ACI Tilt-Up Supervisor study materials
ACI Tilt-Up Supervisor study resources

ACI Tilt-Up Supervisor key terms

ACI Tilt-Up Supervisor · Get comfortable with the vocabulary.

Tilt-up panel

A concrete wall element cast flat on a horizontal bed and then tilted upright into its final vertical position, usually serving as both structural wall and exterior finish.

Related: Casting bed, Lifting insert, Panel erection
Casting bed

The prepared, level, and smooth horizontal surface on or adjacent to the slab where tilt-up panels are formed, reinforced, and cast before lifting.

Related: Bond breaker, Panel layout, Edge form
Bond breaker

A membrane or coating applied to the casting surface so cured panel concrete releases cleanly instead of adhering to the slab or bed beneath it.

Related: Casting bed, Curing compound, Panel finish
Panel layout plan

A drawing that fixes each panel's size, shape, location, orientation, and cast sequence on the site, coordinating openings, joints, and lifting points.

Related: Casting bed, Panel geometry, Shop drawing
Edge form

The perimeter formwork that confines fresh concrete and defines a panel's outer edges, thickness, and any reveals, chamfers, or rustication profiles.

Related: Rustication, Form release agent, Panel geometry
Rustication

A recessed groove or reveal formed in a panel face or joint line to create a shadow line and control the appearance of cracking or joint movement.

Related: Edge form, Reveal, Joint
Form release agent

A material applied to forms and casting surfaces to prevent concrete from bonding, allowing clean stripping without damaging the panel face or edges.

Related: Edge form, Bond breaker, Panel finish
Panel geometry

The dimensional description of a panel including its length, height, thickness, openings, edge profiles, and any non-rectangular shape affecting lifting and stability.

Related: Center of gravity, Panel layout plan, Aspect ratio
Aspect ratio

The ratio of a panel's height to its thickness or width, used to judge slenderness and how vulnerable the panel is to cracking or instability during lifting.

Related: Panel geometry, Lifting stress, Strongback
Center of gravity

The point where a panel's weight is considered concentrated; lifting hardware is arranged around it so the panel hangs level and predictable during hoisting.

Related: Rigging, Lifting insert, Panel geometry
Lifting insert

A cast-in device such as a coil, ferrule, or lifting loop embedded in the panel that transfers hoisting forces from the crane rigging into the concrete.

Related: Embed, Rigging, Lifting stress
Embed

Any item cast into a panel for later connection or support, including plates, angles, anchors, sleeves, and inserts positioned per the shop drawings.

Related: Lifting insert, Connection hardware, Shop drawing
Connection hardware

The plates, angles, bolts, welds, and anchors that tie erected panels to the foundation, roof structure, and adjacent panels after lifting.

Related: Embed, Brace anchor, Weld plate
Brace anchor

A cast-in or post-installed anchor in the slab or panel that receives the temporary bracing used to hold an erected panel plumb and stable.

Related: Temporary bracing, Connection hardware, Embed
Temporary bracing

Adjustable struts and anchors installed to hold a freshly erected panel in position against wind and construction loads until permanent connections are complete.

Related: Brace anchor, Panel erection, Wind load
Strongback

A stiffening beam or truss temporarily or permanently attached to a panel to increase its bending resistance during lifting and erection.

Related: Lifting stress, Aspect ratio, Rigging
Rigging

The slings, shackles, spreader beams, and related hardware that connect a crane hook to a panel's lifting inserts and distribute hoisting forces.

Related: Spreader beam, Center of gravity, Lifting insert
Spreader beam

A rigid lifting beam used between the crane hook and slings to keep sling legs near vertical and reduce horizontal compression in the panel during lifting.

Related: Rigging, Lifting stress, Center of gravity
Lifting stress

The internal force induced in a panel by hoisting loads, which is highest before the panel is fully vertical and must be checked against its concrete strength.

Related: Lifting insert, Strongback, Concrete strength at lift
Concrete strength at lift

The compressive strength a panel must reach before hoisting, verified by field-cured cylinders or maturity methods per the lifting design assumptions.

Related: Lifting stress, Curing, Cylinder break
Cylinder break

A compression test of a field-cured concrete specimen used to confirm the panel has achieved the strength assumed for lifting, stripping, or post-tensioning.

