Pay Application 7: Stored Steel, Wrong Retainage, Short Waiver

ARE 5.0: CE · Put your knowledge to work in context.

All case studies

Pay Application 7: Stored Steel, Wrong Retainage, Short Waiver

The contractor submits Pay Application 7 for $1,240,000 on a $9.8M office building. It includes $310,000 for structural steel that has been fabricated and is stored in the fabricator's yard 90 miles away; the schedule of values carries that line at 100% complete, although no steel is on site. Retainage is computed at 5% of the total, but the contract requires 10% until the project is 50% complete; the schedule of values shows 44% complete. The steel subcontractor's signed waiver of lien is for $290,000, not $310,000. The owner's lender requires a site visit before funding, and your last visit was nine days ago. The contractor is pressing hard because its fabricator will stop shipments without payment.

1. What amount do you certify, and how do you show the math?

Read the worked answer

Certify conservatively and show the arithmetic so the contractor can see the basis rather than argue about the total.

Step 1 - strip the stored steel. The schedule of values says 100%, but nothing is in place. Value in place: $1,240,000 − $310,000 = $930,000.

Step 2 - apply the right retainage. At 44% completion the contract requires 10%, not 5%. $930,000 × 0.90 = $837,000.

Step 3 - stored materials are a separate decision. If you later approve them (see next task), the certified amount becomes $1,240,000 × 0.90 = $1,116,000 - but only once the conditions are satisfied and documented.

Certify $837,000 now. The gap between that and the request is not a rejection of the contractor's work; it is the contract's retainage rule plus an unapproved stored-materials item. Write the certificate that way: line-item adjustments with reasons, so the contractor's remedy is to cure the documentation rather than to dispute the total. The pressure from the fabricator is a cash-flow problem, not an entitlement - say so plainly and offer to expedite review of the stored-materials package.

2. What must be in place before you approve payment for offsite stored steel?

Read the worked answer

Offsite payment transfers the owner's money to material the owner cannot see. Require, at minimum:

  • Identification to the project - material marked, tagged, or segregated as destined for this job.
  • Bill of sale or invoice transferring title, and confirmation the fabricator holds the material free of other encumbrances.
  • Insurance covering the material in the owner's name, at the storage location, for fire and theft, with a certificate naming the owner.
  • Right of entry and inspection - owner or architect may inspect the yard on notice.
  • Storage agreement confirming the material will be held for this project and not shipped elsewhere.
  • Physical verification. The lender requires a site visit and your last one was nine days ago. Send someone to the yard to confirm the steel exists, is identified, and matches the count. A photograph and a signed inventory beat a certificate every time.

Until those exist, offsite material is an unfunded advance. The architect's certification is not a warranty of title, and the owner should not pay for steel it cannot find.

3. The steel sub's waiver is for $290,000 against a $310,000 request. What is the correct response?

Read the worked answer

The waiver must match the payment, dollar for dollar. A $290,000 waiver against a $310,000 request leaves $20,000 of the owner's exposure unprotected by any release.

  • Require a corrected conditional waiver and release for the full amount being paid, conditioned on actual receipt of funds - not a waiver signed at the time of application that purports to release before payment clears.
  • If a corrected waiver cannot be produced before funding, reduce the certified amount for that scope by the $20,000 difference. Do not 'average it out' or approve and chase paper later.
  • Check the sub-tier. If the $20,000 relates to a lower-tier supplier, the prime contractor's own waiver does not necessarily cover it; ask for the lower-tier conditional waiver as well.

Separately, confirm the discrepancy is not a sign the steel scope has changed without a change order - a $20,000 mismatch is also how unauthorized substitutions enter the record. Note the resolution in the payment log so the file shows what was withheld and why, and so the withheld amount is released automatically once the corrected waiver arrives rather than becoming a negotiation.