Question 1Core units of competency

Which document primarily governs safe work practices and site-specific hazards before tiling work begins on a new site?

  1. The council development approval notice
  2. The customer's written quotation
  3. The manufacturer's tile colour chart
  4. The safe work method statement for the task Correct answer.

Explanation

A safe work method statement sets out the high-risk activities, the hazards involved, and the control measures to be applied before work starts. It is reviewed and signed on site so every worker understands the risks. Colour charts, quotations and approvals do not describe hazard controls.

Question 2Core units of competency

When setting out battens on a roof, the batten spacing must be determined mainly by which factor?

  1. The colour of the tiles being installed
  2. The tile manufacturer's specified gauge for the tile profile Correct answer.
  3. The width of the scaffolding planks
  4. The length of the available timber stock

Explanation

Batten spacing, or gauge, is dictated by the tile profile so that each course laps the one below correctly and the fixing holes align. Manufacturers publish the correct gauge for each tile, and deviating from it causes poor lapping and leaks. Timber length, tile colour and scaffold width do not govern the gauge.

Question 3Core units of competency

What is the main purpose of sarking or underlay installed beneath roof tiles?

  1. To insulate the roof against heat gain
  2. To collect and discharge water that passes the tiles Correct answer.
  3. To bond the tiles together into one sheet
  4. To increase the structural strength of the rafters

Explanation

Sarking is a secondary weather barrier that catches any wind-driven or condensation water passing the tiles and directs it to the gutter. It does not carry structural loads, provide meaningful insulation on its own, or fix tiles together. Correct lapping and drainage of the sarking are essential to its performance.

Question 4Core units of competency

Which personal protective equipment is essential when working at height on a pitched roof?

  1. Knee pads for kneeling on battens
  2. A dust mask rated for fine silica
  3. A correctly fitted fall-arrest harness where required Correct answer.
  4. A high-visibility vest only

Explanation

Fall-arrest or restraint equipment is the key control for work at height on pitched roofs and must be fitted and anchored correctly. Dust masks, vests and knee pads offer comfort or other protection but do nothing to arrest a fall. A hierarchy of controls should be applied before relying on PPE.

Question 5Core units of competency

Which fixing method is most appropriate for tiles in the first course at the eaves on a typical tiled roof?

  1. Rely on the weight of the tiles
  2. Fix only the end tiles of the course
  3. Fix every tile with the specified fastener Correct answer.
  4. Fix every second tile only

Explanation

Eaves course tiles are exposed to high wind uplift and are typically required to be fixed at every tile, in line with the manufacturer and standard requirements. Intermittent fixing or relying on tile mass leaves the edge vulnerable to wind damage. End-only fixing does not secure the intermediate tiles.

Question 6Core units of competency

What is the standard purpose of a ridge capping on a tiled roof?

  1. To vent the roof cavity to the atmosphere
  2. To support the ends of the battens
  3. To provide a walkway for future maintenance
  4. To cover the junction of two roof planes and shed water Correct answer.

Explanation

Ridge cappings close the gap where opposing roof slopes meet, weatherproofing the apex and shedding water to both sides. They are bedded and pointed to seal the joint. They are not walkways, batten supports or ventilation devices.

Question 7Core units of competency

When mixing mortar for bedding ridge cappings, which property is most important for durability?

  1. The colour match to the tiles
  2. The brand of the mixing bucket
  3. The speed at which it sets in the bucket
  4. The correct ratio of cement, sand and water Correct answer.

Explanation

Mortar strength and durability depend on the correct proportions of cement, sand and water, mixed to a workable but not overly wet consistency. Colour matching is cosmetic, setting speed is a consequence of mix design, and the bucket brand is irrelevant. Over-wet mortar weakens and cracks.

Question 8Core units of competency

Why must roof tiles be stacked and distributed carefully on a roof during installation?

