AK General Contractor study materials
AK General Contractor study resources

AK General Contractor cheat sheet

AK General Contractor · Keep the key ideas within reach.

Quick reference

Business and Financial Management

  • Working capital = current assets − current liabilities; measures short-term ability to pay project costs.

  • Retainage receivable is an asset, not revenue; recognize it only when billed and collectible.

  • Straight-line depreciation = (cost − salvage value) ÷ useful life in years.

  • Break-even revenue = fixed overhead ÷ contribution margin ratio, where contribution margin ratio = (revenue − variable costs) ÷ revenue.

  • Over/under billing = earned revenue (costs incurred plus recognized profit) − billings to date; a positive value is underbilling.

  • Current ratio = current assets ÷ current liabilities; quick ratio excludes inventory and prepaid items.

  • Alaska has no state sales tax and no state personal income tax; do not add a state sales tax line to estimates.

  • Payroll burden percentage = (payroll taxes + insurance + benefits) ÷ base wages; apply to every labor hour in the bid.

  • Cash flow lag equals the gap between cash out for labor/materials and cash in from progress payments; fund it with working capital or a line of credit.

Quick reference

Contracting Law and Regulations

  • A written change order signed by the owner is required before performing work outside the contract scope; oral directives should be confirmed in writing.

  • Substantial completion starts warranty periods and often triggers release of retainage, subject to contract terms.

  • A lien claimant generally must record a lien within a statutory period after last furnishing labor or materials; the period is set by statute, not by the contract.

  • Pay-when-paid clauses shift timing risk to subcontractors; pay-if-paid clauses shift nonpayment risk and are treated differently by state law.

  • Alaska requires contractors to be licensed and to hold a residential contractors endorsement for residential work; an unlicensed contractor may be barred from collecting.

  • Alaska has a statutory contractor registration/licensing scheme and requires a surety bond as a condition of licensure; bond amounts vary by license category.

  • Notice of claim or notice of lien is typically a prerequisite to a lien; missing the notice can void the lien right.

  • Alaska's Little Miller Act governs bonds on state public works; the federal Miller Act governs federal projects, each with its own claim notice rules.

  • Differing site conditions clauses allow an equitable adjustment if conditions differ materially from those indicated in the contract documents.

Quick reference

Estimating and Bidding

  • Quantity takeoff: compute net quantities from dimensions, then add waste factors (commonly 5–10% for framing lumber, 3–5% for concrete).

  • Concrete volume = length × width × depth in consistent units; divide cubic feet by 27 for cubic yards.

  • Board feet = (thickness in inches × width in inches × length in feet) ÷ 12, per piece.

  • Masonry unit count = wall area ÷ (unit face area including mortar joint), then add breakage allowance.

  • Roof area = horizontal footprint area × roof slope factor; slope factor = square root of (rise² + run²) ÷ run.

  • Labor hours = quantity ÷ crew production rate; labor cost = hours × fully burdened hourly rate.

  • Bid price = direct costs + indirect costs + overhead + profit + contingency; express contingency as a percentage of direct cost.

  • Additive and deductive alternates are priced separately so the owner can select scope without re-bidding.

  • Unit price bids are used where quantities are uncertain; the unit price governs payment regardless of estimated quantity.

Quick reference

Project Management and Scheduling

  • Critical path is the longest duration path through the network; its total float is zero, so any delay there delays completion.

  • Total float = late start − early start (equivalently late finish − early finish); free float is float before affecting a successor.

  • Crashing shortens duration by adding resources to critical activities; fast-tracking overlaps activities that were sequential, increasing risk.

  • A Gantt chart shows time on the horizontal axis and activities as bars; a network diagram shows logical dependencies.

  • Percent complete by cost = cost incurred to date ÷ total estimated cost at completion.

  • Estimate at completion (EAC) = budget at completion ÷ cost performance index, using earned value data.

  • Schedule variance = earned value − planned value; negative SV indicates work behind schedule.

  • Submittals, shop drawings, and long-lead material procurement belong on the schedule as predecessor activities.

  • Look-ahead schedules cover the next 2–6 weeks and identify constraints to remove before work starts.

Quick reference

Site Work, Excavation, and Foundations

  • Cut and fill volumes are computed by the average end area method or by prismoidal formula; net balance means cut equals fill.

