AACE PRMP · Get comfortable with the vocabulary.

Work Breakdown Structure (WBS)

A hierarchical breakdown of total project scope into manageable, deliverable-oriented pieces. It organizes work so activities can be defined, estimated, scheduled, and controlled at a consistent level of detail.

Related: Activity, Rolling Wave Planning
Activity

A discrete, identifiable unit of work with a defined scope, duration, and expected start and finish. Activities are the building blocks scheduled in a network and are usually tied to a WBS element.

Related: Work Breakdown Structure (WBS), Milestone
Milestone

A zero-duration point in time marking a significant event, decision, or contractual deliverable. Milestones show achievement rather than work, and are often used as payment or approval gates.

Related: Activity, Schedule Baseline
Project Calendar

A defined pattern of working and non-working periods that determines when activities may be performed. Calendars account for weekends, holidays, shifts, and weather downtime in duration calculations.

Related: Activity, Resource Leveling
Rolling Wave Planning

A progressive elaboration technique where near-term work is planned in detail while later work remains at a summary level. Detail is added as facts become clearer, usually at each phase gate.

Related: Work Breakdown Structure (WBS), Look-Ahead Schedule
Logic Diagram

A graphical model showing activities as nodes and their dependencies as connecting arrows. It defines the order in which work must be performed and forms the basis of the schedule network.

Related: Precedence Diagramming Method (PDM), Dangling Activity
Precedence Diagramming Method (PDM)

A scheduling technique that builds a network using nodes for activities and arrows for dependencies. Each relationship carries a type and may include lag between predecessor and successor.

Related: Logic Diagram, Finish-to-Start (FS), Lag
Finish-to-Start (FS)

A dependency where a successor activity cannot begin until its predecessor finishes. It is the most common relationship and the default assumption in most scheduling software.

Related: Precedence Diagramming Method (PDM), Fast Tracking
Lag

A planned waiting period inserted between a predecessor and successor, such as cure time for concrete. A negative lag, called lead, allows the successor to start before the predecessor finishes.

Related: Finish-to-Start (FS), Precedence Diagramming Method (PDM)
Critical Path Method (CPM)

A deterministic technique that calculates early and late dates through forward and backward passes, then identifies the longest path through the network. That path sets the shortest possible project duration.

Related: Critical Path, Forward Pass, Backward Pass
Critical Path

The continuous chain of activities with the least total float, usually zero, that determines the project finish date. Any delay on this path delays the project unless the schedule is adjusted.

Related: Total Float, Critical Path Method (CPM)
Total Float

The amount of time an activity can slip without delaying the project completion date. It equals late start minus early start, or late finish minus early finish.

Related: Free Float, Critical Path, Float Ownership
Free Float

The amount of time an activity can slip without delaying the early start of any successor. It is always less than or equal to total float.

Related: Total Float
Forward Pass

A calculation that moves from the project start to the finish, assigning each activity its earliest possible start and finish based on predecessor logic and calendars.

Related: Backward Pass, Critical Path Method (CPM)
Backward Pass

A calculation that works from the project finish back to the start, assigning each activity its latest allowable start and finish without delaying the project.

Related: Forward Pass, Total Float
Schedule Baseline

The approved, time-phased version of the schedule against which progress and performance are measured. Changes require formal change control and produce a new baseline revision.

Related: Data Date, Schedule Variance (SV)
Data Date

The point in time at which schedule status is recorded, separating actual work already performed from remaining forecast work. Also called the status date or time-now date.

Related: Percent Complete, Schedule Baseline
Resource Leveling

A technique that adjusts activity start and finish dates to resolve resource over-allocation, often extending the project duration. It balances demand against available capacity while respecting logic where possible.

Related: Resource Smoothing, Critical Path
Resource Smoothing

A technique that shifts activities within their available float to even out resource demand without changing the project finish date. Unlike leveling, it cannot extend the critical path.