  1. To avoid overloading the roof structure or creating a hazard Correct answer.
  2. To make the tiles easier to colour match
  3. To reduce the number of nails required
  4. To keep the tiles cooler in the sun

Explanation

Concentrated stacks of tiles can exceed the design load of rafters and battens and may also fall and injure workers below. Loads should be spread and reduced as work proceeds. Temperature, colour matching and fixing counts are not the reason for careful distribution.

Question 9Core units of competency

A roof has a rise of 1.5 m over a horizontal run of 6 m. What is the pitch expressed as a ratio of rise to run?

  1. 1:4 Correct answer.
  2. 1:2
  3. 1:6
  4. 1:3

Explanation

Pitch as a ratio compares rise to run, so 1.5 m rise over 6 m run simplifies to 1:4. Dividing both figures by 1.5 gives the ratio directly. The other ratios do not match the given dimensions.

Question 10Core units of competency

A tile has a cover width of 300 mm. How many tiles are needed to cover a roof width of 9 m, ignoring cuts and waste?

  1. 30 Correct answer.
  2. 33
  3. 36
  4. 27

Explanation

Dividing the total width of 9000 mm by the 300 mm cover width gives 30 tiles per course. Cover width, not full tile width, is used because tiles lap sideways. The other answers result from arithmetic errors.

Question 11Core units of competency

During installation, why should tiles be blended from several pallets at once?

  1. To speed up the fixing of nails
  2. To increase the weight on the battens
  3. To reduce the amount of cutting required
  4. To even out shade variation between production batches Correct answer.

Explanation

Tiles can vary slightly in shade between batches, so drawing from multiple pallets and mixing them spreads any variation across the roof. This avoids visible colour patches. Blending does not change structural loading, fixing speed or cutting needs.

Question 12Core units of competency

What is the correct lapping requirement for sarking laid on a pitched roof?

  1. Lap sheets randomly to save material
  2. Lap according to the manufacturer's specification, typically with upper sheets over lower Correct answer.
  3. Lap only at the ridge and eaves
  4. Butt sheets edge to edge without overlap

Explanation

Sarking must be lapped so water runs over the joint and down the roof, with the upper sheet overlapping the lower one by the manufacturer's specified amount. Butting sheets or random lapping allows water to pass through. Correct lapping at ridge and eaves is also required but not only there.

Question 13Core units of competency

A tiler notices a broken tile in a completed section. What is the correct action?

  1. Replace the broken tile and reinstate the fixing Correct answer.
  2. Seal the crack with silicone and leave it
  3. Leave it because one tile does not matter
  4. Paint over the crack to hide it

Explanation

Broken tiles allow water penetration and must be replaced, with the new tile correctly fixed and lapped. Sealing or painting hides but does not repair the defect, and leaving it invites leaks and callbacks. Quality control requires defective work to be corrected.

Question 14Core units of competency

Why is it important to keep battens straight and parallel during installation?

  1. To reduce the total number of battens needed
  2. To allow the use of shorter nails
  3. To make the roof lighter in weight
  4. So tile courses align and lap correctly across the roof Correct answer.

Explanation

Straight, parallel battens at the correct gauge keep tile courses level and ensure each course laps the one below properly. Wandering battens cause uneven courses, poor lapping and visible defects. Batten quantity, nail length and roof weight are not the reason.

Question 15Core units of competency

Which practice best controls the risk of tools falling from a roof to the ground below?

  1. Tethering tools and using toe boards or edge protection Correct answer.
  2. Storing tools on the scaffold plank edge
  3. Passing tools by throwing them between workers
  4. Leaving tools loose on the roof surface

Explanation

Dropped tools are a serious struck-by hazard, so tethering them and using toe boards or edge protection prevents objects reaching people below. Loose storage, throwing and edge storage all increase the risk of falls. Exclusion zones below also support these controls.

Question 16Core units of competency

When should a roof tile be mechanically fixed rather than relying on bedding alone?

  1. Whenever the tiler prefers it
  2. Only when the tile is a dark colour
  3. In high wind areas as specified by the standard and manufacturer Correct answer.
  4. Only on the northern side of the roof

Explanation

Wind uplift governs mechanical fixing, and standards and manufacturers specify where nails, screws or clips are required, particularly in high wind zones and at edges. Colour and orientation do not determine fixing. Personal preference cannot override the specification.

