Preconstruction Activities

  • Bid security: a bid bond is typically 5–10% of the bid amount; performance and payment bonds are each 100% of the contract sum.

  • Addenda are issued only before the bid deadline, become part of the contract documents, and must be acknowledged on the bid form; failure to acknowledge can make a bid nonresponsive.

  • Delivery methods: design-bid-build (sealed low bid), design-build (single entity holds design and construction risk), CM at risk (holds trade contracts, often a GMP), CM agency (advisor with no construction risk).

  • Total float = late start − early start = late finish − early finish; activities with zero total float lie on the critical path.

  • GMP contracts: the contractor's compensation cannot exceed the stated maximum; savings below the GMP are returned or shared per the agreement, and overruns are the contractor's risk absent owner-directed changes.

  • Value engineering savings are shared per the contract clause (commonly 50/50); owner-directed scope reductions are handled as a change order, not VE.

  • Prequalification screens bidders on financial capacity, bonding capacity, safety record (EMR), and comparable project experience before the bid list is issued.

  • Builder's risk insurance covers damage to the work in place during construction and is commonly purchased by the owner under AIA A101.

  • The owner may reject any or all bids and waive informalities; bid opening ends the bidding phase, and late bids are returned unopened.

Quick reference

Construction Observation

  • The architect visits the site at intervals appropriate to the stage of the work to observe general conformance; visits are not continuous and do not guarantee the contractor's work.

  • Construction means, methods, techniques, sequences, and procedures are solely the contractor's responsibility; the architect does not supervise or control them.

  • Observation reports are dated, factual, and distributed to owner and contractor; they record conditions and do not direct changes to cost or time.

  • Known nonconforming work must be reported in writing promptly; allowing nonconforming work to proceed without notice can waive the right to require correction.

  • Differing site conditions: the contractor stops affected work and notifies the architect, who evaluates; the contractor may be entitled to an equitable adjustment in cost and time.

  • Site safety, OSHA compliance, and protection of persons and property belong to the contractor; the architect has no authority over safety programs.

  • Shop drawing review confirms conformance with the design concept only; the review stamp does not relieve the contractor of responsibility for quantities, dimensions, and field conditions.

  • Testing of questionable work may be ordered by the architect; the owner pays if the work proves acceptable and the contractor pays if it does not.

  • Mock-ups and samples are approved before the related work proceeds, and the approved mock-up sets the standard for workmanship and appearance.

Quick reference

Administrative Procedures & Protocols

  • RFIs must be answered in writing; the response is incorporated into the contract documents but changes cost or time only through a change order.

  • A change order is signed by owner, architect, and contractor and states the change in contract sum and/or contract time.

  • A construction change directive is signed only by owner and architect; the contractor must proceed and pricing is negotiated or determined later.

  • An architect's supplemental instruction conveys a minor interpretation that does not change contract sum or time and requires no contractor signature.

  • The architect must certify a complete application for payment within 7 days of receipt or return it with written reasons within that same period (AIA A201).

  • Retainage is commonly 5–10% of each progress payment; a portion is released at substantial completion and the balance at final completion.

  • Lien waivers are conditional (effective only when payment is received) or unconditional (effective on signing), and progress or final in scope.

  • Time extensions are granted only for excusable, non-contractor-caused delays; contractor-caused delay generally carries no extension unless the owner waives liquidated damages.

  • The contractor maintains red-lined record documents reflecting actual installed conditions; the architect may examine them at any time.

Quick reference

Project Closeout & Evaluation

  • Substantial completion is the stage at which the work is sufficiently complete for the owner's intended use; the architect's certificate starts warranty periods and releases part of retainage.

  • Final completion requires completion of all punch list items, final inspection, the final payment application, final lien waivers, and consent of surety.

  • Closeout submittals include record (as-built) documents, O&M manuals, warranties, attic stock, spare parts, keys, and evidence of final cleaning.

  • A certificate of occupancy is issued by the authority having jurisdiction confirming code compliance and legal use; a temporary CO may carry conditions and an expiration date.

  • Consent of surety to final payment confirms the surety's bonded obligations are satisfied and is typically a prerequisite to releasing final retainage.

  • The warranty period is commonly one year from substantial completion; the architect determines whether a reported defect is covered or is normal wear or owner misuse.

  • A post-occupancy evaluation is typically performed roughly 6–12 months after occupancy using occupant surveys, performance data, and maintenance records.

  • The final certificate for payment (AIA G704) is issued after final inspection and certifies that the work is complete in accordance with the contract documents.

