API SIRE · Keep the key ideas within reach.

Quick reference

Inspection Planning and Preparation

  • Hold point (H): production stops until the inspector performs the required surveillance and records acceptance; continuation or rework cannot proceed without that sign-off.

  • Witness point (W): the supplier must notify the inspector before the activity, but work proceeds if the inspector does not attend, and the non-attendance is recorded in the report.

  • Review point (R): records are examined after the activity is finished, so a review point never requires physical attendance at the workstation.

  • ITP content: process sequence, characteristic, specification clause, acceptance criterion, inspection method or NDE technique, frequency, and the H/W/R designation for each step.

  • Revision rule: purchase order revision, drawing revision, material specification, and process procedures must agree before inspection begins; any conflict is resolved in writing first.

  • Sampling: ANSI/ASQ Z1.4 sample size is set by lot size and inspection level, the acceptance number is set by the AQL, and tightened inspection applies after repeated lot rejections.

  • Instrument check: calibration label, certificate date, traceability to a national standard, and full-scale range - test pressure should fall between 1.5x and 4x gauge full scale.

  • Pre-inspection meeting inputs: approved ITP, qualified WPS/PQR with welder list, NDE procedures and personnel certifications, calibration list, sub-supplier approval status, and open NCRs.

Quick reference

Manufacturing Process Surveillance

  • A WPS is qualified by a PQR; welding outside the essential variable ranges covered by that PQR requires a new procedure qualification.

  • ASME Section IX welder performance qualification lapses after six months without use of the process; the employer must document continuity or re-qualify the welder.

  • The mill heat number must be transferred to each piece before cutting so chemistry, mechanical properties, and heat treatment condition remain traceable to the certificate.

  • MTR check points: heat number, grade, chemistry, tensile and yield strength, elongation, impact values where required, heat treatment condition, and specification revision.

  • Preheat and interpass temperature are measured with a calibrated contact thermometer or temperature-indicating crayon and recorded against the WPS minimum and maximum limits.

  • Radiography: density between 1.8 and 4.0 in the area of interest, required IQI wire visible, film and technique identified, and density measured with a calibrated densitometer.

  • Use-as-is disposition of a nonconformance requires design authority approval; rework and repair dispositions require re-inspection and re-test of the affected area.

  • Marking of pressure-containing surfaces uses low-stress rounded-nose stamps or vibro-etch; hard stamping is limited to locations the specification permits.

  • Furnace heat treatment surveillance: verify furnace survey certification, load thermocouple placement, soak temperature and time, and retain chart records linked to the heat number.

Quick reference

Testing, Examination, and Acceptance

  • API 598 hydrostatic shell test pressure is 1.5 times the 38 °C (100 °F) rating and seat test pressure is 1.1 times; shell test duration increases with valve nominal size.

  • Gauge rule: the test gauge must be calibrated with a full-scale range of at least 1.5 and no more than 4 times the intended test pressure, and it is identified on the test record.

  • Austenitic stainless steel test water has a controlled chloride content (commonly 30 ppm maximum) and is drained and dried immediately after the test.

  • Acceptance criteria come from the referencing code or specification; the NDE procedure defines only the technique, not what result is acceptable.

  • Positive material identification by XRF or optical emission verifies alloy identity on critical components; API 578 covers the PMI program, sampling, and records.

  • Pneumatic testing stores far more energy than hydrostatic testing, so it requires lower pressure ratios, remote gauges, barricades, and written approval before use.

  • Any repair affecting the pressure-containing boundary requires the pressure test to be repeated after repair, post-weld heat treatment, and NDE are complete.

  • Functional test: cycle the valve, verify torque or actuator stroke and closure, and confirm any double-block-and-bleed or fire-safe requirement stated on the purchase order.

Quick reference

Documentation, Reporting, and Quality Systems

  • Record chain: mill certificate to heat number to manufacturing, NDE, and test records to the finished item; a break anywhere in the chain is a reportable nonconformance.

  • Release requires every hold point signed, every NCR closed, and a Certificate of Conformance signed by an authorized representative identifying PO, specification, and quantity.

  • Document control: only current revisions at the point of use, obsolete documents removed or marked, and changes reviewed and approved before implementation.

  • API Q1 specifies quality management system requirements for organizations manufacturing equipment for the petroleum and natural gas industry and is applied with the API product specification.

  • Inspection report content: purchase order, item, serial and heat numbers, specification revision, date, activities witnessed, measured results, NCR references, and inspector signature.

  • Corrective action requires root cause analysis, containment of affected product, implementation of the change, and verification that the problem does not recur.

  • Records retention periods are defined by contract and the quality manual; API Q1 requires documented retention times and continued legibility and retrievability.

  • Out-of-calibration instruments trigger an impact assessment on all product measured since the last valid calibration, with results documented in the quality record.