  • Soil swell increases hauled volume above in-place bank volume; shrinkage reduces compacted fill volume relative to bank volume.

  • Compaction is specified as a percentage of maximum dry density from a standard or modified Proctor test at a specified moisture content.

  • Trench excavation requires sloping, benching, or shoring; the required protective system depends on soil classification and depth.

  • Footing depth must reach below the frost line; in much of Alaska frost depth is deep enough that frost-protected shallow foundations or insulated footings are used.

  • Perched water tables and seasonally frozen ground can require dewatering and frost-susceptible soil replacement before footings.

  • Excavation spoil must be kept back from the trench edge to reduce surcharge loading on trench walls.

  • Permafrost disturbance can cause thaw settlement; construction methods must preserve the thermal regime where permafrost is present.

  • Benchmarks and site control must be established and protected before mass excavation begins.

Quick reference

Concrete, Masonry, and Metals

  • Concrete compressive strength is specified at 28 days; mix design targets that strength with a margin above the specified value.

  • Water-cement ratio controls strength and durability; lower w/c increases strength and reduces permeability.

  • Slump test measures workability; air content is measured to verify freeze-thaw durability, which matters in cold climates.

  • Formwork must be designed for lateral pressure of fresh concrete, which increases with placement rate and lower temperature.

  • Concrete must be protected from freezing until it reaches adequate strength; cold-weather practice requires heated enclosures or insulating blankets.

  • Masonry mortar joints are typically 3/8 inch; mortar type (M, S, N, O) governs compressive and bond strength.

  • Reinforcing steel must have specified cover over bars; cover depends on exposure condition and member type.

  • Structural steel connections are either bolted or welded; high-strength bolts are tensioned to a specified pretension.

  • Anchor bolts and embed plates must be set to template dimensions before concrete placement to avoid field correction.

Quick reference

Carpentry, Wood Framing, and Finish

  • Nominal lumber dimensions differ from actual: a 2x4 is 1-1/2 inches by 3-1/2 inches; a 2x10 is 1-1/2 inches by 9-1/4 inches.

  • Stud spacing is typically 16 or 24 inches on center; spacing and grade determine allowable span and load capacity.

  • Floor joist span is limited by species, grade, size, spacing, and deflection criteria (commonly L/360 for floors).

  • Headers over openings must be sized for the span and load; jack and king studs transfer load around openings.

  • Wall framing layout must align studs with sheathing edges and provide nailing for structural panels.

  • Wood must be protected from moisture; kiln-dried lumber shrinks after installation, so allowance for movement is required at joints.

  • Rough openings are framed larger than the finished unit to allow shimming and squaring during installation.

  • Subfloor panel thickness and edge support are set by span rating and joist spacing.

  • Finish carpentry tolerances are tighter than framing tolerances; verify wall plumb and square before trim installation.

Quick reference

Roofing, Thermal and Moisture Protection

  • Roof slope = rise ÷ run; a 4:12 slope rises 4 inches per 12 inches of horizontal run.

  • Slope factor for roof area = square root of (rise² + run²) ÷ run; use it to convert plan area to roof area.

  • Ice dam protection membrane is required at eaves in cold climates and must extend from the eave to a point inside the interior wall line.

  • A vapor retarder is placed on the warm side of insulation; in cold climates that is typically the interior side.

  • Ventilation must balance intake at the soffit and exhaust at or near the ridge; net free vent area is specified by code.

  • Roof underlayment requirements depend on slope; low-slope roofs require different membrane systems than steep-slope roofs.

  • Flashing is required at valleys, penetrations, walls, and roof-to-wall intersections to direct water out of the assembly.

  • Thermal bridging through framing reduces effective R-value; continuous exterior insulation reduces bridging.

  • Air leakage transports far more moisture than diffusion; air sealing precedes insulation in cold-climate assemblies.

Quick reference

Mechanical, Electrical, and Plumbing Systems

  • Ohm's law: voltage = current × resistance; power in watts = volts × amps for resistive loads.

  • Circuit ampacity must not be less than the load; overcurrent protection is sized to protect the conductor, not the appliance.

  • Conductor sizing accounts for voltage drop over long runs; larger wire reduces drop for a given load.

  • GFCI protection is required in bathrooms, kitchens, outdoors, and other wet or damp locations; AFCI protects against arc faults.

