AACE PRMP study materials
AACE PRMP study resources

AACE PRMP cheat sheet

AACE PRMP · Keep the key ideas within reach.

Quick reference

Schedule Planning

  • Planning defines scope, WBS, milestones, calendars, coding, resources, risks, and reporting needs before schedule model construction.

  • WBS 100% rule: the hierarchy includes all project scope and only project scope; each work package is assignable, measurable, and uniquely coded.

  • Activity definition rule: each schedule activity has a unique ID, clear scope, duration basis, responsible owner, and one or more logic ties unless a justified open end exists.

  • Calendar rule: activity duration is calculated on its assigned calendar; resource calendars can restrict working time and increase duration when resources are assigned.

  • Coding rule: standardized activity attributes such as phase, area, discipline, work type, and responsibility enable filtering, grouping, earned-value mapping, and reporting.

  • Milestone rule: contractual, approval, and handover milestones are zero-duration checkpoints unless the contract explicitly defines otherwise.

  • Schedule basis content: scope, assumptions, exclusions, constraints, calendars, resource plan, risk allowances, estimating basis, and reporting requirements.

  • Planning sequence: WBS to activity list to sequencing to duration estimating to resource assignment to schedule calculation to quality review to baseline approval.

Quick reference

Schedule Development

  • Forward pass: ES = max(EF of predecessors + lag); EF = ES + duration using the activity calendar.

  • Backward pass: LF = min(LS of successors minus lag); LS = LF minus duration; total float = LS minus ES = LF minus EF.

  • Free float = min(ES of successors) minus EF, adjusted for lag; zero free float means the activity consumes all float before delaying a successor.

  • Relationship types are FS, SS, FF, and SF; lag adds time between linked activities, while lead reduces the logical gap and can hide missing activities.

  • Negative total float indicates a constraint, imposed date, or logic condition prevents meeting a required date under the current schedule.

  • Resource leveling can change the critical path and completion date; resource smoothing adjusts timing within available float without changing the completion date.

  • PERT expected duration = (O + 4M + P) / 6; standard deviation = (P minus O) / 6 for a three-point duration estimate.

  • Schedule quality rule: no unjustified open ends, negative lags, excessive constraints, or missing logic; the critical path must be continuous from start to finish.

Quick reference

Schedule Maintenance and Control

  • Progress rule: measure activity percent complete by duration, quantity installed, or milestone completion; cost-based percent complete is not a schedule progress measure.

  • Data date rule: actuals are recorded through the data date; remaining durations and forecast dates are calculated from that cutoff, not from the report issue date.

  • Out-of-sequence progress: when a successor starts before its predecessor finishes, a documented rule is applied; retaining logic and revising remaining work are common treatments.

  • Update cycle inputs include actual start and finish dates, remaining duration, revised logic, calendars, resources, and approved changes; the output is a recalculated controlled schedule.

  • Cost-based SPI = EV / PV; time-based SPI(t) = earned schedule / actual time; values below 1.0 indicate behind plan and above 1.0 indicate ahead.

  • Schedule variance in time = current or forecast date minus baseline date; the sign convention must be stated so negative and positive variances are interpreted consistently.

  • Change control rule: only approved changes are incorporated into the controlled schedule; re-baselining requires formal authorization and preserves the prior baseline for audit.

  • Look-ahead planning typically covers a one- to six-week window and identifies near-term constraints, resource needs, and activities required to protect the critical path.

Quick reference

Schedule Analysis

  • Critical path rule: the critical path is the longest logic path through the network; it determines the calculated project duration and can change after progress updates.

  • Total float is path-dependent; an activity's total float can be consumed by other activities on the same path, so float is not a private activity attribute.

  • Near-critical path rule: paths with low total float are monitored because small duration growth or logic changes can transfer criticality and delay completion.

  • Time impact analysis inserts a fragnet representing the event into a contemporaneous schedule at the event time and calculates the change in forecast completion.

  • Delay analysis methods include as-planned versus as-built, impacted as-planned, collapsed as-built, and time impact analysis; method selection depends on records and contract rules.

  • Concurrent delay rule: overlapping independent delay events require separate timing and causation analysis; responsibility is determined by contract and documented facts.

  • Monte Carlo simulation samples duration and risk distributions to produce a completion-date distribution and probability-based dates such as P50 and P80.

  • Schedule audit checks logic continuity, open ends, constraints, lags, calendars, durations, float, critical path, resource loading, and baseline compliance.

Quick reference

Schedule Communication and Reporting

  • Reporting hierarchy: executive summary, dashboard, milestone status, critical path and float summary, variance analysis, detailed schedule, and supporting narrative.

  • S-curve rule: plot cumulative planned versus actual progress against time; the vertical gap shows schedule variance and the horizontal gap estimates time variance.

  • Gantt charts show timing and progress clearly; network diagrams show logic and critical path; tabular reports show detailed data for analysis.

  • Variance reporting rule: define thresholds for schedule deviation and report exceptions above threshold with cause, impact, and corrective action.

  • Forecast reporting distinguishes data-date status from future forecast; forecast dates are projections, not actual commitments, unless contractually stated.

  • Milestone trend chart: plots forecast dates for the same milestones across updates; upward drift indicates recurring slippage and downward drift indicates recovery.

  • Schedule risk reporting includes deterministic dates, probabilistic confidence dates, top risk drivers, and the contingency or float available.

  • Narrative content includes data date, baseline, current and forecast dates, critical path changes, variance causes, risks, decisions needed, and corrective actions.