AM2 / AM2S flashcards
AM2 / AM2S · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Proving unit
- A known voltage source used to confirm that a voltage indicator operates correctly before and after testing a circuit for dead.
- GS38 voltage indicator
- Safety standard for test probes requiring fused leads, finger guards and limited exposed metal, used for proving dead on low-voltage systems.
- Hierarchy of control
- Risk control order: eliminate the hazard, substitute, apply engineering controls, use administrative controls, then PPE as the last resort.
- EAWR 1989
- Electricity at Work Regulations require work to be dead where reasonably practicable; live work only if justified, authorised and controlled.
- Lock-off device
- A lockable isolation device applied to a breaker or switch so that the circuit cannot be re-energised while a person works.
- Reference Method C
- Installation method for flat twin-and-earth cable clipped direct to a surface, used to select current-carrying capacity from BS 7671 tables.
- Correction factor Ca
- Factor applied to cable current-carrying capacity for ambient temperature; it is tabulated in BS 7671 and reduces capacity as temperature rises.
- Main protective bonding
- Connection of extraneous conductive parts to the main earthing terminal; minimum 6 mm² copper, or 10 mm² for PME supplies.
- Ring final circuit
- A 32 A socket circuit wired in 2.5 mm² line and neutral with a 1.5 mm² CPC, limited to 100 m² floor area.
- Conduit fill factor
- BS 7671 limits conductor space in conduit to 40 percent of internal cross-sectional area to allow drawing in and heat dissipation.
- CPC sizing rule
- For line conductors up to 16 mm² the circuit protective conductor may be the same size; larger lines follow Table 54.7.
- Insulation resistance test
- Measured at 500 V DC for 230/400 V circuits; the minimum acceptable value is 1 MΩ per BS 7671 Table 64.1.
- R1 plus R2 test
- Continuity measurement of line and protective conductors connected together, confirming CPC continuity and giving earth fault loop resistance.
- Ring final cross-connection
- Connect line to neutral and neutral to line at the board; expected R1 + R2 equals (r1 + r2) divided by four.
- External earth loop impedance
- Ze is measured at the origin with main bonding disconnected and is used to confirm the supply earth fault loop path.
- RCD five-times test
- At five times rated residual current a 30 mA RCD should trip within 40 ms; at rated current it should trip within 300 ms.
- Electrical Installation Certificate
- Issued for new installation work or major alteration, supported by schedules of test results and signed declarations of design, construction and verification.
- Prove dead sequence
- Test between line and neutral, line and earth, and neutral and earth with an approved two-pole indicator, then re-prove the indicator.
- Borrowed neutral
- A neutral connected to a different circuit's line conductor, causing the isolated circuit to remain live; check by isolating and testing all conductors.
- Multi-lock hasp
- A lockout accessory allowing several workers to fit personal padlocks to one isolation point so the supply cannot be restored.
- Isolation point
- The device used to disconnect all live conductors from the supply; it must be identified, locked and proved dead before work.
- Backfeed risk
- Unexpected energisation from generators, PV, UPS or adjacent circuits; isolate all sources and prove dead at the point of work.
- Half-split method
- Fault-finding technique that divides a circuit into sections and tests each half to locate an open circuit or low insulation fault.
- High resistance joint
- A loose or corroded connection causing volt drop and heat; identified by continuity resistance and voltage-drop tests under load.
- Nuisance RCD tripping
- Cumulative earth leakage from several circuits or appliances exceeding the RCD threshold; isolate circuits and test leakage individually.
- Short circuit fault
- A low-resistance path between line and neutral or earth causing immediate high current and protective device operation.
- Voltage drop formula
- Voltage drop in volts equals millivolts per amp per metre times design current times cable length divided by 1000.
- Part P notification
- In England and Wales, notifiable domestic electrical work must be notified to building control or carried out by a registered competent person.
- BS 7671 status
- The IET Wiring Regulations are not statute law but provide the accepted standard for complying with electricity safety legislation.
- Health and Safety at Work Act
- 1974 Act imposing duties on employers and self-employed persons to ensure health, safety and welfare of employees and others affected.
- CDM 2015
- Construction Design and Management Regulations require coordination of health and safety throughout a construction project, including electrical risks.
- Part M
- Building Regulation requiring reasonable provision for access and use of buildings, affecting socket, switch and consumer unit heights.