ARE 5.0: CE key terms
ARE 5.0: CE · Get comfortable with the vocabulary.
- Bid Package
- Related: Pre-Bid Conference, Addendum
The complete set of drawings, specifications, and bidding documents issued to contractors so each can prepare a comparable price. A well-organized package ensures every bidder prices the same scope of work.
- Pre-Bid Conference
- Related: Bid Package, Addendum
A meeting held before bids are due where the owner and architect explain the project and answer contractors' questions. The discussion is usually documented in an addendum so all bidders receive the same information.
- Addendum
- Related: Bid Package, Pre-Bid Conference
A written modification to the bidding documents issued before the bid deadline. It may clarify, correct, or change the drawings or specifications, and bidders must acknowledge it in their proposal.
- Bid Bond
- Related: Performance Bond, Prequalification
A surety's guarantee that a bidder will honor its proposal and sign the contract if selected. If the bidder walks away, the owner may claim the bond, usually a percentage of the bid amount.
- Performance Bond
- Related: Payment Bond, Bid Bond
A surety's promise to pay for completion of the work if the contractor defaults. It protects the owner up to the bond amount, typically the full contract sum.
- Payment Bond
- Related: Lien Waiver, Performance Bond
A surety's promise to pay subcontractors, suppliers, and laborers if the contractor fails to pay them. It protects the owner from mechanic's liens filed against the property.
- Prequalification
- Related: Bid Bond, Bid Package
A process in which the owner screens contractors for experience, financial capacity, and past performance before allowing them to bid, reducing the risk of awarding work to an unqualified firm.
- Alternates
- Related: Bid Package, Allowance
Defined optional changes to the base bid, such as adding or deleting a scope item, priced separately by bidders. The owner then selects the combination that best fits the budget.
- Allowance
- Related: Alternates, Change Order
A stated amount in the contract for work that cannot be fully defined at bid time. The contractor prices it later, and the contract sum is adjusted to reflect the actual cost.
- Value Engineering
- Related: Change Order, Constructability Review
A structured review that looks for lower-cost ways to achieve the same function and performance. Suggestions are adopted through the proper approval process, not by unilateral contractor action.
- Constructability Review
- Related: Value Engineering, Bid Package
An early review of drawings and specifications by people who build, looking for details that are hard to construct, unclear, or likely to cause conflicts, so problems are resolved before bidding.
- Guaranteed Maximum Price
- Related: Allowance, Change Order
A contract ceiling the contractor promises not to exceed, with savings above it typically shared with or returned to the owner. Costs above the cap are generally the contractor's risk.
- Liquidated Damages
- Related: Substantial Completion, Change Order
A pre-agreed amount the contractor pays the owner for each day of late completion, intended to approximate the owner's actual losses rather than to punish the contractor.
- Site Observation
- Related: Field Report, Nonconforming Work
The architect's periodic visits to the site to check that the work generally conforms to the contract documents. It is not continuous supervision and does not guarantee the contractor's work.
- Field Report
- Related: Site Observation, Nonconforming Work
A written record of each site visit describing progress, weather, workforce, tests, and any observed deviations. It becomes part of the project file and supports later decisions.
- Mock-Up
- Related: Site Observation, Submittal
A full-size sample of a construction assembly or finish built on site for review and approval before the work proceeds, establishing the standard that the rest of that work must match.
- Special Inspector
- Related: Site Observation, Field Report
An inspector hired by the owner, often for structural, welding, or fireproofing work, who performs tests and observations outside the architect's normal scope and reports results in writing.
- Nonconforming Work
- Related: Punch List, Site Observation
Work that does not meet the contract documents. The architect documents it, the contractor must correct it, and the owner is not obligated to accept it or pay for it.
- Beneficial Occupancy
- Related: Substantial Completion, Punch List
The owner's use of a completed portion of the project before substantial completion. It may shift certain responsibilities, such as utilities and insurance, from the contractor to the owner.