Question 17Core units of competency

What is the purpose of a tile clip in roof tiling?

  1. To hold tiles down against wind uplift where nailing is impractical Correct answer.
  2. To join two tiles edge to edge permanently
  3. To support the weight of the tiler
  4. To seal the gap between courses

Explanation

Clips mechanically restrain tiles, often where a nail cannot be driven or where extra uplift resistance is needed at edges and ridges. They do not permanently join tiles, carry worker loads or seal joints. Bedding and pointing perform the sealing role.

Question 18Core units of competency

A tiler is cutting tiles with a powered saw. Which control most directly reduces exposure to crystalline silica dust?

  1. Cutting indoors with the doors closed
  2. Working faster to finish before dust builds up
  3. Wet cutting or on-tool dust extraction with suitable respiratory protection Correct answer.
  4. Wearing only safety glasses

Explanation

Silica dust from cutting tiles is controlled at the source by wet cutting or dust extraction, backed by appropriate respiratory protection. Speed, enclosed spaces and eye protection alone do not reduce inhalation exposure. Enclosing the space can actually increase concentration.

Question 19Core units of competency

Why is it necessary to install flashing at a roof-to-wall junction?

  1. To improve the appearance of the junction
  2. To support the wall cladding above
  3. To provide a fixing point for tiles
  4. To direct water away from the junction and prevent penetration Correct answer.

Explanation

Flashing at a roof-to-wall abutment collects water and directs it onto the roof or into a gutter so it cannot enter the building. It is a weatherproofing element, not a structural support, tile fixing point or decorative feature. Correct lapping of flashing with sarking and tiles is essential.

Question 20Core units of competency

When a roof has a very low pitch, what is the main reason for selecting a specific tile profile?

  1. The tile's minimum pitch rating must suit the roof slope to prevent water entry Correct answer.
  2. Low-pitch roofs require larger tiles for appearance
  3. Low-pitch roofs need fewer battens
  4. Tile colour fades faster on low pitches

Explanation

Each tile profile has a minimum pitch at which it sheds water without leakage, so the roof slope must meet or exceed that rating. Choosing a tile rated for a steeper pitch on a low roof risks water tracking under the laps. Size, batten count and colour fade are not the governing issue.

Question 21Core units of competency

A tiler must calculate the number of tiles for a gable roof 12 m long with a rafter length of 5 m, using tiles with a cover of 0.3 m by 0.4 m. Ignoring waste, approximately how many tiles are required for both slopes?

  1. 1000 Correct answer.
  2. 2000
  3. 750
  4. 500

Explanation

Each slope is 12 m by 5 m, giving 60 square metres, and both slopes give 120 square metres. Each tile covers 0.3 times 0.4, or 0.12 square metres, so 120 divided by 0.12 equals 1000 tiles. The other figures come from using one slope only or misapplying the cover area.

Question 22Core units of competency

Why must mortar bedding under ridge capping be kept clear of the drainage path of the tiles below?

  1. It makes the capping lighter
  2. Squeezed mortar can block water flow and cause pooling or leaks Correct answer.
  3. It prevents the capping from curing
  4. Mortar improves water flow when it protrudes

Explanation

Excess mortar squeezed out under the capping can form a dam that traps water on the roof, leading to overflow and leaks. Bedding should be neat and not obstruct the tile drainage path. Protruding mortar does not aid flow, reduce weight or affect curing.

Question 23Core units of competency

Which sequence correctly describes a typical roof tiling installation?

  1. Install battens, then sarking, then ridge cappings, then tiles
  2. Install sarking, then battens, then tiles, then ridge cappings Correct answer.
  3. Install tiles, then sarking, then battens, then ridge cappings
  4. Install ridge cappings, then tiles, then sarking, then battens

Explanation

The underlay is laid first to provide the weather barrier, battens are then fixed to carry the tiles, tiles are laid over the battens, and ridge cappings finish the apex. Reversing the order would trap or expose materials incorrectly. Each stage depends on the one before it.