Related: Resource Leveling, Total Float
Schedule Constraint

A restriction imposed on an activity's dates, such as start-no-earlier-than or finish-on-a-date. Constraints override logic and can create negative float or hide true schedule flexibility.

Related: Total Float, Data Date
Schedule Compression

Reducing the project duration without cutting scope, typically through crashing or fast tracking. Compression usually raises cost, risk, or both and must be evaluated carefully.

Related: Crashing, Fast Tracking
Crashing

Adding resources, working overtime, or paying premiums to shorten activity durations on the critical path. Crashing is chosen where the cost per day saved is lowest.

Related: Schedule Compression, Critical Path
Fast Tracking

Overlapping activities that would normally run in sequence, converting finish-to-start links into parallel or start-to-start work. It shortens duration but increases coordination risk and rework potential.

Related: Schedule Compression, Finish-to-Start (FS)
Percent Complete

A measure of work accomplished on an activity, expressed as duration, units, or physical progress. Duration-based percent complete can mislead when effort is unevenly distributed.

Related: Data Date, Schedule Variance (SV)
Schedule Variance (SV)

The difference between earned value and planned value for scheduled work. A negative value indicates that work is behind the baseline plan.

Related: Schedule Performance Index (SPI), Earned Value Management (EVM)
Schedule Performance Index (SPI)

The ratio of earned value to planned value, showing how efficiently schedule is being executed. Values below one mean the project is behind plan.

Related: Schedule Variance (SV), Earned Value Management (EVM)
Earned Value Management (EVM)

A method that integrates scope, schedule, and cost by comparing planned, earned, and actual values. It provides objective indicators of performance and supports forecasts.

Related: Schedule Variance (SV), Schedule Performance Index (SPI)
Time Impact Analysis (TIA)

A prospective delay analysis that inserts a modeled delay event into a current schedule update to measure its effect on completion. It is commonly used to support time extension requests.

Related: Forensic Schedule Analysis, Schedule Baseline
Forensic Schedule Analysis

A retrospective, systematic examination of schedule records to apportion delay responsibility among parties, often for claims or disputes. Methods include as-planned versus as-built and window analyses.

Related: Time Impact Analysis (TIA), As-Built Schedule
As-Built Schedule

A record of when work actually started and finished, reconstructed from progress records. It supports claims analysis, lessons learned, and comparison against the baseline.

Related: Forensic Schedule Analysis, Schedule Baseline
Schedule Risk Analysis

A quantitative technique, often Monte Carlo simulation, that applies uncertainty ranges to durations and logic to produce a distribution of possible completion dates.

Related: Critical Path, Schedule Baseline
Look-Ahead Schedule

A short-interval extract of upcoming work, usually three to six weeks, used by field teams to plan crews, materials, and equipment. It translates the master schedule into executable commitments.

Related: Rolling Wave Planning, Schedule Narrative
S-Curve

A graph plotting cumulative progress, cost, or hours over time, typically shaped like the letter S. It allows quick visual comparison of planned versus actual performance.

Related: Percent Complete, Schedule Variance (SV)
Basis of Schedule

A document recording the assumptions, calendars, logic, resources, and constraints used to build the schedule. It gives reviewers the context needed to interpret and trust the plan.

Related: Schedule Narrative, Schedule Baseline
Dangling Activity

An activity lacking a predecessor or successor, creating an open end in the network. Dangling logic distorts float calculations and undermines critical path validity.

Related: Logic Diagram, Critical Path
Resource Loading

Assigning quantities of labor, equipment, or cost to activities over their durations. Loading enables histograms, leveling, and earned value analysis.

Related: Resource Leveling, Percent Complete
Schedule Narrative

A written summary accompanying a schedule submission that explains progress, changes, variances, and forecast issues. It helps reviewers understand the story behind the dates.

Related: Basis of Schedule, Look-Ahead Schedule
Float Ownership

The contractual question of which party controls the use of total float on shared activities. Clear ownership rules prevent disputes when delays consume float.

Related: Total Float, Forensic Schedule Analysis