API 653 study materials
API 653 study resources

API 653 study plan

API 653 · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Tank Design and Construction

  • Calculate required shell-course thickness for a given tank diameter, height, and joint efficiency using the one-foot method, and state the conditions that require the variable-design-point method instead.

  • Differentiate the scope boundary between new-construction rules and in-service tank rules, listing at least five activities that belong to each.

  • Identify the material groupings and impact-testing criteria that determine whether a tank is susceptible to brittle fracture.

  • Sketch the shell-to-bottom, shell-to-shell, and shell-to-roof weld configurations and label the examination requirements that apply to each.

Your checkpoint

One-page formula sheet covering shell thickness, allowable stress, joint efficiency, and minimum thicknesses, plus 25 self-written calculation flashcards.

Week 2

Tank Design and Construction & Inspection, Examination, and Testing

  • Calculate minimum acceptable bottom-plate thickness and decide whether a bottom area may be repaired or must be replaced.

  • Compute maximum allowable fill height for an existing tank from a measured shell-thickness profile and joint efficiency.

  • Evaluate settlement, out-of-plumb, and out-of-round survey data against acceptance criteria and state the disposition for each.

  • Sequence a formal external inspection and list the items examined on shell, roof, foundation, appurtenances, and connected piping.

Your checkpoint

Completed maximum-allowable-fill-height worksheet for five hypothetical tanks with different measured thickness profiles and joint efficiencies.

Week 3

Inspection, Examination, and Testing

  • Compare visual, magnetic particle, liquid penetrant, ultrasonic, and radiographic examination by principle, detectable flaw type, and typical application on shell, bottom, and weld seams.

  • Explain vacuum box testing, when it is used instead of other methods on bottom seams, and how results are interpreted.

  • Describe hydrostatic testing preparation, hold requirements, and the corrective actions triggered by a leak or settlement during the test.

  • Construct an internal inspection plan for a tank due for service, specifying examination method, coverage, and locations for each region.

Your checkpoint

One-page NDT method selection matrix mapping flaw type and tank location to examination method and coverage.

Week 4

Inspection, Examination, and Testing & Repair, Alteration, and Reconstruction

  • Determine inspection intervals from measured corrosion rate, tank construction type, and service history.

  • Describe tank entry preparation: isolation, cleaning, gas-freeing, atmospheric testing, and permitting.

  • Distinguish repair from alteration from reconstruction using concrete field conditions, and state the approval and documentation path for each.

  • Rank candidate repairs by risk and identify which require engineering review before execution.

Your checkpoint

Timed 50-question mixed practice set across Domains 1-3 with a score of at least 75 percent, plus a written list of every missed topic.

Week 5

Repair, Alteration, and Reconstruction

  • Select between insert plate, lap patch, and full-course replacement for a shell defect, and state the thickness and dimensional rules that govern each option.

  • Describe weld procedure qualification and welder performance qualification requirements that apply to repair welding.

  • Explain hot-work authorization on an in-service tank, including cleaning, gas testing, and monitoring precautions.

  • Outline relocation and reconstruction requirements covering foundation preparation, re-rating, and post-move examination.

Your checkpoint

Written repair-versus-alteration decision tree with six worked field scenarios and the correct disposition for each.

Week 6

Operation, Maintenance, and Safety

  • Explain normal and emergency venting requirements and calculate whether a given vent capacity is adequate for fill, withdrawal, and fire exposure.

  • List operating practices for water draw-off, product withdrawal, and overfill prevention, and identify the failure mode each practice controls.

  • Apply brittle-fracture prevention limits during operation, including minimum fill temperature and impact-test status of the shell.

  • Outline safety controls for hot work, confined-space entry, and simultaneous operations on an in-service tank.

Your checkpoint

One-page operating and safety checklist covering venting, overfill, water draw-off, brittle fracture, and permit controls.

Week 7

Operation, Maintenance, and Safety & Decommissioning, Relocation, and Records

  • Sequence tank decommissioning and closure: product removal, cleaning, isolation, gas-freeing, and final documentation.

  • Identify the records that must be created, updated, or retained across a tank's life, and state the retention trigger for each.

  • Explain how an inspection history file is assembled, what belongs in it, and how it supports re-rating decisions.

  • Describe relocation requirements for inspection history, re-rating, and post-installation examination.

Your checkpoint

Sample tank record-file index with 20-plus record types, each annotated with its origin event and retention note.

Week 8

Decommissioning, Relocation, and Records & Tank Design and Construction & Inspection, Examination, and Testing & Repair, Alteration, and Reconstruction & Operation, Maintenance, and Safety

  • Audit a mock tank history file for completeness and flag every missing record against the index built in Week 7.

  • Re-drill the three weakest topics identified from prior practice scores until each is answered correctly on two consecutive attempts.

  • Complete two full-length timed practice exams under exam conditions.

  • Consolidate remaining knowledge gaps into a single prioritized one-page review list.

Your checkpoint

Final timed 100-question mock exam with a score of at least 80 percent, plus a one-page gap list with a remediation action for each item.

Milestones

Week 2: Can compute maximum allowable fill height for a tank with a measured thickness profile and state the governing allowable stress, without notes.

Week 4: Scores 75 percent or higher on the 50-question mixed set covering Domains 1-3, with no more than two misses in any single domain.

Week 6: Can explain vent sizing, brittle-fracture limits, and repair-versus-alteration classification aloud in under five minutes each, unaided.

Week 8: Scores 80 percent or higher on the timed 100-question mock exam, with at least 70 percent in every domain.