Related: Concrete strength at lift, Curing, Quality control
Curing

Maintaining adequate moisture and temperature in fresh concrete so it gains strength and durability; curing is especially important before early panel lifting.

Related: Concrete strength at lift, Curing compound, Cylinder break
Curing compound

A liquid applied to finished concrete that forms a membrane slowing moisture loss, used where wet curing or coverings are impractical on a casting bed.

Related: Curing, Bond breaker, Panel finish
Panel finish

The specified surface treatment of a panel face, such as broom, exposed aggregate, or smooth form finish, established by the casting surface and finishing methods.

Related: Bond breaker, Form release agent, Curing compound
Slab-on-grade

A concrete floor slab cast directly on prepared subgrade, which may also serve as the casting bed or support the panel forms and lifting equipment.

Related: Casting bed, Subgrade, Vapor barrier
Subgrade

The compacted soil beneath a slab or casting bed, prepared and graded to provide uniform support and prevent settlement or cracking of the concrete above.

Related: Slab-on-grade, Vapor barrier, Site preparation
Vapor barrier

An impermeable sheet placed beneath a slab to limit moisture migration from the ground into the concrete and finished floor assembly above.

Related: Subgrade, Slab-on-grade, Panel casting bed
Site preparation

The earthwork, grading, compaction, and access work done before construction so the casting area, crane paths, and foundations are stable and properly drained.

Related: Subgrade, Crane path, Panel layout plan
Crane path

The planned route and standing locations for the lifting crane, evaluated for bearing capacity, slope, overhead obstructions, and clearance to erected panels.

Related: Lift plan, Site preparation, Critical lift
Lift plan

A written document identifying the crane, rigging, load weights, radii, ground conditions, sequence, and responsibilities for a specific panel lifting operation.

Related: Critical lift, Job hazard analysis, Rigging
Critical lift

A lift that exceeds defined thresholds such as high load percentage, multiple cranes, or personnel under load, requiring a more detailed engineered lift plan and review.

Related: Lift plan, Job hazard analysis, Crane path
Job hazard analysis

A structured review of each task that identifies hazards, assesses risk, and documents controls and responsible persons before work begins on site.

Related: Lift plan, Exclusion zone, Critical lift
Exclusion zone

A marked area beneath and around a hoisted panel where unauthorized people are prohibited during lifting, erection, and bracing operations.

Related: Job hazard analysis, Panel erection, Lift plan
Panel erection

The sequence of tilting a panel from its casting bed to vertical, positioning it on its foundation, and securing temporary bracing and permanent connections.

Related: Temporary bracing, Exclusion zone, Tilt-up panel
Wind load

The force exerted by wind on an erected or temporarily braced panel, which governs bracing design and may require stopping work above defined speeds.

Related: Temporary bracing, Brace anchor, Panel erection
Shop drawing

A detailed fabrication and erection drawing prepared by the contractor showing panel dimensions, reinforcement, embeds, openings, and connection details for review.

Related: Embed, Panel layout plan, Quality control
Quality control

The planned inspections, tests, and documentation used to verify that materials, dimensions, and workmanship meet the project specifications and approved drawings.

Related: Shop drawing, Cylinder break, Tolerance
Tolerance

The permissible variation from a specified dimension or position, such as panel plumbness, joint width, or embed location, within which work is accepted.

Related: Quality control, Shop drawing, Panel geometry
Reinforcement

Steel bars, mesh, or fibers placed in a panel to resist tensile and shrinkage stresses, positioned per drawings with specified cover and lap lengths.

Related: Cover, Lap splice, Lifting stress
Cover

The concrete depth between the outer surface of embedded steel and the nearest exposed face, protecting reinforcement from corrosion and fire.

Related: Reinforcement, Embed, Quality control
Lap splice

The overlapping length of two reinforcing bars that transfers force between them through bond with the surrounding concrete.

Related: Reinforcement, Cover, Shop drawing
Joint

A planned separation between panels or within a slab that accommodates movement, defines panel boundaries, and often carries sealant or connection hardware.

Related: Rustication, Panel geometry, Connection hardware
Reveal

A shallow recessed detail formed in a panel face or edge, used for architectural shadow lines, jointing, or to receive sealant and flashing.

Related: Rustication, Edge form, Joint