32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Schedule planning
The process that defines project scope, execution strategy, milestones, calendars, coding, resources, risks, and reporting needs before a schedule model is built.
Work breakdown structure
A hierarchical decomposition of project scope into manageable deliverables and work packages; the 100 percent rule requires all scope and only scope be represented.
Activity coding
Assignment of standardized attributes such as phase, area, responsible party, and work type to activities so schedules can be filtered, grouped, and analyzed consistently.
Project calendar
A defined pattern of working and nonworking periods used to calculate activity durations; resource calendars may further limit when assigned resources can work.
Schedule basis
A document recording assumptions, exclusions, constraints, calendars, resource plan, risk allowances, and reporting requirements supporting a schedule model and its baseline.
Milestone
A significant schedule checkpoint, often zero duration, marking a contractual, approval, handover, or decision event; it has no work but represents a measurable state.
Open end
An activity lacking a predecessor or successor, which can distort critical path and float calculations; schedules are reviewed to eliminate unjustified open ends.
Forward pass
A CPM calculation that determines each activity's earliest start and finish by moving from project start through logic, using max predecessor finish plus lag.
Backward pass
A CPM calculation that determines each activity's latest finish and start by moving from project finish through logic, using min successor start minus lag.
Total float
The time an activity can be delayed without delaying the project finish, calculated as late start minus early start or late finish minus early finish.
Free float
The time an activity can be delayed without delaying any successor's early start, calculated from the minimum successor early start minus the activity's early finish.
Resource leveling
A scheduling technique that adjusts activity timing to resolve resource over-allocation; it may extend the project finish or change the critical path.
PERT expected duration
A weighted three-point estimate calculated as optimistic plus four times most likely plus pessimistic, divided by six, used for probabilistic duration planning.
Schedule baseline
An approved, controlled snapshot of the schedule model used to measure progress and performance; changes require formal change control and authorized re-baselining.
Data date
The status cutoff date through which actual progress is recorded and from which remaining work is forecast; also called the status date.
Out-of-sequence progress
Progress recorded on an activity before its predecessor is complete; it requires a documented rule because it can distort logic, float, and forecast dates.
Schedule update cycle
The recurring process of collecting actual dates and remaining durations, revising logic and resources, recalculating the schedule, and issuing a controlled update.
Schedule variance
A comparison of current or forecast dates with baseline dates; positive time variance usually means later than baseline, depending on the sign convention used.
Earned schedule SPIt
A time-based index calculated as earned schedule divided by actual time; values below one indicate schedule behind plan and above one indicate ahead.
Change control
A formal process for evaluating, approving, and incorporating schedule changes with traceability; only authorized changes may alter the approved baseline.
Critical path
The longest continuous logic path through the schedule network, which determines the calculated project duration; a project can have multiple critical paths.
Near-critical path
A logic path with total float small enough that minor progress or logic changes could make it critical; it is monitored for schedule risk.
Time impact analysis
A delay analysis method that inserts a fragnet representing an event into a contemporaneous schedule and calculates the event's effect on completion.
Fragnet
A small schedule network added to an existing schedule to model a specific change, delay, or scope event for impact analysis.
Monte Carlo schedule risk
A probabilistic simulation that samples duration and risk distributions many times to produce a completion-date distribution and confidence levels.
Concurrent delay
Independent delays occurring at the same time that affect completion; contractual rules determine responsibility and apportionment, so analysis must document timing and causation.
Schedule narrative
A written report explaining status, forecast, variances, critical path changes, risks, and corrective actions so readers can interpret schedule data correctly.
Milestone trend chart
A graph plotting forecast milestone dates over successive updates; diverging lines reveal recurring slippage or improvement before final completion is affected.
Schedule dashboard
A concise visual summary of key schedule indicators, milestones, critical path, float, and risks tailored to management review and decision-making.
Forecast completion date
The projected project finish derived from current progress, remaining durations, logic, calendars, and constraints at the data date.
Exception reporting
Reporting that highlights schedule variances beyond defined thresholds, allowing management to focus on deviations rather than every activity detail.
Confidence level date
A completion date associated with a probability from schedule risk analysis, such as P50 or P80, used to communicate schedule uncertainty.