ACI Tilt-Up Supervisor study materials
ACI Tilt-Up Supervisor study resources

ACI Tilt-Up Supervisor cheat sheet

ACI Tilt-Up Supervisor · Keep the key ideas within reach.

Quick reference

Tilt-Up Planning, Site Preparation, and Layout

  • Casting bed layout must place panel faces within crane reach at the minimum and maximum lift radii used in the lift plan; verify radius at the pick point, not the center of the panel.

  • Panel layout sequence follows erection order: panels cast farthest from the building footprint are typically erected first when the crane must reach over them.

  • Casting surface must be level within 1/4 in. in 10 ft unless the project specifies tighter; verify with a 10-ft straightedge before setting edge forms.

  • Locate all underground utilities, conduits, and site drainage before placing casting beds; a 3-ft minimum clear zone from bed edges to obstructions is a common planning rule.

  • Form a site plan showing crane positions, outrigger footprints, swing radius, laydown areas, and access roads; outrigger loads must be checked against soil bearing capacity.

  • Panel identification marks are placed on the panel's non-exposed face and must match the erection drawings; mark orientation arrows so panels are set with the correct face out.

  • Dunnage and casting bed subgrade must be compacted and stable; differential settlement under a bed causes panel warping and thickness variation.

  • Coordinate casting bed location with the building's slab-on-grade footprint so beds can later be removed without damaging finished slabs or footings.

  • Survey control points must be established and protected before layout; all panel corners and embed locations are set from these controls.

Quick reference

Foundations, Slabs-on-Grade, and Panel Casting Beds

  • Footing bearing capacity and size are governed by the structural design; soil bearing values must be confirmed by geotechnical report before excavation acceptance.

  • Slab-on-grade vapor retarder is typically 10-15 mil and must be continuous with sealed laps; punctures are repaired before concrete placement.

  • Casting bed flatness tolerance is commonly 1/4 in. in 10 ft; beds exceeding tolerance produce panel bow and joint misalignment at erection.

  • Bond breaker application rate follows the manufacturer's coverage; two coats at right angles are common where one coat is insufficient.

  • Casting bed edges must be square and straight within 1/8 in. in 10 ft to keep panel geometry true; check diagonals for square.

  • Anchor bolt and embed locations in foundations are set from survey control with tolerance typically 1/4 in. horizontal unless structural drawings specify otherwise.

  • Concrete casting bed slabs are typically designed for the panel weight plus construction live load; point loads from lifting inserts and strongbacks must be considered.

  • Footing excavation bottoms are protected from disturbance; over-excavation is backfilled with compacted engineered fill, not loose spoils.

  • Curing of cast-in-place foundations follows the specified method; cold-weather protection is required when ambient falls below 40 F unless otherwise specified.

Quick reference

Formwork, Edge Forms, and Panel Geometry

  • Edge forms define panel thickness and perimeter; they are braced to resist concrete pressure and must not deflect more than 1/8 in. under placement loads.

  • Panel thickness tolerance is commonly plus or minus 1/4 in.; measure at multiple points along the perimeter.

  • Chamfers at panel edges are typically 3/4 in. unless architectural drawings show otherwise; chamfer strips are set on the exposed face side.

  • Rustication and reveal strips are attached to the casting surface, not the edge form, so they appear on the exposed face.

  • Form release agent is applied to edge forms and casting surface per manufacturer; excess pooling must be removed before reinforcement placement.

  • Panel length and width tolerances are commonly plus or minus 1/2 in.; diagonal measurements confirm squareness.

  • Window, door, and opening blockouts are located from panel datum lines and checked against erection drawings before concrete placement.

  • Edge form removal time depends on concrete strength; forms are typically stripped when concrete reaches 500 psi or per project specification.

  • Form joints must be tight to prevent paste leakage, which causes honeycomb and surface defects on the exposed face.

Quick reference

Reinforcement, Embeds, Inserts, and Connection Hardware

  • Reinforcement cover on the exposed face is set by exposure class; typical tilt-up cover is 3/4 in. to 1-1/2 in. depending on exposure and member.

  • Lifting inserts are located per the lift design; insert capacity must exceed the calculated lifting load with the specified factor of safety.

  • Embed plates for structural connections are set to template and verified for elevation, plan location, and projection before concrete placement.

  • Weld plates and headed studs must develop the design load; stud spacing and embedment depth follow the connection design.

  • Brace anchor embeds are located on the panel's interior face at the heights shown on the bracing plan; location error changes brace angle and load.

  • Reinforcement splices and development lengths follow ACI 318 provisions unless project specifications are more restrictive.

  • Coil inserts, ferrule loops, and lifting hardware are inspected for thread condition and orientation; damaged hardware is replaced, not reused.

  • Electrical and plumbing embeds in panels are coordinated with the trade drawings and capped to prevent concrete intrusion.

  • Post-installed anchors in cured panels require edge distance and spacing checks against the manufacturer's published values.

Quick reference

Concrete Materials, Placement, Finishing, and Curing

  • Slump for tilt-up panels is typically 4-6 in. unless a plasticizer is used; verify against the approved mix design.

