API 653 flashcards
API 653 · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- API 653 scope pressure limit
- API 653 covers aboveground steel storage tanks built to API 650 or API 12C whose internal design pressure does not exceed 2.5 psig (17 kPa gauge).
- One-foot method formula
- Shell thickness t = 2.6D(H-1)G/(SE) in US customary units, where D is tank diameter in ft, H is design liquid height in ft, G is specific gravity, S allowable stress, E joint efficiency.
- Joint efficiency values
- For shell butt joints, E is 1.00 with full radiography, 0.85 with spot radiography, and 0.70 with no radiography; E appears directly in the shell thickness formula.
- Minimum shell plate thickness
- API 650 requires new shell plates to be at least 3/16 in. (5 mm) nominal thick, exclusive of corrosion allowance, regardless of the calculated design thickness.
- Emergency venting purpose
- Emergency vents, sized per API 2000, relieve pressure from fire exposure or abnormal vapor generation beyond normal vent capacity, protecting the shell-to-roof joint.
- Frangible roof design
- A roof-to-shell attachment intentionally weaker than the shell-to-bottom connection, so excessive internal pressure lifts the roof and vents the tank before the shell is damaged.
- Seismic design appendix
- API 650 Appendix E requires evaluation of impulsive and convective liquid motion, shell compressive stress, sloshing wave height, and anchorage against overturning for tanks in seismic areas.
- External inspection interval
- API 653 requires in-service external inspections by an authorized inspector at intervals not exceeding 5 years, or more often where corrosion rates or conditions warrant.
- Internal inspection interval
- Internal inspection intervals shall not exceed 20 years and shall not exceed one-half of the estimated remaining corrosion life of the shell or bottom.
- Corrosion rate calculation
- Corrosion rate equals thickness lost between two measurement dates divided by the elapsed time; remaining life equals current thickness minus minimum required thickness divided by that rate.
- Hydrostatic test hold
- A new or reconstructed tank is filled with water and held, typically 24 hours, before all welded joints are visually examined and shell settlement is measured.
- Tank bottom MFL scan
- Magnetic flux leakage scanning detects bottom plate thinning and pitting over large areas quickly; findings are then confirmed with ultrasonic thickness measurements at grid points.
- Fitness-for-service assessment
- Corrosion, cracks, or flaws found during inspection may be evaluated with API 579-1/ASME FFS-1 to decide whether the tank is fit for continued service.
- Inspector vision requirement
- Inspectors must have near vision corrected to Jaeger 1 at 12 in. and color vision sufficient to distinguish the colors used in the examination method.
- Repair definition
- Any work necessary to restore a tank, or part of a tank, to a condition suitable for continued service without changing the tank's structural configuration.
- Alteration definition
- Work that changes a tank's structural configuration or design, such as changing shell height, adding an opening larger than 12 in. nominal pipe size, or changing the foundation.
- Reconstruction definition
- Reassembly of a tank that has been dismantled and relocated; the tank must then satisfy applicable new-construction requirements, including testing and nameplate data.
- Insert plate requirements
- Shell insert plates shall be at least 12 in. (300 mm) wide, have rounded corners, and be at least as thick as the minimum thickness required at that location.
- Welding qualification requirement
- All repair, alteration, and reconstruction welding must use welding procedures and welders qualified under ASME Boiler and Pressure Vessel Code Section IX.
- Post-repair hydrostatic test
- Major repairs and alterations, such as shell plate replacement or new large openings, require hydrostatic testing; the authorized inspector may waive it for minor repairs where impractical.
- Tank entry oxygen range
- Before confined-space entry, oxygen must be tested and maintained between 19.5 and 23.5 percent by volume, with flammable vapor and toxic gas also within acceptable limits.
- Hot work gas limit
- Hot work on or in a tank requires a permit and a combustible gas reading below 10 percent of the lower explosive limit, with continuous monitoring while work proceeds.
- Static fill rate limit
- To control static ignition, initial filling is limited to about 3 ft/s (1 m/s) until the inlet is submerged, after which higher filling rates are permitted.
- Cathodic protection criterion
- Steel tank bottoms in soil are adequately protected when polarized to at least -0.85 V measured against a copper-copper sulfate reference electrode.
- Overfill protection standard
- API 2350 sets overfill prevention requirements including level alarms, independent high-high detection, and procedures to stop filling a tank before it overflows.
- Water bottoms control
- Water and sediment accumulating on the tank bottom promote pitting and underside corrosion; routine water draw-off and sludge removal reduce the corrosion rate.
- Out-of-service isolation
- Tanks removed from service must be cleaned, gas-freed, and positively isolated from all connected piping, typically with blinds or a double block and bleed arrangement.
- Return-to-service inspection
- Before an out-of-service tank returns to service, an authorized inspector evaluates its condition and specifies any required internal or external inspection and testing.
- Relocation treated as reconstruction
- A dismantled and re-erected tank is a reconstruction, so it must comply with new-construction requirements for foundation, shell roundness, welding, and hydrostatic testing.
- Nameplate after relocation
- The tank keeps its original nameplate; reconstruction and relocation data are recorded on a new or supplemental nameplate attached near the original.
- Record retention period
- Construction, inspection, repair, and alteration records must be maintained by the owner for the life of the tank and made available to the authorized inspector.
- Inspection record contents
- Records include thickness measurements with locations and dates, calculated corrosion rates and remaining life, examination and test reports, and nameplate data.