Week 1

F-gas and ODS regulations, legal duties and environmental impact

  • List the core legal duties of a certified F-gas operative and state which activities are restricted to certified personnel and certified companies

  • Explain global warming potential and ozone depletion potential, then rank the main refrigerant families (HFCs, HFOs, CO2, ammonia, hydrocarbons, CFCs/HCFCs) by environmental impact

  • Convert refrigerant charge weights into CO2-equivalent tonnes using GWP values and apply the resulting thresholds to real system examples

  • Identify the environmental consequences of refrigerant venting and the correct legal route for disposing of recovered ODS and F-gas

  • Summarise the penalties, enforcement routes and record-retention periods that apply to non-compliance

Your checkpoint

A one-page GWP-to-CO2e conversion table with five worked examples plus 15 self-written questions on legal duties, scored at 80% or better

Week 2

F-gas and ODS regulations, legal duties and environmental impact & Leak checking, containment, record keeping and reporting obligations

  • Build a leak-check frequency matrix from CO2e band, system type and whether a leak detection system is fitted

  • State the statutory intervals for re-checking after a leak is repaired and for verifying that a repaired leak is sealed

  • Complete a compliant F-gas equipment record for a fictitious system, including charge history, leak checks and repairs

  • Describe who must be notified, in what form and within what timeframe when a reportable leak occurs

  • Explain the labelling, containment and record-transfer duties that apply when a system changes hands

Your checkpoint

A leak-check schedule matrix covering five system sizes plus a fully completed sample equipment record and leak report

Week 3

Installation, commissioning, pressure testing and evacuation of RAC systems

  • Plan the installation sequence for a split and a small packaged system, listing the isolation, brazing, pipework and electrical checks required at each stage

  • Calculate strength-test and tightness-test pressures for R410A, R32 and R134a systems and distinguish when each test is mandatory

  • Specify the correct test gas, regulator, gauge class and test duration, and state why oxygen and air must never be used

  • Write an evacuation and dehydration procedure including triple evacuation, vacuum hold test and micron-level acceptance criteria

  • Draft a commissioning checklist covering charge verification, superheat/subcool, safety controls and handover documentation

Your checkpoint

A written commissioning procedure with calculated test pressures and vacuum targets for three refrigerants, plus 15 pressure and vacuum calculation problems solved correctly

Week 4

Installation, commissioning, pressure testing and evacuation of RAC systems & Servicing, maintenance, refrigerant recovery, recycling and decommissioning

  • Explain why pipework is nitrogen-purged during brazing and describe the checks that detect a poor purge

  • Select and justify test instruments, stating the accuracy, calibration and range requirements for pressure and vacuum measurement

  • Compare vapour, liquid and push-pull recovery methods and select the right one for a given system and refrigerant state

  • Calculate the maximum fill weight for a recovery cylinder from its water capacity and the refrigerant density, applying the 80% fill limit

  • Identify the hazards and controls for recovering a flammable refrigerant from a system containing residual charge

Your checkpoint

A timed 40-question mixed paper across domains 1, 3 and 4, completed in 60 minutes with a score of 75% or better and an error log in your own words

Week 5

Servicing, maintenance, refrigerant recovery, recycling and decommissioning

  • Distinguish recovery, recycling, reclaiming and destruction, and state which processes a Cat I operative may carry out on site

  • Write a decommissioning procedure for a system containing ODS, including pump-down, isolation, oil handling and cylinder labelling

  • Describe how recovered refrigerant is documented, stored, transported and consigned for destruction or reclaim

  • Explain the risks of mixing refrigerant types and the checks that prevent cross-contamination of recovery cylinders

  • Outline the correct handling and disposal routes for contaminated oil, filter driers and contaminated components

Your checkpoint

A written recovery and decommissioning procedure plus 12 scenario questions on recovered-refrigerant handling, scored at 80% or better

Week 6

Refrigerant safety, cylinder handling, PPE and risk assessment

  • Classify the main refrigerants by ASHRAE safety group and state the practical consequence of each class for working methods

  • Select appropriate PPE for a given task and explain the limitations of each item, including glove type and eye protection during liquid contact

  • Complete a five-step risk assessment and a dynamic on-site assessment for a live plant room job

  • Describe safe cylinder handling, storage, inspection and transport requirements, including valve protection and temperature limits

  • Identify asphyxiation, flammability, pressure-release, freeze-burn and electrical hazards and specify a control for each

Your checkpoint

Two completed risk assessments - one for an A2L system and one for an A3 system - plus a PPE selection matrix covering five different tasks

Week 7

Refrigerant safety, cylinder handling, PPE and risk assessment & Leak checking, containment, record keeping and reporting obligations

  • Work through scenario questions that combine safety decisions with leak-checking and record-keeping duties

  • Re-test every goal from weeks 1 to 6 and rank the weakest six by mock-question error rate

  • Practise explaining legal and technical points aloud in the concise style required by written exam answers

  • Review the error log and rewrite every missed question with the correct reasoning

Your checkpoint

A 60-question mixed bank across all five domains scored at 80% or better, with a dated error log showing each weak area and the action taken

Week 8

F-gas and ODS regulations, legal duties and environmental impact & Refrigerant safety, cylinder handling, PPE and risk assessment & Leak checking, containment, record keeping and reporting obligations & Installation, commissioning, pressure testing and evacuation of RAC systems & Servicing, maintenance, refrigerant recovery, recycling and decommissioning

  • Sit two full-length timed mock papers under exam conditions and record the score for each domain

  • Revisit the three lowest-scoring domain areas and close each gap with targeted revision

  • Memorise the key numbers - leak-check intervals, CO2e thresholds, test pressures, vacuum limits, cylinder fill limits - and self-test them from memory

  • Confirm the practical tasks and documentation you can perform confidently, and list anything still needing supervised practice

Your checkpoint

Two completed timed mock papers at 85% or better, with a final one-page revision sheet of key figures and a written list of remaining weak points

Milestones

Week 2: Can state the leak-check interval and post-repair re-check timing for any given charge size and system type without notes, and produce a compliant equipment record unaided

Week 4: Scores 75% or better on a timed 40-question paper covering domains 1, 3 and 4, and can calculate a strength-test pressure and a recovery cylinder fill limit correctly

Week 6: Produces a complete risk assessment in under 20 minutes and correctly assigns the safety group and required controls for six named refrigerants