  • Plumbing drain lines rely on gravity slope, commonly 1/4 inch per foot for pipes 3 inches and smaller.

  • Vent piping admits air behind a trap to prevent siphonage; every trap must be vented.

  • Water supply pressure and pipe sizing must satisfy fixture flow demand at the farthest fixture.

  • Heating load is calculated from envelope heat loss plus infiltration and ventilation loads; equipment is sized to the calculated load, not by rule of thumb.

  • Duct leakage and insulation affect system efficiency; ducts in unconditioned space must be sealed and insulated.

Quick reference

Safety, Environmental, and Occupational Requirements

  • Fall protection is required when working at heights of 6 feet or more in construction, using guardrails, nets, or personal fall arrest.

  • Excavations 5 feet deep or more require a protective system unless the excavation is entirely in stable rock.

  • A competent person must inspect excavations daily and after rain or other events that could affect stability.

  • Scaffolds must be designed and loaded per the manufacturer and erected under the supervision of a qualified person; guardrails are required above 10 feet.

  • Hazard communication requires safety data sheets and labeling for chemicals on site.

  • Personal protective equipment is the last line of defense in the hierarchy of controls: elimination, substitution, engineering controls, administrative controls, then PPE.

  • Spill prevention and erosion control require silt fencing, containment, and proper disposal of wash water and fuels.

  • Asbestos and lead-containing materials require identification and regulated handling before demolition or renovation disturbs them.

  • Lockout/tagout procedures isolate hazardous energy before servicing or maintaining equipment.

Quick reference

Business and Financial Management

  • Working capital = current assets − current liabilities; measures short-term ability to pay project costs.

  • Retainage receivable is an asset, not revenue; recognize it only when billed and collectible.

  • Straight-line depreciation = (cost − salvage value) ÷ useful life in years.

  • Break-even revenue = fixed overhead ÷ contribution margin ratio, where contribution margin ratio = (revenue − variable costs) ÷ revenue.

  • Over/under billing = earned revenue (costs incurred plus recognized profit) − billings to date; a positive value is underbilling.

  • Current ratio = current assets ÷ current liabilities; quick ratio excludes inventory and prepaid items.

  • Alaska has no state sales tax and no state personal income tax; do not add a state sales tax line to estimates.

  • Payroll burden percentage = (payroll taxes + insurance + benefits) ÷ base wages; apply to every labor hour in the bid.

  • Cash flow lag equals the gap between cash out for labor/materials and cash in from progress payments; fund it with working capital or a line of credit.

Quick reference

Contracting Law and Regulations

  • A written change order signed by the owner is required before performing work outside the contract scope; oral directives should be confirmed in writing.

  • Substantial completion starts warranty periods and often triggers release of retainage, subject to contract terms.

  • A lien claimant generally must record a lien within a statutory period after last furnishing labor or materials; the period is set by statute, not by the contract.

  • Pay-when-paid clauses shift timing risk to subcontractors; pay-if-paid clauses shift nonpayment risk and are treated differently by state law.

  • Alaska requires contractors to be licensed and to hold a residential contractors endorsement for residential work; an unlicensed contractor may be barred from collecting.

  • Alaska has a statutory contractor registration/licensing scheme and requires a surety bond as a condition of licensure; bond amounts vary by license category.

  • Notice of claim or notice of lien is typically a prerequisite to a lien; missing the notice can void the lien right.

  • Alaska's Little Miller Act governs bonds on state public works; the federal Miller Act governs federal projects, each with its own claim notice rules.

  • Differing site conditions clauses allow an equitable adjustment if conditions differ materially from those indicated in the contract documents.

Quick reference

Estimating and Bidding

  • Quantity takeoff: compute net quantities from dimensions, then add waste factors (commonly 5–10% for framing lumber, 3–5% for concrete).

  • Concrete volume = length × width × depth in consistent units; divide cubic feet by 27 for cubic yards.

  • Board feet = (thickness in inches × width in inches × length in feet) ÷ 12, per piece.

  • Masonry unit count = wall area ÷ (unit face area including mortar joint), then add breakage allowance.

  • Roof area = horizontal footprint area × roof slope factor; slope factor = square root of (rise² + run²) ÷ run.

  • Labor hours = quantity ÷ crew production rate; labor cost = hours × fully burdened hourly rate.

