Critical Path
The longest sequence of dependent activities through a project network; it determines the minimum project duration and has zero total float.
Total Float Formula
Total float equals late start minus early start, or late finish minus early finish; an activity with zero total float is critical.
Cost Performance Index
CPI equals earned value divided by actual cost; a value below 1.0 indicates the project is over budget.
Schedule Performance Index
SPI equals earned value divided by planned value; a value below 1.0 indicates the project is behind schedule.
Liquidated Damages
Predetermined money amount per day of delay; enforceable when it is a reasonable forecast of probable loss rather than a penalty.
Substantial Completion
The stage when work is sufficiently complete for the owner's intended use; it starts warranty periods and the punch list.
RFI Versus Submittal
An RFI requests clarification or information; a submittal transmits product data or shop drawings for review and approval.
Bid Bond
A bond usually equal to 5 percent of the bid; it guarantees the bidder will sign the contract and furnish required bonds.
Performance Bond
A bond usually equal to 100 percent of the contract price; it protects the owner if the contractor fails to perform.
Payment Bond
A bond usually equal to 100 percent of the contract price; it protects subcontractors and suppliers from nonpayment on the project.
Addendum
A written modification to bidding documents issued before bid opening; bidders must acknowledge it and incorporate it into their bid.
Unit Price Precedence
In bid conflicts, the unit price normally prevails over the extended total, and written words normally prevail over figures.
Constructive Change
An owner action or inaction that requires extra work without a formal change order; it may support a cost or time claim.
Scale Factor
A drawing scale of 1/4 inch equals 1 foot means one drawing inch represents 48 real inches, or four feet.
Board Foot Formula
Board feet equals thickness in inches times width in inches times length in feet, divided by 12.
Concrete Volume
Volume equals length times width times depth in consistent units; order 5 to 10 percent extra for waste and spillage.
Number 4 Rebar
A number 4 reinforcing bar is 1/2 inch in diameter and weighs about 0.668 pounds per linear foot.
Contour Lines
Lines on a drawing connecting points of equal elevation; closely spaced contours indicate steep slopes and widely spaced contours indicate gentle slopes.
Crew Hours Formula
Crew labor hours equal total quantity divided by the crew's output per hour; multiply by crew size to get individual worker hours.
Water-Cement Ratio
The ratio of water weight to cement weight in concrete; lower ratios increase strength and durability, while higher ratios improve workability but reduce strength.
Slump Test
A field test that measures fresh concrete workability; the measured slump must fall within the specification limits for the placement.
Concrete Cover
The minimum distance from reinforcing steel to the concrete surface; concrete cast against earth typically requires 3 inches of cover.
Proctor Test
A laboratory test that determines a soil's maximum dry density and optimum moisture content for compaction control in the field.
Nominal Lumber Size
The labeled size of lumber before surfacing; a nominal 2 by 4 is actually 1-1/2 by 3-1/2 inches when dry.
Weep Holes
Openings in a retaining wall or masonry veneer that allow water to drain and relieve hydrostatic pressure behind the wall.
Sling Tension
Tension in a sling increases as its angle from horizontal decreases; for two equal legs, each tension is load divided by twice the sine of the angle.
Fall Protection Threshold
OSHA requires fall protection for construction workers exposed to falls of 6 feet or more above a lower level.
Trench Protective System
Required for excavations 5 feet or deeper unless a competent person determines stable rock or no hazard exists.
Competent Person
A person capable of identifying existing and predictable hazards and authorized to take prompt corrective action; required to inspect trenches daily.
GFCI Protection
A ground-fault circuit interrupter protects workers from electrical shock by quickly shutting off power; required for temporary construction power.
Fatality Reporting Rule
Employers must report a work-related fatality to OSHA within 8 hours and a hospitalization, amputation, or eye loss within 24 hours.
Stormwater Construction Permit
Construction disturbing 1 acre or more requires NPDES permit coverage and a stormwater pollution prevention plan addressing erosion and sediment control.