CAPM study materials
CAPM study resources

CAPM cheat sheet

CAPM · Keep the key ideas within reach.

Quick reference

Project Management Fundamentals and Core Concepts

  • A project is a temporary endeavor undertaken to create a unique product, service, or result; operations are ongoing and repetitive.

  • The PMBOK Guide 7th edition has 12 principles and 8 performance domains: stakeholders, team, development approach and life cycle, planning, project work, delivery, measurement, and uncertainty.

  • Distinguish three terms: project life cycle (phases from initiation to closure), development approach (predictive, hybrid, adaptive), and product life cycle (spans the product's whole life, often beyond the project).

  • Project manager authority increases along this continuum: functional organization < weak matrix < balanced matrix < strong matrix < project-oriented.

  • PMO types and control level: supportive (consulting and templates, low control), controlling (compliance with frameworks, moderate control), directive (PMs report to the PMO, high control).

  • The project charter formally authorizes the project and the project manager; the sponsor issues it before planning starts and it contains high-level scope, objectives, budget, and risks.

  • Tuckman team development stages: forming, storming, norming, performing, adjourning; a team can regress when membership changes.

  • Conflict approaches: collaborate/problem-solve is win-win and best for long-term resolution; compromise is partial; force, avoid, and accommodate produce a winner and a loser.

  • Scope creep is uncontrolled addition of work without change control; gold plating is adding unrequested extras that add no value.

Quick reference

Predictive, Plan-Based Methodologies

  • Predictive (waterfall) life cycle: scope, schedule, and cost are baselined early, and changes flow through Perform Integrated Change Control and the change control board.

  • WBS rules: deliverable-oriented decomposition; the 100 percent rule means child elements fully represent the parent; the lowest level is a work package; the 8-80 rule keeps work packages between 8 and 80 hours.

  • The critical path is the longest duration path through the network and has zero total float; it determines the shortest possible project duration, so any delay on it delays the finish date.

  • Float formulas: total float = LS - ES = LF - EF; free float = early start of successor - early finish of the activity.

  • Precedence Diagramming Method relationships: finish-to-start, start-to-start, finish-to-finish, start-to-finish; a lead overlaps activities, a lag inserts waiting time.

  • Three-point estimating: triangular = (O + M + P)/3; PERT beta = (O + 4M + P)/6; standard deviation = (P - O)/6.

  • Earned value: CV = EV - AC; SV = EV - PV; CPI = EV/AC; SPI = EV/PV; EAC = BAC/CPI when performance persists; ETC = EAC - AC; VAC = BAC - EAC; TCPI = (BAC - EV)/(BAC - AC).

  • Contingency reserve covers identified risks (known unknowns) and is controlled by the project manager; management reserve covers unknown unknowns and generally requires sponsor approval.

  • Risk response strategies: threats - escalate, avoid, transfer, mitigate, accept; opportunities - escalate, exploit, share, enhance, accept; EMV = probability x impact.

Quick reference

Agile Frameworks/Methodologies

  • Agile Manifesto (2001) four values: individuals and interactions over processes and tools, working software over comprehensive documentation, customer collaboration over contract negotiation, responding to change over following a plan; items on the right still have value.

  • Agile principles include satisfying the customer through early and continuous delivery, welcoming changing requirements, delivering working software frequently, daily business-developer collaboration, self-organizing teams, sustainable pace, and simplicity.

  • Scrum roles: product owner (maximizes value and orders the backlog), scrum master (servant leader who removes impediments and coaches process), developers (build the increment).

  • Scrum events: sprint (1-4 weeks), sprint planning, daily scrum (15 minutes), sprint review, retrospective; artifacts: product backlog, sprint backlog, increment.

  • The sprint goal gives the sprint its focus; scope may be clarified with the product owner but is not changed arbitrarily once the sprint starts.

  • Kanban core practices: visualize the workflow, limit work in progress, manage flow, make policies explicit, implement feedback loops, improve collaboratively; it is pull-based and requires no fixed iterations.

  • Extreme Programming practices include pair programming, test-driven development, continuous integration, refactoring, small releases, simple design, and collective code ownership.

  • Lean targets waste: overproduction, waiting, transport, overprocessing, inventory, motion, and defects; tools include value stream mapping and kaizen (continuous improvement).

  • Metrics and scaling: velocity forecasts team capacity, burndown shows remaining work, burnup shows completed scope; scaling frameworks include SAFe, LeSS, Scrum@Scale, DSDM, FDD, and Crystal.

Quick reference

Business Analysis Frameworks

  • BABOK Guide knowledge areas (6): business analysis planning and monitoring, elicitation and collaboration, requirements life cycle management, strategy analysis, requirements analysis and design definition, and solution evaluation.

  • BACCM core concepts (6): change, need, solution, stakeholder, value, and context; every business analysis task is performed in relation to all six.

  • Requirement types: business requirements (why the change), stakeholder requirements (what stakeholders need), solution requirements (functional and non-functional), and transition requirements (temporary, for implementation only).

  • Elicitation techniques: interviews, workshops, focus groups, observation/job shadowing, surveys, document analysis, prototyping, brainstorming, and interface analysis.

  • A requirements traceability matrix links each requirement to its source, business need, design components, and test cases, enabling impact analysis and coverage verification.

  • Prioritization approaches: MoSCoW (Must, Should, Could, Won't this time), Kano (must-be, performance, delighter, indifferent, reverse), time-boxing, and voting.

  • User story format: 'As a , I want , so that '; INVEST criteria are Independent, Negotiable, Valuable, Estimable, Small, and Testable.

  • Process and scope models: SIPOC (Suppliers, Inputs, Process, Outputs, Customers), BPMN diagrams, use case diagrams, and context diagrams; compare as-is versus to-be states.

  • Solution evaluation measures delivered value against desired outcomes, assesses solution and enterprise limitations, and recommends actions; cost-benefit analysis and ROI support the business case.