  • Bid price = direct costs + indirect costs + overhead + profit + contingency; express contingency as a percentage of direct cost.

  • Additive and deductive alternates are priced separately so the owner can select scope without re-bidding.

  • Unit price bids are used where quantities are uncertain; the unit price governs payment regardless of estimated quantity.

Quick reference

Project Management and Scheduling

  • Critical path is the longest duration path through the network; its total float is zero, so any delay there delays completion.

  • Total float = late start − early start (equivalently late finish − early finish); free float is float before affecting a successor.

  • Crashing shortens duration by adding resources to critical activities; fast-tracking overlaps activities that were sequential, increasing risk.

  • A Gantt chart shows time on the horizontal axis and activities as bars; a network diagram shows logical dependencies.

  • Percent complete by cost = cost incurred to date ÷ total estimated cost at completion.

  • Estimate at completion (EAC) = budget at completion ÷ cost performance index, using earned value data.

  • Schedule variance = earned value − planned value; negative SV indicates work behind schedule.

  • Submittals, shop drawings, and long-lead material procurement belong on the schedule as predecessor activities.

  • Look-ahead schedules cover the next 2–6 weeks and identify constraints to remove before work starts.

Quick reference

Site Work, Excavation, and Foundations

  • Cut and fill volumes are computed by the average end area method or by prismoidal formula; net balance means cut equals fill.

  • Soil swell increases hauled volume above in-place bank volume; shrinkage reduces compacted fill volume relative to bank volume.

  • Compaction is specified as a percentage of maximum dry density from a standard or modified Proctor test at a specified moisture content.

  • Trench excavation requires sloping, benching, or shoring; the required protective system depends on soil classification and depth.

  • Footing depth must reach below the frost line; in much of Alaska frost depth is deep enough that frost-protected shallow foundations or insulated footings are used.

  • Perched water tables and seasonally frozen ground can require dewatering and frost-susceptible soil replacement before footings.

  • Excavation spoil must be kept back from the trench edge to reduce surcharge loading on trench walls.

  • Permafrost disturbance can cause thaw settlement; construction methods must preserve the thermal regime where permafrost is present.

  • Benchmarks and site control must be established and protected before mass excavation begins.

Quick reference

Concrete, Masonry, and Metals

  • Concrete compressive strength is specified at 28 days; mix design targets that strength with a margin above the specified value.

  • Water-cement ratio controls strength and durability; lower w/c increases strength and reduces permeability.

  • Slump test measures workability; air content is measured to verify freeze-thaw durability, which matters in cold climates.

  • Formwork must be designed for lateral pressure of fresh concrete, which increases with placement rate and lower temperature.

  • Concrete must be protected from freezing until it reaches adequate strength; cold-weather practice requires heated enclosures or insulating blankets.

  • Masonry mortar joints are typically 3/8 inch; mortar type (M, S, N, O) governs compressive and bond strength.

  • Reinforcing steel must have specified cover over bars; cover depends on exposure condition and member type.

  • Structural steel connections are either bolted or welded; high-strength bolts are tensioned to a specified pretension.

  • Anchor bolts and embed plates must be set to template dimensions before concrete placement to avoid field correction.

Quick reference

Carpentry, Wood Framing, and Finish

  • Nominal lumber dimensions differ from actual: a 2x4 is 1-1/2 inches by 3-1/2 inches; a 2x10 is 1-1/2 inches by 9-1/4 inches.

  • Stud spacing is typically 16 or 24 inches on center; spacing and grade determine allowable span and load capacity.

  • Floor joist span is limited by species, grade, size, spacing, and deflection criteria (commonly L/360 for floors).

  • Headers over openings must be sized for the span and load; jack and king studs transfer load around openings.

  • Wall framing layout must align studs with sheathing edges and provide nailing for structural panels.

  • Wood must be protected from moisture; kiln-dried lumber shrinks after installation, so allowance for movement is required at joints.

  • Rough openings are framed larger than the finished unit to allow shimming and squaring during installation.

  • Subfloor panel thickness and edge support are set by span rating and joist spacing.

  • Finish carpentry tolerances are tighter than framing tolerances; verify wall plumb and square before trim installation.

Quick reference

Roofing, Thermal and Moisture Protection

  • Roof slope = rise ÷ run; a 4:12 slope rises 4 inches per 12 inches of horizontal run.

