ASHRAE BCxP study materials
ASHRAE BCxP study resources

ASHRAE BCxP cheat sheet

ASHRAE BCxP · Keep the key ideas within reach.

Quick reference

Commissioning Process Fundamentals and Project Initiation

  • Commissioning (Cx) is a quality-focused process applied to new construction, renovation, and existing buildings to verify that systems perform per the Owner's Project Requirements (OPR).

  • ASHRAE Guideline 0 defines the Cx process; ASHRAE Standard 202 defines the minimum Cx requirements that can be adopted as code language.

  • The Cx Team is led by the Commissioning Authority (CxA); the CxA must be independent of the design and construction contract for the systems being commissioned to preserve objectivity.

  • Primary phases: pre-design, design, construction, occupancy/acceptance, and post-acceptance (warranty). Each phase has defined deliverables and review activities.

  • The Cx Plan documents scope, team roles, schedule, communication protocols, test procedures, and deliverable formats; it is updated as the project evolves.

  • Pre-design phase deliverables include the initial OPR, initial Cx Plan, and identification of systems to be commissioned (Cx scope).

  • Systems typically commissioned: HVAC&R, controls/BAS, plumbing, electrical power, lighting controls, fire protection/life safety, and renewable energy systems.

  • The Cx process does not replace design review, construction inspection, or contractor quality control; it supplements and verifies them.

Quick reference

Owner's Project Requirements, Basis of Design, and Design Review

  • The OPR is a written document that details the functional requirements of the project and the expectations of how the facility and systems will be used and operated.

  • OPR content includes project goals, measurable performance criteria, cost/budget, schedule, occupant comfort, environmental/sustainability goals, and O&M expectations.

  • The Basis of Design (BOD) is the designer's written record of design assumptions, calculations, and decisions that satisfy the OPR.

  • Design review in Cx compares the BOD against the OPR to confirm each OPR requirement is addressed and to flag gaps for resolution.

  • OPR updates require owner approval; BOD updates require designer action and CxA review of impacts on Cx scope and test procedures.

  • Measurable OPR criteria (e.g., temperature setpoints, ventilation rates, IAQ targets, energy use intensity) become the acceptance benchmarks for functional performance testing.

  • Design review checkpoints typically occur at schematic design, design development, and construction documents milestones.

  • Documented OPR-BOD discrepancies are tracked in an issues log with assigned responsibility and resolution status.

Quick reference

Commissioning Specifications, Contractor Procurement, and Submittals

  • The Cx specification (typically Division 01, Section 01 91 00) defines contractor responsibilities, submittal requirements, testing obligations, and schedule impacts.

  • Cx specification must require the contractor to participate in Cx activities, provide qualified personnel, and include Cx in subcontractor scopes and schedules.

  • Procurement should require the CxA to review contractor qualifications and confirm the CxA's authority and independence before contract award.

  • Pre-submittal and submittal review: contractor submits product data, shop drawings, and O&M data; CxA reviews for Cx-relevant performance characteristics.

  • The contractor must submit a construction Cx schedule and a testing plan consistent with the Cx Plan and the project schedule.

  • The Cx specification should establish a pre-functional checklist requirement and a functional performance test (FPT) requirement for each commissioned system.

  • Submittal review should verify that submitted equipment and controls match the BOD performance criteria and support the OPR benchmarks.

  • O&M manual and systems manual requirements should be defined in the specification so training and documentation deliverables are contractually enforceable.

Quick reference

Construction-Phase Commissioning Activities and Functional Performance Testing

  • Pre-functional checklists (PFCs) verify installation, static conditions, and readiness before functional testing; they are completed by the installing contractor and verified by the CxA.

  • Functional performance testing (FPT) demonstrates that systems and components operate interactively and meet the OPR under specified conditions.

  • FPT procedures must specify test prerequisites, instrumentation, steps, acceptance criteria, and documentation of results.

  • Test scripts should cover normal operation, part-load, failure modes, alarms, safeties, interlocks, and sequence of operations.

  • Prerequisites for FPT include completed PFCs, calibrated test instruments, trained operators present, and stable system conditions.

  • Failed tests are documented, deficiencies are logged with responsible party and due date, and retesting is required after correction.

  • The CxA witnesses or directs FPT and records results; contractor personnel perform the actual testing and adjustments.

  • Construction-phase Cx also includes periodic site observation, issue tracking, and progress reporting to the owner.

Quick reference

Seasonal Testing, Training, Systems Manual, and Final Commissioning Report

  • Seasonal testing verifies performance under conditions not achievable during initial FPT, such as peak heating, peak cooling, and shoulder-season changeover.

  • Seasonal test procedures should be planned during design and scheduled for the appropriate season within the warranty period.

  • Training must cover operation, maintenance, and troubleshooting of commissioned systems; it is verified by attendance records and training evaluations.

  • The systems manual compiles OPR, BOD, equipment data, control sequences, as-built information, O&M procedures, and training records.

  • The final Cx report documents the Cx process, test results, unresolved issues, deferred seasonal testing, and the CxA's statement of compliance.

  • The final report should identify systems that passed, systems with open deficiencies, and any limitations of the Cx scope.

  • Post-acceptance Cx includes warranty-phase reviews, seasonal testing completion, and verification that open issues are resolved.

  • Lessons-learned feedback from the Cx process should be delivered to the owner for future projects and facility operation improvements.