The AACE Certified Scheduling Technician (CST) is a technician-level credential offered by AACE International and listed on the association's site under Technician Certifications, alongside the Certified Cost Technician. It is aimed at practitioners who build, update and maintain project schedules - junior schedulers, planning engineers, project controls technicians and coordinators - who want to show working-level competence rather than the advanced, professional-level knowledge expected of a PSP holder. The AACE CST case studies are 5 cases and about 2,229 words.

1

The 1,850-Activity Water Plant Schedule

Northgate Utilities is expanding a 40 ML/d water treatment plant over 14 months. The contractor's first draft schedule contains 1,850 activities, most at 8-hour task level, on a single 7-day calendar.

448 words, about 2 min
2

Negative Float in a 21-Day Substation Outage

During development of a 21-day substation outage schedule, the scheduler links 'Replace breaker' (10 days) to 'Energize and test' (3 days) with a start-to-start lag of 10 days. 'Energize and test' also carries a start-no-earlier-than constraint of Day 15.

447 words, about 2 min
3

Out-of-Sequence Progress at Month-End

At the month-end update, the data date is 30 September. The schedule shows 22 activities whose successors have actual starts before the predecessors' actual finishes, and 8 activities with actual finishes but no actual starts.

443 words, about 2 min
4

The Critical Path That Is Not the Longest Path

At a monthly review, the contractor reports the project 35 days behind and states the critical path runs through mechanical completion. The owner's analyst finds that the longest path actually runs through electrical commissioning, but that path carries 18 days of total float because of a finish-to-finish relationship and a 10-day lag.

439 words, about 2 min
5

SPI Above One on a Late Project

At a portfolio review, a project shows CPI 0.94 and SPI 1.08, and the project manager reports that the project is ahead of schedule. The CPM forecast, however, shows completion six weeks after the baseline.

452 words, about 2 min