  • Slope factor for roof area = square root of (rise² + run²) ÷ run; use it to convert plan area to roof area.

  • Ice dam protection membrane is required at eaves in cold climates and must extend from the eave to a point inside the interior wall line.

  • A vapor retarder is placed on the warm side of insulation; in cold climates that is typically the interior side.

  • Ventilation must balance intake at the soffit and exhaust at or near the ridge; net free vent area is specified by code.

  • Roof underlayment requirements depend on slope; low-slope roofs require different membrane systems than steep-slope roofs.

  • Flashing is required at valleys, penetrations, walls, and roof-to-wall intersections to direct water out of the assembly.

  • Thermal bridging through framing reduces effective R-value; continuous exterior insulation reduces bridging.

  • Air leakage transports far more moisture than diffusion; air sealing precedes insulation in cold-climate assemblies.

Quick reference

Mechanical, Electrical, and Plumbing Systems

  • Ohm's law: voltage = current × resistance; power in watts = volts × amps for resistive loads.

  • Circuit ampacity must not be less than the load; overcurrent protection is sized to protect the conductor, not the appliance.

  • Conductor sizing accounts for voltage drop over long runs; larger wire reduces drop for a given load.

  • GFCI protection is required in bathrooms, kitchens, outdoors, and other wet or damp locations; AFCI protects against arc faults.

  • Plumbing drain lines rely on gravity slope, commonly 1/4 inch per foot for pipes 3 inches and smaller.

  • Vent piping admits air behind a trap to prevent siphonage; every trap must be vented.

  • Water supply pressure and pipe sizing must satisfy fixture flow demand at the farthest fixture.

  • Heating load is calculated from envelope heat loss plus infiltration and ventilation loads; equipment is sized to the calculated load, not by rule of thumb.

  • Duct leakage and insulation affect system efficiency; ducts in unconditioned space must be sealed and insulated.

Quick reference

Safety, Environmental, and Occupational Requirements

  • Fall protection is required when working at heights of 6 feet or more in construction, using guardrails, nets, or personal fall arrest.

  • Excavations 5 feet deep or more require a protective system unless the excavation is entirely in stable rock.

  • A competent person must inspect excavations daily and after rain or other events that could affect stability.

  • Scaffolds must be designed and loaded per the manufacturer and erected under the supervision of a qualified person; guardrails are required above 10 feet.

  • Hazard communication requires safety data sheets and labeling for chemicals on site.

  • Personal protective equipment is the last line of defense in the hierarchy of controls: elimination, substitution, engineering controls, administrative controls, then PPE.

  • Spill prevention and erosion control require silt fencing, containment, and proper disposal of wash water and fuels.

  • Asbestos and lead-containing materials require identification and regulated handling before demolition or renovation disturbs them.

  • Lockout/tagout procedures isolate hazardous energy before servicing or maintaining equipment.

Quick reference

Business and Financial Management

  • Working capital = current assets − current liabilities; measures short-term ability to pay project costs.

  • Retainage receivable is an asset, not revenue; recognize it only when billed and collectible.

  • Straight-line depreciation = (cost − salvage value) ÷ useful life in years.

  • Break-even revenue = fixed overhead ÷ contribution margin ratio, where contribution margin ratio = (revenue − variable costs) ÷ revenue.

  • Over/under billing = earned revenue (costs incurred plus recognized profit) − billings to date; a positive value is underbilling.

  • Current ratio = current assets ÷ current liabilities; quick ratio excludes inventory and prepaid items.

  • Alaska has no state sales tax and no state personal income tax; do not add a state sales tax line to estimates.

  • Payroll burden percentage = (payroll taxes + insurance + benefits) ÷ base wages; apply to every labor hour in the bid.

  • Cash flow lag equals the gap between cash out for labor/materials and cash in from progress payments; fund it with working capital or a line of credit.

Quick reference

Contracting Law and Regulations

  • A written change order signed by the owner is required before performing work outside the contract scope; oral directives should be confirmed in writing.

  • Substantial completion starts warranty periods and often triggers release of retainage, subject to contract terms.

  • A lien claimant generally must record a lien within a statutory period after last furnishing labor or materials; the period is set by statute, not by the contract.