Question 24Core units of competency

A completed roof shows uneven tile courses that dip in one area. Which is the most likely cause?

  1. Sarking lapped in the correct direction
  2. A batten fixed out of line or at the wrong gauge Correct answer.
  3. Tiles fixed with the specified nails
  4. Tiles blended from several pallets

Explanation

Uneven or dipping courses usually trace back to a batten that is out of line, bowed or set at the wrong gauge, which throws out the rows above it. Correct blending, lapping and fixing do not cause dips. The batten line should be checked and corrected.

Question 25Core units of competency

Why is a written record of the fixing specification and materials used valuable on a tiling project?

  1. It removes the need for quality checks
  2. It provides evidence of compliance for inspection and future maintenance Correct answer.
  3. It guarantees the roof will never leak
  4. It replaces the need for a safe work method statement

Explanation

Recording the fixing specification and materials creates a compliance trail for building surveyors and helps future maintenance or repairs match the original work. It does not substitute for safety documentation, guarantee performance or remove the need for inspection.

Question 26Core units of competency

Which document should a roof tiler consult first to confirm the required fixing pattern and lap for a specific tile on a job?

  1. The builder's progress claim
  2. The site safety plan
  3. The tile manufacturer's installation manual Correct answer.
  4. The supplier's delivery docket

Explanation

Manufacturer installation manuals state the tested fixing pattern, minimum laps and pitch limits for each tile profile, and compliance depends on following them. Delivery dockets, safety plans and payment claims do not carry installation requirements.

Question 27Core units of competency

Which personal protective equipment is essential when handling roof tiles on site?

  1. Hearing muffs and a face shield
  2. A dust mask and gumboots
  3. A high-visibility vest only
  4. Gloves and safety footwear Correct answer.

Explanation

Tiles are heavy and have sharp edges, so gloves protect hands and safety footwear with grip protects feet and reduces slips on battens and roof surfaces. Other items may be needed for specific tasks but are not the core protection for manual tile handling.

Question 28Core units of competency

What is the primary purpose of roof sarking under tiles?

  1. To provide a secondary weather barrier and collect any water that passes the tiles Correct answer.
  2. To increase the roof's structural strength
  3. To insulate the roof space against heat
  4. To bond the battens to the rafters

Explanation

Sarking is a pliable membrane that sheds any water driven past the tiles and reduces wind and dust entry. It is not a structural member, not the main thermal barrier and does not fix battens.

Question 29Core units of competency

Which tool is used to check that battens are level and evenly spaced along a rafter?

  1. A plumb bob and hammer
  2. A chalk line and tape measure
  3. A string line and tin snips
  4. A spirit level and tape measure Correct answer.

Explanation

A spirit level confirms level across the roof and a tape measure confirms the gauge between battens. A chalk line marks positions but does not verify level, and the other tools do not measure spacing.

Question 30Core units of competency

What does the term 'gauge' mean in roof tiling?

  1. The vertical distance between successive battens Correct answer.
  2. The angle of the roof measured in degrees
  3. The thickness of the tile at the head
  4. The width of a tile including its side lap

Explanation

Gauge is the vertical spacing of battens, which equals the tile's effective length and sets the course spacing up the slope. Side lap relates to cover width, and pitch is a separate roof measurement.

Question 31Core units of competency

Why should a tiler avoid walking on the finished field of tiles where possible?

  1. It can crack tiles and disturb the bedding and laps Correct answer.
  2. It voids the manufacturer's warranty on battens
  3. It makes the roof heavier
  4. It dulls the tile colour

Explanation

Concentrated foot loads can crack tiles and shift or break the bedding and lap, creating leaks. Walking boards spread the load and protect the finished surface.

Question 32Core units of competency

What is the correct way to store pallets of tiles on site before installation?

