ASHRAE BCxP study materials
ASHRAE BCxP study resources

ASHRAE BCxP study plan

ASHRAE BCxP · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Commissioning Process Fundamentals and Project Initiation

  • Define the commissioning process phases and list the deliverables produced in each

  • Distinguish the roles of owner, Cx authority, design team, contractor, and TAB provider in your own written summary

  • Identify the differences between commissioning, retro-commissioning, and ongoing commissioning

  • Map the project initiation activities (Cx scope, budget, schedule, team selection) onto a sample project timeline

Your checkpoint

One-page process map of the Cx lifecycle with phase deliverables and responsible parties labeled

Week 2

Owner's Project Requirements, Basis of Design, and Design Review

  • Draft a complete set of Owner's Project Requirements for a hypothetical building, covering program, environmental, and operational criteria

  • Translate each OPR item into a corresponding Basis of Design element

  • Perform a design review against the OPR and log at least 10 findings with severity ratings

  • Explain how OPR and BOD documents flow into later testing and acceptance decisions

Your checkpoint

Mock OPR plus BOD cross-reference table with a 10-item design review findings log

Week 3

Commissioning Specifications, Contractor Procurement, and Submittals

  • Outline the sections of a commissioning specification, including roles, submittal requirements, and testing obligations

  • Draft contractor procurement language that assigns Cx responsibilities and acceptance conditions

  • Build a submittal review checklist tied to commissioning-critical equipment

  • Sequence pre-functional checklists for three representative equipment types

Your checkpoint

Draft Cx specification outline with a submittal review checklist for three equipment types

Week 4

Construction-Phase Commissioning Activities and Functional Performance Testing

  • Design functional performance test procedures for an air handling unit, a chiller plant, and a controls sequence

  • Write pass/fail acceptance criteria and prerequisite conditions for each test

  • Plan a construction-phase issue log and resolution workflow

  • Identify safety and coordination requirements before energizing and testing systems

Your checkpoint

Three complete FPT scripts with prerequisites, steps, expected results, and acceptance criteria

Week 5

Construction-Phase Commissioning Activities and Functional Performance Testing & Seasonal Testing, Training, Systems Manual, and Final Commissioning Report

  • Construct a seasonal testing plan that identifies deferred and weather-dependent tests

  • Define the contents and review cycle of the systems manual

  • Design a training plan with audience, objectives, and verification of competency

  • Draft the structure of the final commissioning report

Your checkpoint

Seasonal testing matrix plus a systems manual table of contents and training plan outline

Week 6

Seasonal Testing, Training, Systems Manual, and Final Commissioning Report & Commissioning Process Fundamentals and Project Initiation

  • Assemble a complete final Cx report from the artifacts produced in earlier weeks

  • Verify that each OPR requirement is traced to a test result or documented acceptance

  • Write a lessons-learned summary that identifies process gaps across the Cx lifecycle

  • Rehearse explaining the Cx authority's independence and authority to a project team

Your checkpoint

Mock final commissioning report with an OPR-to-test traceability matrix

Week 7

Commissioning Process Fundamentals and Project Initiation & Owner's Project Requirements, Basis of Design, and Design Review & Commissioning Specifications, Contractor Procurement, and Submittals

  • Answer timed practice sets covering initiation, OPR/BOD, and specifications

  • Correct every missed item by writing the underlying principle in your own words

  • Re-derive the OPR-to-BOD-to-specification linkage without notes

  • Identify your three weakest subtopics and schedule targeted review

Your checkpoint

Error log of missed practice items with corrected principles and a ranked weakness list

Week 8

Construction-Phase Commissioning Activities and Functional Performance Testing & Seasonal Testing, Training, Systems Manual, and Final Commissioning Report

  • Answer timed practice sets covering construction-phase activities and closeout

  • Redo FPT and seasonal testing scenarios under time pressure

  • Review the full weakness list and confirm each item is resolved

  • Complete a full-length timed mock exam and score it

Your checkpoint

Full-length timed mock exam score with a final one-page review sheet

Milestones

Week 2: Can produce an OPR and matching BOD cross-reference from memory in under 45 minutes

Week 4: Three FPT scripts written with acceptance criteria and prerequisites, self-scored against a checklist

Week 6: Mock final report traces every OPR item to a test or documented acceptance

Week 8: Full-length timed mock exam completed with score recorded and all logged errors resolved