ICDL Project Planning study materials
ICDL Project Planning study resources

ICDL Project Planning (ICDL) flashcards

ICDL Project Planning · Build recall with a focused review session.

33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Triple constraint
The interdependent limits of scope, time, and cost. Changing one requires adjusting at least one of the others to keep the project feasible.
Project charter
A document that formally authorizes the project and names the project manager. It is issued by the sponsor before detailed planning begins.
Progressive elaboration
The iterative refinement of project plans as more information becomes available. Detail increases as the project moves from planning toward execution.
Stakeholder register
A record listing each stakeholder's role, interest, influence, and engagement approach. It guides communication planning and stakeholder management throughout the project.
100% rule
A WBS principle stating that the work breakdown structure must capture all project scope and no work outside it. Child levels sum to the parent deliverable.
Work package
The lowest level of the WBS, small enough to estimate, assign, and control. Often sized between 8 and 80 hours of effort.
Scope creep
Uncontrolled expansion of project scope without formal change approval. It erodes schedule and budget and is managed through integrated change control.
WBS dictionary
A companion document to the WBS describing each work package's content, acceptance criteria, owner, and dependencies. It clarifies what each element includes.
Finish-to-Start dependency
A logical relationship where the successor activity cannot begin until the predecessor finishes. It is the most common dependency in project networks.
Discretionary dependency
A preferred sequencing chosen by the project team, often based on best practice. Also called a soft dependency; it can be changed if needed.
Lag and lead
Lag is a positive delay added between dependent activities; lead is a negative lag that accelerates the successor. Both adjust logical relationships.
Precedence diagramming method
A network technique that uses boxes for activities and arrows for dependencies. It supports the four dependency types: FS, SS, FF, and SF.
PERT estimate formula
A weighted three-point estimate: (Optimistic + 4 x Most Likely + Pessimistic) / 6. It emphasizes the most likely value over the extremes.
Parametric estimating
An estimating technique that multiplies a unit rate by a quantity, such as hours per module times modules. Accuracy depends on reliable historical data.
Contingency reserve
Budget or time set aside for identified risks with known probability. It is included in the cost baseline and controlled by the project manager.
Bottom-up estimating
Summing detailed estimates from individual work packages to build a total. It is the most accurate technique but also the most time-consuming.
Critical path
The longest path through the project network. It determines the shortest possible project duration, and its activities have zero total float.
Total float formula
Total float equals Late Start minus Early Start, or Late Finish minus Early Finish. It is the time an activity can slip without delaying the project.
Forward and backward pass
The forward pass calculates earliest start and finish dates; the backward pass calculates latest start and finish. Together they reveal float and the critical path.
Crashing
A schedule compression technique that adds resources to shorten critical path duration. It usually increases cost and has diminishing returns.
Fast tracking
A compression technique that overlaps activities normally done in sequence. It can shorten duration but increases risk and rework potential.
Resource leveling
Adjusting activity start and finish dates to resolve resource overallocation. It may extend the project duration and change the critical path.
Resource smoothing
Using available float to balance resource demand without extending the project end date. It does not change the critical path.
Resource histogram
A bar chart showing resource demand over time. Peaks above available capacity indicate overallocation requiring leveling or smoothing.
RACI matrix
A responsibility chart labeling tasks as Responsible, Accountable, Consulted, or Informed. Exactly one person should be Accountable per task.
Earned value management
A technique integrating scope, schedule, and cost by comparing planned value, earned value, and actual cost to measure performance and forecast outcomes.
Schedule variance
SV equals Earned Value minus Planned Value. A negative value indicates the project is behind schedule.
Cost performance index
CPI equals Earned Value divided by Actual Cost. A value below 1.0 means the project is spending more than planned for work done.
Estimate at completion
A forecast of total project cost, often calculated as Budget at Completion divided by CPI when current cost performance is expected to continue.
Cost baseline
The approved time-phased budget excluding management reserves. It serves as the reference S-curve for measuring cost performance.
Change control board
A group that reviews, approves, or rejects changes to baselines. It enforces integrated change control and protects approved reference points.
Re-baselining
Resetting the approved scope, schedule, or cost reference after a significant approved change. It should be rare and formally authorized.
Performance report
A report comparing actual progress against the baseline, including variances, SPI and CPI values, and forecasts of final cost and schedule.