  • Pay-when-paid clauses shift timing risk to subcontractors; pay-if-paid clauses shift nonpayment risk and are treated differently by state law.

  • Alaska requires contractors to be licensed and to hold a residential contractors endorsement for residential work; an unlicensed contractor may be barred from collecting.

  • Alaska has a statutory contractor registration/licensing scheme and requires a surety bond as a condition of licensure; bond amounts vary by license category.

  • Notice of claim or notice of lien is typically a prerequisite to a lien; missing the notice can void the lien right.

  • Alaska's Little Miller Act governs bonds on state public works; the federal Miller Act governs federal projects, each with its own claim notice rules.

  • Differing site conditions clauses allow an equitable adjustment if conditions differ materially from those indicated in the contract documents.

Quick reference

Estimating and Bidding

  • Quantity takeoff: compute net quantities from dimensions, then add waste factors (commonly 5–10% for framing lumber, 3–5% for concrete).

  • Concrete volume = length × width × depth in consistent units; divide cubic feet by 27 for cubic yards.

  • Board feet = (thickness in inches × width in inches × length in feet) ÷ 12, per piece.

  • Masonry unit count = wall area ÷ (unit face area including mortar joint), then add breakage allowance.

  • Roof area = horizontal footprint area × roof slope factor; slope factor = square root of (rise² + run²) ÷ run.

  • Labor hours = quantity ÷ crew production rate; labor cost = hours × fully burdened hourly rate.

  • Bid price = direct costs + indirect costs + overhead + profit + contingency; express contingency as a percentage of direct cost.

  • Additive and deductive alternates are priced separately so the owner can select scope without re-bidding.

  • Unit price bids are used where quantities are uncertain; the unit price governs payment regardless of estimated quantity.

Quick reference

Project Management and Scheduling

  • Critical path is the longest duration path through the network; its total float is zero, so any delay there delays completion.

  • Total float = late start − early start (equivalently late finish − early finish); free float is float before affecting a successor.

  • Crashing shortens duration by adding resources to critical activities; fast-tracking overlaps activities that were sequential, increasing risk.

  • A Gantt chart shows time on the horizontal axis and activities as bars; a network diagram shows logical dependencies.

  • Percent complete by cost = cost incurred to date ÷ total estimated cost at completion.

  • Estimate at completion (EAC) = budget at completion ÷ cost performance index, using earned value data.

  • Schedule variance = earned value − planned value; negative SV indicates work behind schedule.

  • Submittals, shop drawings, and long-lead material procurement belong on the schedule as predecessor activities.

  • Look-ahead schedules cover the next 2–6 weeks and identify constraints to remove before work starts.

Quick reference

Site Work, Excavation, and Foundations

  • Cut and fill volumes are computed by the average end area method or by prismoidal formula; net balance means cut equals fill.

  • Soil swell increases hauled volume above in-place bank volume; shrinkage reduces compacted fill volume relative to bank volume.

  • Compaction is specified as a percentage of maximum dry density from a standard or modified Proctor test at a specified moisture content.

  • Trench excavation requires sloping, benching, or shoring; the required protective system depends on soil classification and depth.

  • Footing depth must reach below the frost line; in much of Alaska frost depth is deep enough that frost-protected shallow foundations or insulated footings are used.

  • Perched water tables and seasonally frozen ground can require dewatering and frost-susceptible soil replacement before footings.

  • Excavation spoil must be kept back from the trench edge to reduce surcharge loading on trench walls.

  • Permafrost disturbance can cause thaw settlement; construction methods must preserve the thermal regime where permafrost is present.

  • Benchmarks and site control must be established and protected before mass excavation begins.

Quick reference

Concrete, Masonry, and Metals

  • Concrete compressive strength is specified at 28 days; mix design targets that strength with a margin above the specified value.

  • Water-cement ratio controls strength and durability; lower w/c increases strength and reduces permeability.

  • Slump test measures workability; air content is measured to verify freeze-thaw durability, which matters in cold climates.

  • Formwork must be designed for lateral pressure of fresh concrete, which increases with placement rate and lower temperature.

  • Concrete must be protected from freezing until it reaches adequate strength; cold-weather practice requires heated enclosures or insulating blankets.

  • Masonry mortar joints are typically 3/8 inch; mortar type (M, S, N, O) governs compressive and bond strength.