  • Maximum aggregate size is limited by reinforcement spacing and panel thickness; commonly 3/4 in. or 1 in. for tilt-up.

  • Concrete placement lifts in panels are limited to avoid cold joints; typical practice keeps vertical placement continuous within a panel.

  • Consolidation uses internal vibration at regular spacing; over-vibration causes segregation and surface defects on the exposed face.

  • Finishing of the exposed face is done after screeding and before initial set; troweling is typically avoided on surfaces receiving applied finishes.

  • Curing compound application rate follows the manufacturer; coverage is verified by the square-foot-per-gallon rate.

  • Cold-weather concrete protection is required when ambient falls below 40 F; panels must not be lifted until strength is verified.

  • Hot-weather placement requires evaporation control; evaporation rate above 0.2 lb/sq ft/hr indicates curing and placement precautions.

  • Panel lift strength is verified by field-cured cylinders or maturity testing; the lifting strength is typically 75% of design strength unless the lift design states otherwise.

Quick reference

Lifting and Bracing Design, Rigging, and Hardware

  • Lifting insert capacity is selected using the panel weight multiplied by a dynamic factor; a common design factor is 2:1 on the static load.

  • Panel weight equals volume times concrete unit weight, typically 150 lb/cu ft; include embeds, insulation, and applied finishes.

  • Number and location of lifting points are set so the panel's center of gravity is balanced; pick points are symmetric about the centroid.

  • Brace design uses the panel as a vertical cantilever; brace loads include wind and construction loads per the bracing plan.

  • Brace angle affects capacity: braces are most efficient near 45 degrees; angles steeper than 60 degrees from horizontal reduce capacity.

  • Rigging hardware including slings, shackles, and spreader beams is inspected before each lift; damaged gear is removed from service.

  • Spreader beams are used where sling angles would induce excessive compression or bending in the panel.

  • Lifting hardware is proof-tested per the manufacturer; field-fabricated lifting devices require engineering approval.

  • Brace anchor design considers pullout, concrete breakout, and steel capacity; the controlling mode governs the required embed.

Quick reference

Panel Erection, Lifting Operations, and Bracing Installation

  • Panels are lifted only after concrete strength is verified by test cylinders or maturity method meeting the lift design requirement.

  • The crane operator and rigger maintain communication by radio or hand signals per the standard signal chart; one designated signal person.

  • Panels are set on shims or leveling devices at the foundation line; final elevation and plumb are verified before braces are attached.

  • Braces are installed and snugged before the crane releases the panel; at least two braces per panel are common, with three for tall or narrow panels.

  • Brace base plates are anchored to the slab or foundation with the specified anchors; temporary anchors are not substituted without approval.

  • Plumb tolerance for erected panels is typically 1/4 in. in 10 ft; final plumb is verified after all braces are installed.

  • Panels are not left unbraced overnight; if braces cannot be installed, the panel is not released from the crane.

  • Wind speed limits for lifting are defined in the lift plan; lifting stops when wind exceeds the plan limit or when panel sail area makes control unsafe.

  • Brace removal follows the permanent connection completion; braces are removed only after the structural connection is completed and approved.

Quick reference

Safety, Job Hazard Analysis, and Lift Planning

  • A job hazard analysis identifies tasks, hazards, controls, and responsible persons; it is reviewed with the crew before work begins.

  • The lift plan includes crane capacity, load weight, radius, boom configuration, outrigger loading, and ground bearing pressure.

  • Crane capacity at the required radius must exceed the load weight plus rigging weight; the load chart is consulted at the actual radius.

  • Exclusion zones are established under and around the lift; personnel do not stand or walk under a suspended panel.

  • Tag lines are used to control panel rotation; personnel handling tag lines stay clear of the panel's swing path.

  • Outrigger mats or cribbing distribute crane loads to the soil; ground bearing pressure is verified against soil capacity.

  • Fall protection is required when working at heights above 6 ft; brace installation at height uses ladders, lifts, or platforms per the plan.

  • Pre-lift meeting confirms roles, signals, communications, and emergency procedures with all crew members.

  • Daily inspections of rigging, crane, and lifting hardware are documented before the first lift of the day.

Quick reference

Inspection, Tolerances, and Quality Assurance

  • Panel thickness tolerance is commonly plus or minus 1/4 in.; panel length and width tolerance is commonly plus or minus 1/2 in.

  • Panel flatness is checked with a 10-ft straightedge; deviation typically does not exceed 1/4 in. in 10 ft.

  • Plumb tolerance for erected panels is typically 1/4 in. in 10 ft, measured along the panel height.

  • Embed and insert location tolerance is commonly plus or minus 1/2 in. unless the connection design requires tighter.

  • Concrete strength acceptance uses field-cured cylinders for lift strength and standard-cured cylinders for design strength.

  • Inspection records include pre-placement reinforcement and embed checks, placement records, curing records, and lift strength verification.

  • Nonconforming panels are documented and dispositioned by the engineer of record; repair procedures are approved before execution.

  • Anchor bolt elevation and projection tolerances are verified before panel erection; out-of-tolerance anchors are corrected per approved detail.

  • Final inspection confirms brace installation, plumb, connection completion, and documentation before brace removal.