The 30% mandate and the 120-point forecast
The company has announced a programme to deliver a '30% engineering productivity gain from AI by Q3'. Your Scrum Team was an early pilot and now holds a licence for an assistant plus a mandate to log 'AI-assisted hours' every week. Legal has not finished the data-handling review, so nobody is certain whether customer data may be sent to the tool; two teams have quietly stopped using it and one uses it heavily. A director has asked every team to reserve 20% of each Sprint for 'AI experimentation', announced at a town hall; your Product Owner learned about it afterwards. Last Sprint the team's forecast was 'adjusted' upward after the tool generated an estimate of 120 points for the backlog, which the director found convincing.
1. What is wrong here from a Scrum perspective, and what would you do in the next two weeks?
Read the worked answer
Four distinct problems, with different owners.
- Capacity is being allocated outside the Product Owner's ordering and the team's self-management. A 20% reservation imposed at a town hall means the Sprint Backlog is now partly written by someone who is not doing the work. The team can still self-manage, but only if the reservation becomes an ordered Product Backlog item with a Sprint Goal it can actually serve - not a slice of capacity removed from every Sprint regardless of what is most valuable.
- A numeric target has replaced a hypothesis. '30% by Q3' is not falsifiable as stated: 30% of what, measured how, against which baseline, controlling for what else changed? A target with no measurement definition reliably produces activity that looks like the target.
- The forecast has been converted into a commitment. A tool-generated estimate of 120 points, accepted upward, turns an empirical forecast into a promise made by people who did not make it. That is the opposite of the transparency Scrum depends on.
- A risk with no owner. Legal has not concluded. Teams are therefore each making their own guess about customer data - which is exactly why usage is bimodal. Unclear rules produce both recklessness and paralysis.
Next two weeks:
- With the Product Owner: get the 20% onto the Product Backlog as an explicit, ordered item with a stated question it answers and a written kill criterion. Capacity is then allocated by the person accountable for value, visibly.
- Surface the legal gap as an impediment with a named owner and a date. Bring it to the director as a delivery risk, not a compliance complaint.
- Replace 'AI-assisted hours' with measures that mean something: cycle time, items reaching Done, escaped defects, review load. Hours logged measures enthusiasm, not productivity.
- Make AI use visible in the Definition of Done so the Sprint Review shows what was actually produced and verified.
2. The director is attached to the 120-point forecast. How do you respond without simply refusing?
Read the worked answer
Explain what the number actually is. A generative model has no access to your team's capacity, its history, its codebase, its dependencies or its interruptions. Asked for an estimate, it produces plausible text conditioned on the prompt - usually anchored to whatever number or framing the prompt contained. It is a prompt-shaped guess, and the fact that it reads fluently is a property of the writing, not evidence about the work.
Then give the director something better, not nothing. Offer an empirical forecast the team can stand behind:
- Plot items reaching Done per Sprint for the last six Sprints. Use the range - for example, between 38 and 52 items - as the forecast, with the assumptions stated.
- State the confidence and the conditions: this holds if the team is not pulled onto unplanned work and if the review queue is reduced.
- Explain the cone of uncertainty widening with horizon: a confident number for next Sprint, a range for next quarter, and honest doubt beyond that.
Name the anchoring risk out loud. Once 120 is on a slide, it becomes the expectation, and every subsequent conversation is about the gap to 120 rather than about what is actually achievable. That is not a reason to hide the data; it is a reason to publish the right data first.
Also offer the experiment frame the director is actually looking for. A 30% target becomes useful when written as: 'we believe assistant use reduces time from started to Done; we will measure cycle time on comparable items for two Sprints; we will stop if cycle time does not improve or if escaped defects rise.' That gives the director a real answer with a date attached, and gives the team something it can influence.
3. You have no authority over the director, the Product Owner or Legal. How do you influence this so the initiative helps rather than harms the teams?
Read the worked answer
Use the levers a Scrum Master actually has: transparency, evidence, relationships and framing.
- Make reality visible rather than argued. Publish the data the teams already generate - items reaching Done, cycle time, review queue depth, escaped defects, and what happened to them after AI adoption. An argument about whether the tool helps is unwinnable; a two-Sprint chart of cycle time is hard to dismiss and is also honest when it shows a gain.
- Work through the Product Owner, not around them. The 20% question is a value-ordering question, and the Product Owner is the person accountable for ordering. Coach the PO to bring the trade-off to the director themselves - a PO asking for the experiment to be framed as a backlog item is a different conversation from a Scrum Master objecting.
- Convert complaints into owned risks. For Legal: 'who owns the decision on customer data, and by when?' For the director: 'if this lands and has to be rolled back, what does that cost?' Executives respond to owned risk far better than to unease.
- Propose a small bet with a pre-agreed kill criterion. It gives the initiative momentum and gives the teams a protected way to stop something that is not working. Being the person with a viable next step beats being the person who says no.
- Use the Sprint Review as the forum. Show a real Increment and the real measures; invite the director. Empiricism works best when the sceptic is in the room looking at the same artefact.
- Escalate once, factually, if a team is being asked to breach the DoD or a legal constraint. State what you observed, the risk, and who is accepting it. Your accountability is to make it visible and owned; not to win.