- Hold point (H)
- A step in the inspection and test plan where work must stop; production cannot continue until the inspector completes the required surveillance and records acceptance.
- Witness point (W)
- A notification point where the supplier must inform the inspector before the activity, but the work may proceed without the inspector's physical presence if they do not attend.
- Review point (R)
- A documentation-only point where records are examined after the activity is complete; no physical surveillance attendance is needed and results are verified from the records.
- Inspection and test plan
- A document listing process steps, characteristics inspected, acceptance criteria, inspection methods, and hold, witness, or review designations for each manufacturing step.
- Pre-inspection meeting purpose
- Confirm scope, applicable specifications and revisions, ITP points, sub-supplier approvals, calibration status, personnel qualifications, and open nonconformances before production starts.
- AQL sampling plan basis
- Lot size and inspection level from ANSI/ASQ Z1.4 set the sample size; the acceptance number comes from the AQL, and tightened or reduced plans follow switching rules.
- Calibration check at source
- Confirm each measuring and test instrument has a current calibration label and a certificate traceable to a national standard, and that its range covers the characteristic measured.
- Document revision check
- Before inspection, the purchase order, drawing, specification, and procedure revisions must agree; conflicting revisions are resolved in writing before any product is accepted.
- WPS and PQR relationship
- A welding procedure specification is qualified by a procedure qualification record produced from a test coupon; the PQR supports the ranges of variables that the WPS may use.
- Welder qualification continuity
- Under ASME Section IX, a welder's qualification lapses if the process is not used for six months; the employer must keep continuity records or re-qualify the welder.
- Heat number traceability
- The mill heat number is transferred to each cut piece before cutting so that chemistry and mechanical properties stay linked to the finished component.
- Material test report check
- Verify that heat number, chemical composition, tensile properties, heat treatment condition, and specification grade on the MTR match the drawing and purchase order requirements.
- Preheat and interpass control
- Measure preheat and interpass temperature with a calibrated contact thermometer or temperature-indicating crayon before and during welding, and record values against WPS limits.
- Radiograph density requirement
- ASME Section V requires film density between 1.8 and 4.0 in the area of interest, measured with a densitometer, with IQI sensitivity demonstrated on each film.
- Nonconformance report disposition
- An NCR documents the deviation; disposition options are rework, repair, use-as-is, or reject, and use-as-is requires approval by the design authority rather than the supplier.
- Low-stress stamping
- Marking pressure-containing parts with shallow rounded-nose stamps or vibro-etch avoids notch-like stress raisers; hard stamping is limited to areas the specification permits.
- Hydrostatic shell test pressure
- API 598 sets shell test pressure at 1.5 times the valve pressure rating at 38 °C (100 °F), with no visible leakage permitted at any body joint or connection.
- Seat leakage test pressure
- API 598 seat tests use 1.1 times the pressure rating at 38 °C, with allowable leakage limits set by valve type and size rather than zero leakage for every design.
- Pressure gauge range rule
- ASME code requires the test gauge to be calibrated and its full-scale range to be at least 1.5 and no more than 4 times the intended test pressure.
- Chloride limit for test water
- Water used for hydrotesting austenitic stainless steel must have controlled chloride content, commonly 30 ppm maximum, and be drained and dried after the test.
- Positive material identification
- PMI by X-ray fluorescence or optical emission verifies alloy chemistry on critical components; API 578 governs the program, the sampling, and acceptance of results.
- Pneumatic test hazard
- Pneumatic testing stores far more energy than hydrostatic testing, so the code requires lower pressure ratios, remote gauges, barricades, and written approval before use.
- Re-test after repair
- Any repair or rework affecting the pressure-containing boundary requires the affected test to be repeated after repair, heat treatment, and NDE are complete.
- Acceptance criteria source
- Acceptance criteria come from the referencing code or specification, not from the NDE procedure; the procedure defines the technique and the code defines what is acceptable.
- Certificate of conformity
- A signed statement that the product meets purchase order and specification requirements, issued only after all hold points, tests, and nonconformances are closed.
- Record retention requirement
- API Q1 requires documented retention times for quality records; contracts often specify five years, and records must remain legible and retrievable for that period.
- Document control basics
- Only current revisions may be available at the point of use; obsolete documents are removed or marked, and changes are reviewed and approved before release.
- Corrective action requirement
- A corrective action addresses root cause rather than only the symptom; it includes containment, cause analysis, implementation, and verification that the problem does not recur.
- Traceability record linkage
- Heat numbers, serial numbers, and test report numbers must link the mill certificate, manufacturing records, and the finished item so any component can be traced back.
- Inspector stop-work authority
- The inspector may halt work when a documented nonconformance or specification violation is found; release then requires objective evidence of correction and acceptance.
- API Q1 scope
- API Q1 specifies quality management system requirements for organizations manufacturing equipment for the petroleum and natural gas industry and is used with API product specifications.
- Inspection report content
- A source inspection report identifies purchase order, item and serial or heat numbers, specification revision, date, activities witnessed, results, nonconformances, and the inspector's signature.