-tracking overlaps activities and increases coordination risk.

  • A change order is a written instrument signed by owner and contractor that defines changed scope, price, and time before changed work proceeds.

  • An RFI requests interpretation or clarification; a submittal transmits product data or shop drawings for approval; neither alone changes contract price.

  • Liquidated damages are a predetermined per-day amount for delay; they must be a reasonable forecast of probable loss, not a penalty.

  • South Carolina generally requires a contractor license when construction cost is $5,000 or more; the license classification must match the work.

  • Substantial completion occurs when work is sufficiently complete for owner use; it starts warranty periods and the punch list.

Quick reference

Contract Administration and Bidding

  • Bid bond is typically 5 percent of the bid; performance and payment bonds are typically 100 percent of the contract price.

  • Addenda modify bid documents before bid opening; bidders must acknowledge each addendum in the bid.

  • A lump-sum contract assigns quantity risk to the contractor; a unit-price contract pays actual quantities at fixed unit rates.

  • When bid figures conflict, the unit price normally prevails over the extended total, and written words normally prevail over numerals.

  • A differing site condition is a physical condition materially different from contract documents; notify the owner promptly before disturbing it.

  • A constructive change arises when owner action or inaction requires extra work without a formal change order; document cost and time impact.

  • Progress payments are supported by a schedule of values; retainage is withheld until contract conditions for release are met.

  • Mechanic's lien rights depend on strict statutory filing and notice deadlines measured from last furnishing labor or materials.

  • Alternates are priced options selected by the owner; allowances are provisional sums adjusted to actual cost.

Quick reference

Estimating and Plan Reading

  • A scale of 1/4 inch = 1 foot means one drawing inch represents 48 real inches, or four feet.

  • Board feet = (thickness in inches x width in inches x length in feet) / 12.

  • Concrete volume = length x width x depth in consistent units; add 5 to 10 percent for waste.

  • No. 4 rebar is 1/2 inch diameter and weighs about 0.668 lb/ft; No. 5 rebar is 5/8 inch diameter and weighs about 1.043 lb/ft.

  • Contour lines connect points of equal elevation; closely spaced contours indicate steep slope, widely spaced contours indicate gentle slope.

  • Cut-and-fill balance compares bank volume with fill volume adjusted for soil swell and compaction shrinkage.

  • Crew hours = total quantity / crew output per hour; labor cost = hours x wage rate x burden factor.

  • Roof slope factor = square root of (rise squared + run squared) divided by run; use it to convert plan area to sloped area.

  • Solid lines show visible work; dashed lines show hidden or overhead work; section marks identify cut locations.

Quick reference

Construction Methods, Materials, and Site Work

  • Lower water-cement ratio increases concrete strength and durability; higher ratio improves workability but reduces strength.

  • The slump test measures fresh concrete workability; measured slump must fall within specification limits for the placement.

  • Concrete cast against earth typically requires 3 inches of cover over reinforcing steel.

  • Standard Proctor test determines maximum dry density and optimum moisture content; field compaction is commonly specified as 95 percent of maximum dry density.

  • Nominal 2x4 lumber is actually 1-1/2 x 3-1/2 inches when surfaced dry; nominal 2x10 is 1-1/2 x 9-1/4 inches.

  • Retaining walls require weep holes or footing drains and free-draining backfill to relieve hydrostatic pressure.

  • For a two-leg sling, each leg tension = load / (2 x sine of angle from horizontal); lower angles increase tension.

  • Excavated spoil and equipment must be kept at least 2 feet back from the edge of a trench.

  • Finish grade should slope away from the foundation at least 6 inches within the first 10 feet.

Quick reference

Safety, Codes, and Regulatory Compliance

  • OSHA requires fall protection for construction workers exposed to falls of 6 feet or more above a lower level.

  • Guardrails for fall protection have a top rail about 42 inches high, within 38 to 45 inches, plus a midrail.

  • Excavations 5 feet or deeper require a protective system unless a competent person determines stable rock or no hazard.

  • A competent person must inspect excavations daily before work and after rain or other hazard-changing events.

  • GFCI protection is required for temporary construction power, or an assured equipment grounding conductor program may be used.

  • Employers must report a work-related fatality to OSHA within 8 hours and an inpatient hospitalization, amputation, or eye loss within 24 hours.

  • Construction disturbing 1 acre or more requires NPDES permit coverage and a stormwater pollution prevention plan.

  • South Carolina adopts the International Building Code and International Residential Code through the Building Codes Council; local authorities issue permits and inspect work.

  • A certificate of occupancy is issued by the building official after required inspections confirm code compliance.