ASHRAE BCxP · Get comfortable with the vocabulary.

Commissioning (Cx)

A quality-focused process that verifies and documents that building systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the owner's project requirements.

Related: Owner's Project Requirements, Commissioning Authority
Commissioning Authority (CxA)

The individual or entity leading the commissioning process, responsible for planning, coordinating, and documenting verification activities while maintaining independence from the design and construction team.

Related: Commissioning Plan, Commissioning Team
Commissioning Team

The group carrying out commissioning activities, typically including the owner, CxA, design professionals, contractors, and manufacturers' representatives, each with defined roles and responsibilities.

Related: Commissioning Authority, Commissioning Plan
Commissioning Plan

A document outlining the scope, schedule, roles, deliverables, and procedures for commissioning activities throughout all project phases, serving as the roadmap for the commissioning process.

Related: Commissioning Authority, Commissioning Team
Pre-Design Phase

The earliest project stage where commissioning scope, budget, and team roles are established, and initial owner project requirements begin to be captured before design work starts.

Related: Owner's Project Requirements, Commissioning Plan
Owner's Project Requirements (OPR)

A written document describing the owner's functional needs, performance expectations, operational criteria, and constraints that the finished project must satisfy.

Related: Basis of Design, Design Review
Basis of Design (BOD)

A document recording the design team's assumptions, calculations, system selections, and rationale that explain how the design will satisfy the owner's project requirements.

Related: Owner's Project Requirements, Design Review
Design Review

A structured examination of design documents by the commissioning authority to confirm the design can meet the owner's project requirements and is commissionable before construction begins.

Related: Basis of Design, Owner's Project Requirements
Commissioning Design Review Comment

A written issue log entry recording a concern, gap, or recommendation identified during design review, tracked with a responsible party and resolution status.

Related: Design Review, Issues Log
Systems Manual

A compiled reference containing design and as-built information, equipment data, operating procedures, and maintenance guidance needed to operate and maintain the building after turnover.

Related: As-Built Documentation, Training Plan
Commissioning Specification

The contract document section that assigns commissioning responsibilities, submittal and testing requirements, and acceptance criteria to the construction team.

Related: Contractor Commissioning Responsibilities, Submittal Review
Contractor Commissioning Responsibilities

The duties assigned to the installing contractor, such as providing submittals, performing startup checks, executing prefunctional checklists, and supporting functional performance tests.

Related: Commissioning Specification, Prefunctional Checklist
Commissioning Scope Matrix

A table identifying which systems and equipment are commissioned, and which commissioning activities and deliverables apply to each, clarifying boundaries of the commissioning effort.

Related: Commissioning Specification, Systems Manual
Submittal Review

The process of checking contractor product data, shop drawings, and coordination documents against the basis of design and specifications before equipment is approved for installation.

Related: Commissioning Specification, Basis of Design
Pre-Bid Conference

A meeting held before bid submission where the owner and commissioning authority explain commissioning requirements so bidders can price and plan for them accurately.

Related: Commissioning Specification, Contractor Commissioning Responsibilities
Construction Checklist

A documented list of installation verification items completed by the contractor during construction to confirm equipment is installed per manufacturer instructions and design intent.

Related: Prefunctional Checklist, Installation Verification
Prefunctional Checklist

A structured set of static checks performed before energization or dynamic testing, covering items such as cleanliness, alignment, labeling, sensor calibration, and control point verification.

Related: Construction Checklist, Functional Performance Test
Functional Performance Test (FPT)

A scripted, dynamic test that exercises a system under specified conditions to verify it responds and performs in accordance with the design intent and owner's project requirements.

Related: Test Procedure, Acceptance Criteria
Test Procedure

A written step-by-step script listing prerequisites, actions, expected responses, instrumentation, and documentation requirements used to execute a functional performance test consistently.

Related: Functional Performance Test, Acceptance Criteria
Acceptance Criteria

The predefined measurable conditions or tolerances a system must meet for a test to be considered passing and the work accepted.

Related: Functional Performance Test, Test Procedure
Installation Verification

Confirmation that equipment and systems are installed, connected, labeled, and accessible as specified, typically documented through checklists before functional testing begins.

Related: Construction Checklist, Prefunctional Checklist
Issues Log

A tracked record of commissioning findings, nonconformances, and open items, each with an owner, priority, and resolution status used to drive closure before acceptance.

Related: Commissioning Design Review Comment, Deferred Testing
Deferred Testing

Functional tests that cannot be completed during the normal construction schedule, such as seasonal performance checks, which are documented and scheduled for later execution.

Related: Seasonal Testing, Issues Log
Seasonal Testing

Verification performed when weather conditions allow evaluation of heating, cooling, or part-load performance that could not be observed during initial functional testing.

Related: Deferred Testing, Functional Performance Test
Training Plan

A document defining the scope, audience, schedule, and content of owner staff training on system operation and maintenance, including verification of learning outcomes.

Related: Systems Manual, Training Verification
Training Verification

Confirmation that required training was delivered and that operators can demonstrate the knowledge and skills needed to run and maintain the systems.

Related: Training Plan, Systems Manual
As-Built Documentation

Record drawings and updated documents reflecting actual installed conditions, including equipment locations, control sequences, and deviations from the original design.

Related: Systems Manual, Final Commissioning Report
Final Commissioning Report

The closing deliverable summarizing commissioning scope, activities performed, test results, unresolved issues, deferred testing, and a statement of overall system readiness.

Related: Issues Log, Deferred Testing
Commissioning Provider

An organization or firm engaged to deliver commissioning services, encompassing the commissioning authority role and associated staff and resources.

Related: Commissioning Authority, Commissioning Team
Design Intent

The documented concept and performance goals the designer intends each system to achieve, used as a reference when developing tests and evaluating performance.

Related: Basis of Design, Functional Performance Test
Sequence of Operations

A written description of how controls are intended to make equipment and systems respond to conditions, setpoints, and modes; a primary basis for functional test scripts.

Related: Basis of Design, Functional Performance Test
Controls Point Verification

Checking that each sensor, actuator, and control point is correctly installed, addressed, calibrated, and reporting to the building automation system before dynamic testing.

Related: Prefunctional Checklist, Sequence of Operations
Acceptance Phase

The project stage where testing is completed, issues are closed or documented, training and manuals are delivered, and the owner formally accepts the commissioned systems.

Related: Final Commissioning Report, Substantial Completion
Substantial Completion

The milestone at which the work is sufficiently complete for the owner to occupy and use it for its intended purpose, subject to remaining punch list items.

Related: Acceptance Phase, Final Commissioning Report
Punch List

A record of incomplete or deficient work items identified near turnover that must be corrected before final acceptance and closeout.

Related: Issues Log, Substantial Completion
Retrocommissioning

A commissioning process applied to an existing building that was not commissioned when built, focused on identifying and correcting operational deficiencies.

Related: Commissioning (Cx), Issues Log
Continuous Commissioning

An ongoing process of monitoring, analyzing, and adjusting system performance over the building's life to sustain efficiency and meet current owner requirements.

Related: Retrocommissioning, Systems Manual