32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Work Breakdown Structure
- A hierarchical decomposition of the total scope of work into manageable deliverables and work packages. It organizes both schedule activities and cost accounts and defines project scope.
- 100% Rule
- A WBS principle requiring that the sum of the work defined in child elements equals 100 percent of the parent element's scope, with no overlap or omitted work between siblings.
- Schedule Basis Document
- A record of the scope, assumptions, constraints, calendars, data sources, and methodologies used to develop the schedule. It supports review, validation, and later forensic analysis.
- Milestone
- A zero-duration activity marking a significant event, decision, or contractual deliverable. It has no work content but consumes no time and is used to track key dates.
- Mandatory Constraint
- A hard constraint that fixes an activity's start or finish to a specific date, overriding network logic. It can create negative float and should be used only when contractually necessary.
- Activity Coding
- A structured scheme of alphanumeric identifiers assigned to activities to enable sorting, filtering, and grouping by WBS, phase, discipline, responsibility, or location in schedule reports.
- Forward Pass
- A CPM calculation that determines each activity's earliest start and earliest finish by moving from project start to finish, using durations, calendars, and predecessor relationships.
- Backward Pass
- A CPM calculation that determines each activity's latest start and latest finish by moving from project finish back to start, using successor relationships and the project completion date.
- Total Float
- The amount of time an activity can be delayed from its early start without delaying the project finish date. Calculated as LS minus ES or LF minus EF.
- Free Float
- The amount of time an activity can be delayed without delaying the early start of any successor. Calculated as the minimum successor early start minus the activity's early finish.
- Critical Path
- The longest continuous sequence of logically linked activities through the network, determining the shortest possible project duration. Activities on it have zero or minimal total float.
- Lag
- A defined waiting period between the finish or start of one activity and the finish or start of its successor. Positive lag adds time; negative lag creates overlap.
- Negative Float
- A condition where an activity's late dates fall before its early dates, usually caused by a constraint or imposed finish date earlier than the logic-driven completion. It signals an impossible schedule.
- Baseline Schedule
- The approved, frozen version of the schedule against which progress and performance are measured. Changes to it require formal change control approval.
- Data Date
- The status date that separates actual progress already recorded from forecast work not yet performed. Also called the status date or time now date.
- Remaining Duration
- The estimated work time still needed to complete an activity, measured from the data date. It is used to forecast the activity's finish during schedule updates.
- Progress Override
- A scheduling option that ignores logic when out-of-sequence work is reported, allowing completed work to be preserved and remaining work to proceed without re-sequencing.
- Retained Logic
- A scheduling option that preserves the original network logic during updates, so remaining work cannot start until its predecessors finish, even if progress is out of sequence.
- Out-of-Sequence Progress
- A condition where an activity starts or finishes before its predecessors are complete, violating the planned logic. It must be resolved during schedule updates.
- Schedule Update
- A periodic revision of the schedule incorporating actual progress, revised durations, and approved changes. It produces a new forecast used for reporting and control.
- Schedule Variance
- The difference between earned value and planned value, expressed in cost or time units. A negative value indicates the project is behind schedule.
- Schedule Performance Index
- The ratio of earned value to planned value. A value below one indicates schedule slippage; above one indicates ahead-of-schedule performance.
- Time Impact Analysis
- A method that inserts a fragnet representing a change or delay into the current schedule and measures the resulting change in project completion to quantify entitlement.
- Earned Schedule
- A time-based extension of earned value that converts earned value into the time at which the planned value was achieved, giving schedule performance in time units.
- Float Consumption
- The reduction of available total float on an activity or path between schedule updates. High consumption indicates increasing schedule risk and reduced flexibility.
- Windows Analysis
- A retrospective delay analysis that divides the project into time windows between updates and compares planned versus as-built schedules to apportion delay among parties.
- Earned Value Management
- An integrated cost and schedule performance technique comparing planned value, earned value, and actual cost to measure progress and forecast outcomes.
- Cost Performance Index
- The ratio of earned value to actual cost. Values below one indicate cost overrun; above one indicate cost efficiency better than planned.
- Budget at Completion
- The total authorized budget for the project, representing the sum of all cost account budgets and the performance measurement baseline.
- Estimate at Completion
- A forecast of the total project cost based on actual costs to date plus the estimated cost to complete remaining work, using a chosen performance factor.
- Management Reserve
- A contingency fund held by management outside the performance measurement baseline for unplanned scope changes and unidentified risks requiring management approval.
- Cost Account
- A control point at the intersection of a WBS element and an organizational unit where budgets and earned value are managed and performance is assessed.