- K-factor
- The discharge coefficient relating sprinkler flow to pressure by Q = K × √P. It gives flow in gpm at 1 psi and must not be altered by paint or modification.
- Design density
- The minimum water application rate in gpm/ft² applied over the hydraulically most remote operating area, and the basis for the sprinkler hydraulic calculation.
- Glass bulb color code
- Bulb color indicates temperature rating: orange 135°F, red 155°F, yellow 175°F, green 200°F, blue 286°F, purple 360°F, and black 440°F.
- Remote area
- The hydraulically most demanding area of sprinkler operation. Its size in square feet depends on hazard classification and the density/area curve selected for design.
- Psi to feet of head
- One psi equals 2.31 feet of water column, and one foot of water column equals 0.433 psi; these convert elevation differences into pressure loss in calculations.
- Authority having jurisdiction
- The organization, office, or individual responsible for approving equipment, installations, and procedures and for enforcing the adopted code edition in a given location.
- NFPA 25 scope
- It sets minimum inspection, testing, and maintenance frequencies for water-based fire protection systems after acceptance, covering valves, gauges, alarms, sprinklers, and pumps.
- Code adoption by reference
- Model codes take legal effect only when a jurisdiction adopts them; the adopted edition year and local amendments govern the project rather than the newest publication.
- Annual main drain test
- A flow test through the main drain that confirms the water supply and reveals closed or obstructed valves by comparing static and residual pressures against baseline readings.
- Weekly fire pump churn
- Fire pumps run weekly at no flow, at least 10 minutes for electric drive and 30 minutes for diesel drive, verifying automatic starting, pressure, and lubrication.
- Ordinary hazard spacing limits
- Standard spray sprinklers in ordinary hazard are spaced no more than 15 feet apart with no more than 130 square feet of protection area per sprinkler.
- Deflector position
- Standard spray pendent and upright deflectors are positioned 1 inch to 12 inches below the ceiling, measured to the deflector, unless the listing permits otherwise.
- Three times rule
- An obstruction is acceptable when the sprinkler is placed within three times the obstruction's depth below the deflector plane; otherwise additional sprinklers are required.
- Water supply flow test
- Hydrant flow data used for design must be no more than 12 months old and adjusted for seasonal and daily demand variations before use in calculations.
- Pipe schedule method limits
- Pipe schedule sizing applies only within limits on system area, occupancy, and pressure. Other systems require full hydraulic calculation to demonstrate adequate supply.
- Hydrostatic test pressure
- New sprinkler piping is tested at 200 psi for 2 hours, or at 50 psi above maximum working pressure where that working pressure exceeds 150 psi.
- Impairment coordinator
- The designated person who authorizes a system shutdown, notifies the AHJ and insurer, posts impairment tags, and establishes fire watch until protection is restored.
- Underground main flushing
- Buried mains are flushed before connection to building piping at a flow producing about 10 feet per second velocity, removing debris that could obstruct sprinklers.
- Hot work permit
- Written authorization required before cutting, welding, or grinding that specifies precautions, a fire watch during work, and monitoring for at least 30 minutes afterward.
- Quarterly waterflow alarm test
- Waterflow alarm devices and valve supervisory switches are tested quarterly by opening the inspector's test valve and confirming local alarm and remote signal reception.
- Five-year internal inspection
- Dry pipe and preaction piping, and piping in corrosive environments, is internally examined at 5-year intervals, with corrosion findings and corrective actions documented.
- Spare sprinkler stock
- At least 6 spare sprinklers for systems up to 300 sprinklers, 12 for 301 to 1000, and 24 above 1000, matching installed types and temperature ratings.
- Gauge calibration interval
- System gauges are replaced or recalibrated at 5-year intervals; any gauge with a broken lens or a reading off zero is replaced immediately.
- ITM record retention
- Inspection and test records are kept at least one year and made available to the AHJ; the system owner retains copies of all completed inspection and testing documentation.
- Lockout tagout
- An energy isolation procedure using locks and tags on pumps, valves, or electrical disconnects before maintenance, preventing unexpected energization or release of stored energy.
- Fire watch during impairment
- A person assigned to patrol the affected area with extinguishing equipment, maintaining a continuous watch while protection is out of service and until it is restored.
- Freeze protection risk
- Wet pipe systems in unheated spaces are protected by dry pipe, preaction, listed antifreeze, or heat; freezing ruptures pipe and disables protection, a major property risk.
- Backflow prevention
- An assembly that prevents reverse flow of nonpotable water into the potable supply, tested annually by a certified tester and reported to the water authority.
- Working plans
- Scaled drawings submitted for approval before installation, showing occupancy, sprinkler layout, pipe sizes, hydraulic calculations, and a bill of materials.
- Hydraulic design placard
- A sign at the riser stating design density, operating area, hose stream allowance, and duration so future modifications can be checked against the original design basis.
- Material and test certificate
- The contractor's signed record documenting flushing and hydrostatic testing, including system pressure, test duration, results, and the signature submitted to the AHJ.
- As-built drawings
- Record drawings updated to reflect field conditions and approved changes; they are the reference baseline for future inspection, maintenance, and modification work.