ABBE L6 Building Surveying: Contract Administration and Project Management

ABBE L6 Building Surveying · Work through your exam, one topic at a time.

All guide sections

Contract Administration and Project Management

Managing the works

You must understand the main procurement routes and contract forms and the surveyor's role in administering them:

  • Procurement: traditional, design-and-build, management contracting; single vs two-stage tendering.
  • Contract forms: JCT and NEC families; the difference between lump sum, measure and value, and cost-plus.
  • Administration: instructions, variations, valuations, interim certificates, retention, practical completion, defects liability, and final accounts.
  • Programme and risk: critical path, float, risk registers, change control.

Key concepts:

  • Variations must be instructed in writing by the correct authority.
  • Retention protects the client during the defects period.
  • Practical completion triggers the defects liability period and release of part retention.
  • NEC uses defined events and early warnings; JCT uses architect/contract administrator certification.

Traps in questions

  • Issuing oral instructions that are not confirmed in writing - a classic administration failure.
  • Confusing practical completion with final completion (end of defects period).
  • Assuming the lowest tender is the best value; whole-life cost and quality matter.
  • Ignoring float and the critical path when assessing delay.

Worked rule of thumb

Apply the written-instruction rule: no variation is valid until instructed in writing by the authorised person; confirm verbal instructions immediately and value them before execution where possible.

Example: A contractor proceeds on a verbal change; the contract administrator must confirm in writing, assess cost/time impact, and issue a valuation - otherwise the final account is disputed.