Quick reference

Preconstruction Activities

  • Bid security: a bid bond is typically 5–10% of the bid amount; performance and payment bonds are each 100% of the contract sum.

  • Addenda are issued only before the bid deadline, become part of the contract documents, and must be acknowledged on the bid form; failure to acknowledge can make a bid nonresponsive.

  • Delivery methods: design-bid-build (sealed low bid), design-build (single entity holds design and construction risk), CM at risk (holds trade contracts, often a GMP), CM agency (advisor with no construction risk).

  • Total float = late start − early start = late finish − early finish; activities with zero total float lie on the critical path.

  • GMP contracts: the contractor's compensation cannot exceed the stated maximum; savings below the GMP are returned or shared per the agreement, and overruns are the contractor's risk absent owner-directed changes.

  • Value engineering savings are shared per the contract clause (commonly 50/50); owner-directed scope reductions are handled as a change order, not VE.

  • Prequalification screens bidders on financial capacity, bonding capacity, safety record (EMR), and comparable project experience before the bid list is issued.

  • Builder's risk insurance covers damage to the work in place during construction and is commonly purchased by the owner under AIA A101.

  • The owner may reject any or all bids and waive informalities; bid opening ends the bidding phase, and late bids are returned unopened.

Quick reference

Construction Observation

  • The architect visits the site at intervals appropriate to the stage of the work to observe general conformance; visits are not continuous and do not guarantee the contractor's work.

  • Construction means, methods, techniques, sequences, and procedures are solely the contractor's responsibility; the architect does not supervise or control them.

  • Observation reports are dated, factual, and distributed to owner and contractor; they record conditions and do not direct changes to cost or time.

  • Known nonconforming work must be reported in writing promptly; allowing nonconforming work to proceed without notice can waive the right to require correction.

  • Differing site conditions: the contractor stops affected work and notifies the architect, who evaluates; the contractor may be entitled to an equitable adjustment in cost and time.

  • Site safety, OSHA compliance, and protection of persons and property belong to the contractor; the architect has no authority over safety programs.

  • Shop drawing review confirms conformance with the design concept only; the review stamp does not relieve the contractor of responsibility for quantities, dimensions, and field conditions.

  • Testing of questionable work may be ordered by the architect; the owner pays if the work proves acceptable and the contractor pays if it does not.

  • Mock-ups and samples are approved before the related work proceeds, and the approved mock-up sets the standard for workmanship and appearance.

Quick reference

Administrative Procedures & Protocols

  • RFIs must be answered in writing; the response is incorporated into the contract documents but changes cost or time only through a change order.

  • A change order is signed by owner, architect, and contractor and states the change in contract sum and/or contract time.

  • A construction change directive is signed only by owner and architect; the contractor must proceed and pricing is negotiated or determined later.

  • An architect's supplemental instruction conveys a minor interpretation that does not change contract sum or time and requires no contractor signature.

  • The architect must certify a complete application for payment within 7 days of receipt or return it with written reasons within that same period (AIA A201).

  • Retainage is commonly 5–10% of each progress payment; a portion is released at substantial completion and the balance at final completion.

  • Lien waivers are conditional (effective only when payment is received) or unconditional (effective on signing), and progress or final in scope.

  • Time extensions are granted only for excusable, non-contractor-caused delays; contractor-caused delay generally carries no extension unless the owner waives liquidated damages.

  • The contractor maintains red-lined record documents reflecting actual installed conditions; the architect may examine them at any time.

Quick reference

Project Closeout & Evaluation

  • Substantial completion is the stage at which the work is sufficiently complete for the owner's intended use; the architect's certificate starts warranty periods and releases part of retainage.

  • Final completion requires completion of all punch list items, final inspection, the final payment application, final lien waivers, and consent of surety.

  • Closeout submittals include record (as-built) documents, O&M manuals, warranties, attic stock, spare parts, keys, and evidence of final cleaning.

  • A certificate of occupancy is issued by the authority having jurisdiction confirming code compliance and legal use; a temporary CO may carry conditions and an expiration date.

  • Consent of surety to final payment confirms the surety's bonded obligations are satisfied and is typically a prerequisite to releasing final retainage.

  • The warranty period is commonly one year from substantial completion; the architect determines whether a reported defect is covered or is normal wear or owner misuse.

  • A post-occupancy evaluation is typically performed roughly 6–12 months after occupancy using occupant surveys, performance data, and maintenance records.

  • The final certificate for payment (AIA G704) is issued after final inspection and certifies that the work is complete in accordance with the contract documents.

