ASHRAE BCxP key terms
ASHRAE BCxP · Get comfortable with the vocabulary.
- Commissioning (Cx)
- Related: Owner's Project Requirements, Commissioning Authority
A quality-focused process that verifies and documents that building systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the owner's project requirements.
- Commissioning Authority (CxA)
- Related: Commissioning Plan, Commissioning Team
The individual or entity leading the commissioning process, responsible for planning, coordinating, and documenting verification activities while maintaining independence from the design and construction team.
- Commissioning Team
- Related: Commissioning Authority, Commissioning Plan
The group carrying out commissioning activities, typically including the owner, CxA, design professionals, contractors, and manufacturers' representatives, each with defined roles and responsibilities.
- Commissioning Plan
- Related: Commissioning Authority, Commissioning Team
A document outlining the scope, schedule, roles, deliverables, and procedures for commissioning activities throughout all project phases, serving as the roadmap for the commissioning process.
- Pre-Design Phase
- Related: Owner's Project Requirements, Commissioning Plan
The earliest project stage where commissioning scope, budget, and team roles are established, and initial owner project requirements begin to be captured before design work starts.
- Owner's Project Requirements (OPR)
- Related: Basis of Design, Design Review
A written document describing the owner's functional needs, performance expectations, operational criteria, and constraints that the finished project must satisfy.
- Basis of Design (BOD)
- Related: Owner's Project Requirements, Design Review
A document recording the design team's assumptions, calculations, system selections, and rationale that explain how the design will satisfy the owner's project requirements.
- Design Review
- Related: Basis of Design, Owner's Project Requirements
A structured examination of design documents by the commissioning authority to confirm the design can meet the owner's project requirements and is commissionable before construction begins.
- Commissioning Design Review Comment
- Related: Design Review, Issues Log
A written issue log entry recording a concern, gap, or recommendation identified during design review, tracked with a responsible party and resolution status.
- Systems Manual
- Related: As-Built Documentation, Training Plan
A compiled reference containing design and as-built information, equipment data, operating procedures, and maintenance guidance needed to operate and maintain the building after turnover.
- Commissioning Specification
- Related: Contractor Commissioning Responsibilities, Submittal Review
The contract document section that assigns commissioning responsibilities, submittal and testing requirements, and acceptance criteria to the construction team.
- Contractor Commissioning Responsibilities
- Related: Commissioning Specification, Prefunctional Checklist
The duties assigned to the installing contractor, such as providing submittals, performing startup checks, executing prefunctional checklists, and supporting functional performance tests.
- Commissioning Scope Matrix
- Related: Commissioning Specification, Systems Manual
A table identifying which systems and equipment are commissioned, and which commissioning activities and deliverables apply to each, clarifying boundaries of the commissioning effort.
- Submittal Review
- Related: Commissioning Specification, Basis of Design
The process of checking contractor product data, shop drawings, and coordination documents against the basis of design and specifications before equipment is approved for installation.
- Pre-Bid Conference
- Related: Commissioning Specification, Contractor Commissioning Responsibilities
A meeting held before bid submission where the owner and commissioning authority explain commissioning requirements so bidders can price and plan for them accurately.
- Construction Checklist
- Related: Prefunctional Checklist, Installation Verification
A documented list of installation verification items completed by the contractor during construction to confirm equipment is installed per manufacturer instructions and design intent.
- Prefunctional Checklist
- Related: Construction Checklist, Functional Performance Test
A structured set of static checks performed before energization or dynamic testing, covering items such as cleanliness, alignment, labeling, sensor calibration, and control point verification.
- Functional Performance Test (FPT)
- Related: Test Procedure, Acceptance Criteria
A scripted, dynamic test that exercises a system under specified conditions to verify it responds and performs in accordance with the design intent and owner's project requirements.
- Test Procedure
- Related: Functional Performance Test, Acceptance Criteria
A written step-by-step script listing prerequisites, actions, expected responses, instrumentation, and documentation requirements used to execute a functional performance test consistently.
- Acceptance Criteria
- Related: Functional Performance Test, Test Procedure
The predefined measurable conditions or tolerances a system must meet for a test to be considered passing and the work accepted.
- Installation Verification
- Related: Construction Checklist, Prefunctional Checklist
Confirmation that equipment and systems are installed, connected, labeled, and accessible as specified, typically documented through checklists before functional testing begins.
- Issues Log
- Related: Commissioning Design Review Comment, Deferred Testing
A tracked record of commissioning findings, nonconformances, and open items, each with an owner, priority, and resolution status used to drive closure before acceptance.
- Deferred Testing
- Related: Seasonal Testing, Issues Log
Functional tests that cannot be completed during the normal construction schedule, such as seasonal performance checks, which are documented and scheduled for later execution.
- Seasonal Testing
- Related: Deferred Testing, Functional Performance Test
Verification performed when weather conditions allow evaluation of heating, cooling, or part-load performance that could not be observed during initial functional testing.
- Training Plan
- Related: Systems Manual, Training Verification
A document defining the scope, audience, schedule, and content of owner staff training on system operation and maintenance, including verification of learning outcomes.
- Training Verification
- Related: Training Plan, Systems Manual
Confirmation that required training was delivered and that operators can demonstrate the knowledge and skills needed to run and maintain the systems.
- As-Built Documentation
- Related: Systems Manual, Final Commissioning Report
Record drawings and updated documents reflecting actual installed conditions, including equipment locations, control sequences, and deviations from the original design.
- Final Commissioning Report
- Related: Issues Log, Deferred Testing
The closing deliverable summarizing commissioning scope, activities performed, test results, unresolved issues, deferred testing, and a statement of overall system readiness.
- Commissioning Provider
- Related: Commissioning Authority, Commissioning Team
An organization or firm engaged to deliver commissioning services, encompassing the commissioning authority role and associated staff and resources.
- Design Intent
- Related: Basis of Design, Functional Performance Test
The documented concept and performance goals the designer intends each system to achieve, used as a reference when developing tests and evaluating performance.
- Sequence of Operations
- Related: Basis of Design, Functional Performance Test
A written description of how controls are intended to make equipment and systems respond to conditions, setpoints, and modes; a primary basis for functional test scripts.
- Controls Point Verification
- Related: Prefunctional Checklist, Sequence of Operations
Checking that each sensor, actuator, and control point is correctly installed, addressed, calibrated, and reporting to the building automation system before dynamic testing.
- Acceptance Phase
- Related: Final Commissioning Report, Substantial Completion
The project stage where testing is completed, issues are closed or documented, training and manuals are delivered, and the owner formally accepts the commissioned systems.
- Substantial Completion
- Related: Acceptance Phase, Final Commissioning Report
The milestone at which the work is sufficiently complete for the owner to occupy and use it for its intended purpose, subject to remaining punch list items.
- Punch List
- Related: Issues Log, Substantial Completion
A record of incomplete or deficient work items identified near turnover that must be corrected before final acceptance and closeout.
- Retrocommissioning
- Related: Commissioning (Cx), Issues Log
A commissioning process applied to an existing building that was not commissioned when built, focused on identifying and correcting operational deficiencies.
- Continuous Commissioning
- Related: Retrocommissioning, Systems Manual
An ongoing process of monitoring, analyzing, and adjusting system performance over the building's life to sustain efficiency and meet current owner requirements.