  1. Stacked beside the excavation edge
  2. Stacked on the ground in a low, stable position on firm level ground Correct answer.
  3. Leaned against the scaffold for easy access
  4. Placed on the roof ridge for later distribution

Explanation

Pallets should sit on firm, level ground in a stable stack so they cannot topple or sink. Placing them on the roof, against scaffold or near excavations creates fall and collapse hazards.

Question 33Core units of competency

Which action best protects a tiler from falling at the roof edge during installation?

  1. Keeping tools in a bucket
  2. Wearing gloves
  3. Working faster near the edge
  4. Installing guardrail or edge protection Correct answer.

Explanation

Edge protection such as guardrail or scaffold prevents a fall from occurring, which is the highest-order control. Speed, gloves and tool storage do not prevent a fall.

Question 34Core units of competency

A roof section measures 6 m along the eaves and the tiles have a cover width of 300 mm. How many tiles are required across that section, before cuts and waste?

  1. 18
  2. 20 Correct answer.
  3. 22
  4. 24

Explanation

Divide the length by the cover width: 6000 mm divided by 300 mm equals 20 tiles. Adding waste for cuts is done after this base calculation.

Question 35Core units of competency

A roof has a total rise of 2 m over a run of 5 m. What is the pitch as a ratio of rise to run?

  1. 1:3
  2. 1:2.5 Correct answer.
  3. 1:4
  4. 1:2

Explanation

Divide rise by run: 2 divided by 5 gives 0.4, expressed as 1:2.5. This ratio is used to check the roof is within the tile's minimum pitch.

Question 36Core units of competency

What is the main reason for laying sarking with the laps running down the slope?

  1. To make the membrane easier to cut
  2. To allow the battens to sit flatter
  3. To reduce the amount of membrane used
  4. So water flows over the laps rather than into them Correct answer.

Explanation

Laps must shed water downhill, so each upper sheet overlaps the lower one and water runs over the joint. Reversed laps trap water and direct it into the roof space.

Question 37Core units of competency

Which fastening method is appropriate for fixing battens to steel rafters?

  1. Galvanised clouts driven by hand
  2. Self-drilling screws or appropriate metal fasteners Correct answer.
  3. Mortar bedding
  4. Tile clips

Explanation

Steel rafters require metal fasteners such as self-drilling screws of the specified type and corrosion class. Clouts suit timber, while mortar and clips are not batten-to-rafter fixings.

Question 38Core units of competency

Why must tile battens be fixed to every rafter they cross?

  1. To reduce the number of tiles needed
  2. To allow tiles to slide into place
  3. To spread the tile load and resist wind uplift Correct answer.
  4. To make the roof easier to paint

Explanation

Fixing to every rafter transfers the tile and wind loads evenly into the frame, which is essential in high-wind areas. Skipping rafters concentrates load and weakens uplift resistance.

Question 39Core units of competency

What is the purpose of a valley in a roof?

  1. To collect and discharge rainwater where two roof planes meet Correct answer.
  2. To provide access to the roof space
  3. To support the ridge capping
  4. To ventilate the roof cavity

Explanation

A valley is the internal intersection of two roof slopes and must carry concentrated water flow to the gutter. It is lined with valley boards or trays sized to the roof catchment.

Question 40Core units of competency

A tiler is installing tiles on a roof with a pitch below the minimum for the chosen profile. What is the most appropriate response?

  1. Reduce the batten gauge to increase the lap
  2. Select a tile profile and sarking system rated for that pitch Correct answer.
  3. Install the tiles with extra overlap and no sarking
  4. Proceed because pitch does not affect weatherproofing

Explanation

Each tile profile has a tested minimum pitch, and below it the roof cannot shed water reliably. The correct action is to use a profile and sarking system approved for the low pitch, not to improvise.

Question 41Core units of competency

What is the main function of a barge capping?

  1. To cover the joint between the tiles and the fascia at a gable edge Correct answer.
  2. To seal the gap at a valley
  3. To support the gutter
  4. To fix the battens to the rafter

Explanation

Barge capping finishes and weatherproofs the gable edge where the tiles meet the barge board or fascia. It is bedded and pointed to shed water clear of the edge.

