ARE 5.0: PA study materials
ARE 5.0: PA study resources

ARE 5.0: PA study plan

ARE 5.0: PA · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Building Analysis & Programming

  • Decompose a sample project brief into owner-stated requirements, code-driven requirements, and designer-derived requirements, tagging each item with its source.

  • Compute net assignable area, gross area, and efficiency ratio for three different program sets, showing the arithmetic.

  • Build an adjacency matrix and a corresponding bubble diagram for a 10,000-15,000 sf institutional program.

  • List the categories of programmatic data gathered in a pre-design interview and write one probe question for each category.

Your checkpoint

A one-page program document for a 12,000 sf community health clinic containing a source-tagged requirement table, an adjacency matrix, and a net/gross area calculation that closes within 5% of the target area.

Week 2

Building Analysis & Programming

  • Compare three structural bay systems and quantify how each changes usable floor area within a fixed gross footprint.

  • Analyze a building section to locate MEP distribution zones and calculate the resulting floor-to-floor height.

  • Evaluate two adaptive-reuse scenarios for an existing building against the same program, scoring each on structural capacity, egress, and floor-plate fit.

  • Assemble a preliminary code summary table (occupancy, construction type, allowable area and height, egress) for one program scenario.

Your checkpoint

A building analysis worksheet that compares new-construction and adaptive-reuse options for the same program and ends with a written, scored recommendation.

Week 3

Environmental & Contextual Conditions

  • Plot sun angles for the summer and winter solstices at a stated latitude and mark resulting shadow lengths on a site plan.

  • Classify a site's climate zone and derive passive design implications for orientation, glazing ratio, and thermal mass.

  • Analyze prevailing wind and topographic data to designate desirable and undesirable outdoor zones on a hypothetical site.

  • Identify context factors (adjacency, scale, character, views, noise) that constrain massing and restate them as design criteria.

Your checkpoint

A three-diagram site response set (sun/shadow study, annotated wind rose, context map) accompanied by a written list of 10 context-derived design criteria.

Week 4

Environmental & Contextual Conditions & Codes & Regulations

  • Determine the buildable envelope on a lot after applying setbacks, height limits, and floor-area ratio, then compute the resulting gross floor area.

  • Compare infiltration, detention, and permeable-surface stormwater strategies for one site and estimate required storage volumes.

  • Interpret a geotechnical summary to select a foundation approach and flag the risks it introduces.

  • Check a site plan against grading, drainage, and utility easement constraints and note conflicts.

Your checkpoint

A zoning envelope calculation sheet showing setbacks, FAR, height limit, and resulting floor area, paired with a buildable-volume axonometric sketch.

Week 5

Codes & Regulations

  • Classify a mixed-occupancy building into occupancy groups and apply the separated versus non-separated occupancy rules.

  • Determine allowable building area and height for a given construction type, applying frontage increase and sprinkler allowances.

  • Calculate occupant load, required egress width, and number of exits for three floor plans.

  • Check a floor plan against accessibility requirements for routes, clearances, and toilet room layouts.

Your checkpoint

A code analysis summary for a 3-story mixed-use building containing occupancy classification, allowable area/height calculations, an occupant load table, and an egress compliance checklist with cited deficiencies.

Week 6

Site Analysis & Programming

  • Compile a site inventory checklist covering utilities, access, topography, vegetation, and hazards, and rate the availability of each data item.

  • Score three candidate parcels against a weighted criteria matrix and justify the weighting.

  • Analyze vehicular and pedestrian circulation to locate building entry points and service access.

  • Estimate parking demand and lay out a parking and loading scheme that satisfies a stated zoning requirement.

Your checkpoint

A weighted site selection matrix for three parcels with a written recommendation, plus a circulation and parking diagram for the preferred site.

Week 7

Site Analysis & Programming & Codes & Regulations

  • Synthesize site analysis into a site development concept that fixes building placement, orientation, and landscape response.

  • Reconcile the program against the site's buildable envelope and report any surplus or shortfall in square footage.

  • Draft a 500-word site analysis narrative written for a client audience.

  • Cross-check the site concept against zoning, stormwater, and parking regulations and list every required variance.

Your checkpoint

A combined site plan and programming report that reconciles programmed area to buildable area with a closure within plus or minus 5%.

Week 8

Environmental & Contextual Conditions & Codes & Regulations & Site Analysis & Programming & Building Analysis & Programming

  • Complete two timed 60-question practice sets and log every missed item by domain and error type.

  • Rewrite notes into one-page summary sheets for the domains showing the lowest practice accuracy.

  • Rehearse calculations (FAR, occupant load, egress width, area and frontage increases) under a three-minute-per-item limit.

  • Restate the programming-to-site-analysis workflow end to end without notes.

Your checkpoint

A scored practice exam log reporting domain accuracy percentages plus a remediation sheet listing specific actions for any domain scoring below 70%.

Milestones

Week 2: Produce a professional program document and building analysis worksheet from memory in under 90 minutes each, with area calculations closing within 5%.

Week 4: Calculate a correct buildable envelope and gross floor area for an unseen lot description in under 15 minutes with no reference material.

Week 6: Complete a full code analysis and a weighted site selection matrix for unseen scenarios, scoring at least 75% on self-graded checks.

Week 8: Score 70% or higher on both timed practice sets overall and 65% or higher in every domain; schedule the exam only if both thresholds are met.