Schedule Planning

  • The 100% rule requires that child WBS elements sum exactly to the parent's scope, with no overlap between siblings and no omitted work.

  • Activity duration formula: Duration = (Quantity of work) ÷ (Crew size × Productivity per unit), then converted to workdays using the assigned calendar.

  • Planning defines what work will be performed and how; scheduling applies logic, durations, and calendars to determine when it will be performed.

  • A milestone is a zero-duration activity representing a significant event or contractual date; it is not a work activity and carries no resources.

  • Hard (mandatory) constraints override network logic and can produce negative float; use them only when externally imposed, such as a contract milestone.

  • The schedule basis document records scope, assumptions, constraints, calendars, data sources, and software settings used to build the schedule.

  • Activity ID coding should be unique and structured so the schedule can be sorted and filtered by WBS, phase, discipline, responsibility, and location.

  • A resource-loaded plan assigns labor, equipment, and materials to activities; the resulting resource histogram drives leveling decisions.

Quick reference

Schedule Development

  • Forward pass: ES = maximum predecessor EF plus lag; EF = ES + duration, with duration computed on the activity's assigned calendar.

  • Backward pass: LF = minimum successor LS minus lag; LS = LF − duration.

  • Total float = LS − ES = LF − EF; free float = minimum successor ES − EF.

  • The critical path is the longest logic path through the network; its length equals the shortest possible project duration.

  • Four relationship types: finish-to-start, start-to-start, finish-to-finish, and start-to-finish; finish-to-start is the default in most schedules.

  • Positive lag adds wait time between activities; negative lag (lead) overlaps them; lags should be justified and minimized.

  • Negative total float means the logic-driven finish is later than an imposed date; resolving it requires re-sequencing, crashing, or fast tracking.

  • An open end is an activity lacking a predecessor or successor; excessive open ends reduce logic validity and can hide the true critical path.

Quick reference

Schedule Maintenance and Control

  • The baseline is the approved, frozen schedule; any change to it must pass through formal change control and be re-approved.

  • The data date (status date) separates recorded actuals from forecast work; all remaining durations are scheduled forward from this date.

  • Remaining duration is the work time still needed from the data date; duration percent complete = (original duration − remaining duration) ÷ original duration.

  • Out-of-sequence progress occurs when a successor starts before its predecessor finishes; it must be resolved using retained logic or progress override.

  • Retained logic preserves the original network logic during updates; progress override ignores logic to accommodate reported out-of-sequence work.

  • Schedule updates follow the contract-specified cycle, commonly monthly, and each update records progress, revised durations, and approved changes.

  • Actual start and actual finish dates are historical facts and are not moved by later updates; only remaining work is rescheduled.

  • A schedule log documents revisions, rationale, and approvals for each update to preserve an audit trail.

Quick reference

Schedule Analysis and Reporting

  • Schedule variance (SV) = BCWP − BCWS; a negative value indicates work is behind the baseline plan.

  • Schedule performance index (SPI) = BCWP ÷ BCWS; SPI below 1.0 indicates slippage, above 1.0 indicates ahead-of-plan progress.

  • Earned schedule converts earned value into time: ES is the date when BCWS equals BCWP, and SPI(t) = ES ÷ actual time.

  • Time impact analysis inserts a fragnet for the change or delay into the current schedule and measures the resulting movement of the completion date.

  • Windows analysis compares successive schedule updates over defined periods to apportion delay among parties retrospectively.

  • Float trend analysis compares baseline total float with current total float; declining float signals increasing schedule risk and reduced flexibility.

  • Common reports include the Gantt chart, network diagram, resource histogram, cash-flow S-curve, and critical path report.

  • Resource leveling shifts activities within their float to resolve peaks; if float is insufficient, the project completion date may extend.

Quick reference

Project Controls Fundamentals

  • Earned value terms: planned value (BCWS), earned value (BCWP), and actual cost (ACWP); all performance metrics derive from these three.

  • Cost variance = EV − AC; cost performance index = EV ÷ AC; CPI below 1.0 indicates cost overrun.

  • Estimate at completion = AC + (BAC − EV) ÷ CPI when current cost performance is expected to continue.

  • Estimate to complete = EAC − AC; variance at completion = BAC − EAC.

  • The WBS is the common framework linking scope, schedule activities, cost accounts, and earned value measurement.

  • A cost account is the control point where a WBS element meets an organizational unit; it is where budgets and earned value are managed.

  • Management reserve sits outside the performance measurement baseline for unidentified risks; contingency sits inside for identified risks.

  • Integrated change control evaluates scope, schedule, cost, and risk impacts before approving any change to the baseline.