Question 42Core units of competency

Why should a tiler check the roof frame for straightness before laying battens?

  1. To ensure battens and tiles finish in straight, true planes Correct answer.
  2. To confirm the gutter is level
  3. To calculate the number of ridge caps
  4. To decide the tile colour

Explanation

Rafters that are out of line transfer through the battens and show as wavy tile courses. Checking and packing the frame first keeps the finished roof true.

Question 43Core units of competency

Which statement correctly describes the purpose of a tile underlay batten or counter batten?

  1. It supports the gutter
  2. It replaces the main battens
  3. It creates a drainage gap between sarking and tiles Correct answer.
  4. It fixes the ridge capping

Explanation

Counter battens run up the slope and hold the sarking clear of the main battens, allowing any water to drain to the gutter. They do not replace the main battens or support other components.

Question 44Core units of competency

A tiler finds that a batch of tiles differs noticeably in colour from the previous batch. What is the best action?

  1. Return both batches and stop work
  2. Install the new batch at the ridge only
  3. Install the new batch on one complete roof plane
  4. Mix tiles from both batches evenly across the whole roof Correct answer.

Explanation

Blending batches across the roof spreads colour variation so it is less obvious from ground level. Concentrating a different batch on one plane creates a visible patch.

Question 45Core units of competency

What is the correct treatment where a tiled roof meets a chimney?

  1. Seal the joint with silicone from the outside
  2. Bed the tiles directly against the brickwork with mortar only
  3. Leave a gap for ventilation
  4. Install a flashing system with an apron and side flashings Correct answer.

Explanation

A chimney junction needs a flashing system including an apron, side flashings and a back flashing or cricket to shed water. Mortar or sealant alone will crack and leak over time.

Question 46Core units of competency

A tiler is about to cut tiles on site. Which control most directly reduces the risk of injury from flying fragments?

  1. Wearing safety glasses or goggles Correct answer.
  2. Wearing a high-visibility vest
  3. Working with a partner
  4. Wetting the cutting area

Explanation

Eye protection is the direct control against flying tile fragments during cutting. Wetting the area controls dust and a partner can assist but neither protects the operator's eyes.

Question 47Core units of competency

A tiled roof shows water stains on the ceiling below a hip. Which is the most likely cause?

  1. The hip capping bedding or flashing has failed Correct answer.
  2. The ridge capping is too wide
  3. The battens are spaced too closely
  4. The tiles are the wrong colour

Explanation

Hip junctions rely on correct bedding, pointing and often a hip flashing to shed water. Failure of that bedding or flashing allows water to track into the roof space.

Question 48Core units of competency

Why is it important to record the fixing specification used on a roof, such as clip types and fastener corrosion class?

  1. It reduces the number of tiles required
  2. It replaces the need for a manufacturer's manual
  3. It allows the tiler to skip the final inspection
  4. It supports proof of compliance and future maintenance decisions Correct answer.

Explanation

A record of fixings and materials demonstrates compliance with the specification and helps future trades match components during repairs. It does not replace manuals, change quantities or remove inspection requirements.

Question 49Core units of competency

A roof has a rafter length of 4 m and an eaves width of 10 m, and the tiles have a cover of 0.3 m by a gauge of 0.4 m. What is the approximate tile count before waste?

  1. 360
  2. 333 Correct answer.
  3. 400
  4. 300

Explanation

Tiles per course is 10 divided by 0.3, about 33.3, and courses are 4 divided by 0.4, which is 10. Multiplying gives about 333 tiles before allowing for cuts and waste.

Question 50Core units of competency

A roof is to be tiled in a cyclonic region. Which change to the fixing specification is most appropriate?

  1. Rely on tile weight alone
  2. Increase the number and type of mechanical fixings to every tile as specified Correct answer.
  3. Use mortar only at the ridge
  4. Reduce the number of clips to save time

Explanation

High-wind regions demand greater uplift resistance, so specifications require mechanical fixing of every tile or a higher proportion with rated clips and screws. Reducing fixings or relying on weight would fail under uplift.