Quick reference

Preconstruction Activities

  • Bid security: a bid bond is typically 5–10% of the bid amount; performance and payment bonds are each 100% of the contract sum.

  • Addenda are issued only before the bid deadline, become part of the contract documents, and must be acknowledged on the bid form; failure to acknowledge can make a bid nonresponsive.

  • Delivery methods: design-bid-build (sealed low bid), design-build (single entity holds design and construction risk), CM at risk (holds trade contracts, often a GMP), CM agency (advisor with no construction risk).

  • Total float = late start − early start = late finish − early finish; activities with zero total float lie on the critical path.

  • GMP contracts: the contractor's compensation cannot exceed the stated maximum; savings below the GMP are returned or shared per the agreement, and overruns are the contractor's risk absent owner-directed changes.

  • Value engineering savings are shared per the contract clause (commonly 50/50); owner-directed scope reductions are handled as a change order, not VE.

  • Prequalification screens bidders on financial capacity, bonding capacity, safety record (EMR), and comparable project experience before the bid list is issued.

  • Builder's risk insurance covers damage to the work in place during construction and is commonly purchased by the owner under AIA A101.

  • The owner may reject any or all bids and waive informalities; bid opening ends the bidding phase, and late bids are returned unopened.

Quick reference

Construction Observation

  • The architect visits the site at intervals appropriate to the stage of the work to observe general conformance; visits are not continuous and do not guarantee the contractor's work.

  • Construction means, methods, techniques, sequences, and procedures are solely the contractor's responsibility; the architect does not supervise or control them.

  • Observation reports are dated, factual, and distributed to owner and contractor; they record conditions and do not direct changes to cost or time.

  • Known nonconforming work must be reported in writing promptly; allowing nonconforming work to proceed without notice can waive the right to require correction.

  • Differing site conditions: the contractor stops affected work and notifies the architect, who evaluates; the contractor may be entitled to an equitable adjustment in cost and time.

  • Site safety, OSHA compliance, and protection of persons and property belong to the contractor; the architect has no authority over safety programs.

  • Shop drawing review confirms conformance with the design concept only; the review stamp does not relieve the contractor of responsibility for quantities, dimensions, and field conditions.

  • Testing of questionable work may be ordered by the architect; the owner pays if the work proves acceptable and the contractor pays if it does not.

  • Mock-ups and samples are approved before the related work proceeds, and the approved mock-up sets the standard for workmanship and appearance.

Quick reference

Administrative Procedures & Protocols

  • RFIs must be answered in writing; the response is incorporated into the contract documents but changes cost or time only through a change order.

  • A change order is signed by owner, architect, and contractor and states the change in contract sum and/or contract time.

  • A construction change directive is signed only by owner and architect; the contractor must proceed and pricing is negotiated or determined later.

  • An architect's supplemental instruction conveys a minor interpretation that does not change contract sum or time and requires no contractor signature.

  • The architect must certify a complete application for payment within 7 days of receipt or return it with written reasons within that same period (AIA A201).

  • Retainage is commonly 5–10% of each progress payment; a portion is released at substantial completion and the balance at final completion.

  • Lien waivers are conditional (effective only when payment is received) or unconditional (effective on signing), and progress or final in scope.

  • Time extensions are granted only for excusable, non-contractor-caused delays; contractor-caused delay generally carries no extension unless the owner waives liquidated damages.

  • The contractor maintains red-lined record documents reflecting actual installed conditions; the architect may examine them at any time.

Quick reference

Project Closeout & Evaluation

  • Substantial completion is the stage at which the work is sufficiently complete for the owner's intended use; the architect's certificate starts warranty periods and releases part of retainage.

  • Final completion requires completion of all punch list items, final inspection, the final payment application, final lien waivers, and consent of surety.

  • Closeout submittals include record (as-built) documents, O&M manuals, warranties, attic stock, spare parts, keys, and evidence of final cleaning.

  • A certificate of occupancy is issued by the authority having jurisdiction confirming code compliance and legal use; a temporary CO may carry conditions and an expiration date.

  • Consent of surety to final payment confirms the surety's bonded obligations are satisfied and is typically a prerequisite to releasing final retainage.

  • The warranty period is commonly one year from substantial completion; the architect determines whether a reported defect is covered or is normal wear or owner misuse.

  • A post-occupancy evaluation is typically performed roughly 6–12 months after occupancy using occupant surveys, performance data, and maintenance records.

  • The final certificate for payment (AIA G704) is issued after final inspection and certifies that the work is complete in accordance with the contract documents.