Electrical Coordination and Code Compliance

AK General Contractor · Put your knowledge to work in context.

All case studies

Electrical Coordination and Code Compliance

A general contractor is building a 10,000 sq ft retail store. The electrical subcontractor has installed the main service panel (400A, 208Y/120V, 3-phase) and branch circuits. During a rough-in inspection, the electrical inspector notes that the panel is located in a storage room that is used for flammable liquids, and that the working space in front of the panel is only 24 inches deep. The inspector also finds that the panel's short-circuit current rating (SCCR) is 10kA, but the utility transformer available fault current is 22kA. The contractor must address these issues to pass inspection and ensure safety.

1. What code violations are present, and what are the potential consequences?

Read the worked answer

Violations per NEC: 1) Panel located in a storage room with flammable liquids: NEC 240.24 prohibits overcurrent devices in the vicinity of easily ignitable material. The panel must be relocated or the storage changed. 2) Working space depth: NEC 110.26 requires a minimum depth of 36 inches (for 208Y/120V, 3-phase, 400A, the depth is 36 inches per Table 110.26(A)(1)). Only 24 inches is insufficient. 3) SCCR: NEC 110.9 and 110.10 require equipment to have a short-circuit current rating not less than the available fault current. 10kA is less than 22kA, so the panel is inadequately rated. Consequences: unsafe conditions, potential fire or explosion, failed inspection, and liability. The contractor must correct these before energizing.

2. What corrective actions should the contractor take?

Read the worked answer
  1. Relocate the panel to a location not used for flammable storage, or create a dedicated electrical room with fire-rated separation. 2) Increase working space to at least 36 inches deep and 30 inches wide, with 6.5 ft headroom. 3) Replace the panel with one rated for at least 22kA SCCR, or install current-limiting fuses or a series-rated system if approved. 4) Coordinate with the electrical engineer and utility to confirm available fault current. 5) Submit revised drawings for approval. 6) Re-inspect. The contractor should also check other equipment for adequate SCCR.