- Submittal
- Related: Shop Drawing, Request for Information
Information the contractor sends to the architect for review, such as shop drawings, product data, and samples, showing how the contractor intends to meet the design requirements.
- Shop Drawing
- Related: Submittal, Request for Information
A detail drawing prepared by a contractor, fabricator, or supplier showing how a component will actually be made and installed, used for coordination and for the architect's review.
- Substitution Request
- Related: Submittal, Addendum
A contractor's formal proposal to use a product or method different from what the specifications name, which the architect evaluates for equivalence and either approves or rejects.
- Request for Information
- Related: Architect's Supplemental Instruction, Change Order
A written request asking the architect to clarify or interpret the contract documents. Responses are logged and may lead to a change order or supplemental instruction if cost or time is affected.
- Architect's Supplemental Instruction
- Related: Request for Information, Change Order
A written instruction from the architect that clarifies or interprets the contract documents. It does not change the contract sum or contract time unless a change order later does so.
- Change Order
- Related: Construction Change Directive, Architect's Supplemental Instruction
A written, signed agreement among owner, contractor, and architect that modifies the contract sum, the contract time, or the scope of the work.
- Construction Change Directive
- Related: Change Order, Request for Information
A written instruction from the owner, prepared by the architect, ordering a change before the parties agree on price and time. Costs are documented later and formalized in a change order.
- Application for Payment
- Related: Schedule of Values, Retainage
The contractor's periodic request for money, supported by a schedule of values, showing work completed and materials stored, subject to architect certification and owner approval.
- Schedule of Values
- Related: Application for Payment, Change Order
An itemized breakdown of the contract sum allocating value to each portion of the work. It supports progress payments and shows how much each phase is worth.
- Retainage
- Related: Application for Payment, Substantial Completion
A percentage held back from each payment until the work is substantially or finally complete, giving the owner leverage to ensure remaining items are finished. It is often reduced at substantial completion.
- Lien Waiver
- Related: Payment Bond, Final Payment
A document in which a contractor or subcontractor gives up the right to file a mechanic's lien for a stated amount, usually exchanged for a payment and conditioned on funds clearing.
- Substantial Completion
- Related: Punch List, Beneficial Occupancy
The stage when the work, or a designated portion, is sufficiently complete for its intended use so the owner can occupy it. It starts warranty periods and shifts certain risks to the owner.
- Punch List
- Related: Substantial Completion, Final Inspection
A list of incomplete or defective items identified near the end of construction, which the contractor agrees to finish or correct before final completion and final payment.
- Record Drawings
- Related: Operation and Maintenance Manuals, Final Payment
Drawings the contractor marks up to show actual installed conditions, including changes, concealed work, and field adjustments, then delivers to the owner at closeout.
- Operation and Maintenance Manuals
- Related: Record Drawings, Commissioning
Written materials from the contractor describing how to operate, clean, and maintain the installed systems and equipment, along with parts lists and warranties, delivered to the owner at closeout.
- Warranty
- Related: Substantial Completion, Operation and Maintenance Manuals
The contractor's or manufacturer's written promise to repair or replace defects in materials or workmanship for a stated period after substantial completion, excluding damage from misuse or normal wear.
- Final Payment
- Related: Lien Waiver, Final Inspection
The last payment to the contractor after all closeout requirements are met, including final inspection, lien waivers, and consent of surety, releasing the remaining retainage.
- Post-Occupancy Evaluation
- Related: Substantial Completion, Commissioning
A structured review, conducted after the building has been in use for a while, of how well it serves occupants and the owner, feeding lessons into future projects and correction decisions.
- Commissioning
- Related: Operation and Maintenance Manuals, Post-Occupancy Evaluation
A systematic process of verifying that building systems and assemblies perform as designed and as the owner needs, documented in reports and carried through to operator training at handover.
- Final Inspection
- Related: Punch List, Final Payment
The architect's last review of the site, made with the contractor and often the owner, to confirm the punch list is complete and the work is ready for final payment.