  • Reinforcing steel must have specified cover over bars; cover depends on exposure condition and member type.

  • Structural steel connections are either bolted or welded; high-strength bolts are tensioned to a specified pretension.

  • Anchor bolts and embed plates must be set to template dimensions before concrete placement to avoid field correction.

Quick reference

Carpentry, Wood Framing, and Finish

  • Nominal lumber dimensions differ from actual: a 2x4 is 1-1/2 inches by 3-1/2 inches; a 2x10 is 1-1/2 inches by 9-1/4 inches.

  • Stud spacing is typically 16 or 24 inches on center; spacing and grade determine allowable span and load capacity.

  • Floor joist span is limited by species, grade, size, spacing, and deflection criteria (commonly L/360 for floors).

  • Headers over openings must be sized for the span and load; jack and king studs transfer load around openings.

  • Wall framing layout must align studs with sheathing edges and provide nailing for structural panels.

  • Wood must be protected from moisture; kiln-dried lumber shrinks after installation, so allowance for movement is required at joints.

  • Rough openings are framed larger than the finished unit to allow shimming and squaring during installation.

  • Subfloor panel thickness and edge support are set by span rating and joist spacing.

  • Finish carpentry tolerances are tighter than framing tolerances; verify wall plumb and square before trim installation.

Quick reference

Roofing, Thermal and Moisture Protection

  • Roof slope = rise ÷ run; a 4:12 slope rises 4 inches per 12 inches of horizontal run.

  • Slope factor for roof area = square root of (rise² + run²) ÷ run; use it to convert plan area to roof area.

  • Ice dam protection membrane is required at eaves in cold climates and must extend from the eave to a point inside the interior wall line.

  • A vapor retarder is placed on the warm side of insulation; in cold climates that is typically the interior side.

  • Ventilation must balance intake at the soffit and exhaust at or near the ridge; net free vent area is specified by code.

  • Roof underlayment requirements depend on slope; low-slope roofs require different membrane systems than steep-slope roofs.

  • Flashing is required at valleys, penetrations, walls, and roof-to-wall intersections to direct water out of the assembly.

  • Thermal bridging through framing reduces effective R-value; continuous exterior insulation reduces bridging.

  • Air leakage transports far more moisture than diffusion; air sealing precedes insulation in cold-climate assemblies.

Quick reference

Mechanical, Electrical, and Plumbing Systems

  • Ohm's law: voltage = current × resistance; power in watts = volts × amps for resistive loads.

  • Circuit ampacity must not be less than the load; overcurrent protection is sized to protect the conductor, not the appliance.

  • Conductor sizing accounts for voltage drop over long runs; larger wire reduces drop for a given load.

  • GFCI protection is required in bathrooms, kitchens, outdoors, and other wet or damp locations; AFCI protects against arc faults.

  • Plumbing drain lines rely on gravity slope, commonly 1/4 inch per foot for pipes 3 inches and smaller.

  • Vent piping admits air behind a trap to prevent siphonage; every trap must be vented.

  • Water supply pressure and pipe sizing must satisfy fixture flow demand at the farthest fixture.

  • Heating load is calculated from envelope heat loss plus infiltration and ventilation loads; equipment is sized to the calculated load, not by rule of thumb.

  • Duct leakage and insulation affect system efficiency; ducts in unconditioned space must be sealed and insulated.

Quick reference

Safety, Environmental, and Occupational Requirements

  • Fall protection is required when working at heights of 6 feet or more in construction, using guardrails, nets, or personal fall arrest.

  • Excavations 5 feet deep or more require a protective system unless the excavation is entirely in stable rock.

  • A competent person must inspect excavations daily and after rain or other events that could affect stability.

  • Scaffolds must be designed and loaded per the manufacturer and erected under the supervision of a qualified person; guardrails are required above 10 feet.

  • Hazard communication requires safety data sheets and labeling for chemicals on site.

  • Personal protective equipment is the last line of defense in the hierarchy of controls: elimination, substitution, engineering controls, administrative controls, then PPE.

  • Spill prevention and erosion control require silt fencing, containment, and proper disposal of wash water and fuels.

  • Asbestos and lead-containing materials require identification and regulated handling before demolition or renovation disturbs them.

  • Lockout/tagout procedures isolate hazardous energy before servicing or maintaining equipment.