ICDL Project Planning study materials
ICDL Project Planning study resources

ICDL Project Planning (ICDL) study guide

ICDL Project Planning · Work through your exam, one topic at a time.

ICDL Project Planning (also delivered as ECDL Project Planning in some markets) is a vendor-neutral certification that tests whether you can build and maintain a project schedule using standard planning concepts and a software tool. It suits coordinators, team leads, administrators and anyone who has to turn a scope statement into dated, resourced tasks rather than just track work informally. The ICDL Project Planning study guide has 7 sections and about 2,539 words.

01

Project Planning Fundamentals

A project plan is a decision tool, not a document to file. It converts an agreed objective into a sequence of commitments: what will be delivered, by when, by whom, with what resources, and how deviation will be detected.

340 words, about 2 min
02

Project Scope and Work Breakdown

Scope is defined by the scope statement : product scope (features of what is delivered) and project scope (the work to deliver it). It sets inclusions and exclusions - explicit exclusions prevent later disputes.

325 words, about 2 min
03

Task Dependencies and Sequencing

Sequencing links activities with logical relationships . Know the four: Finish-to-Start (FS) - successor cannot start until predecessor finishes, the most common; Start-to-Start (SS) - successor cannot start until predecessor starts; Finish-to-Finish (FF) - successor cannot finish until predecessor finishes; Start-to-Finish (SF) - successor cannot finish until predecessor starts, rare.

312 words, about 2 min
04

Estimating Duration and Resources

Analogous estimating uses a similar past project; fast and cheap, low accuracy. Parametric uses a rate (e.g.

302 words, about 2 min
05

Scheduling and Critical Path

A schedule network is built from activities, durations and dependencies. Forward pass computes earliest start (ES) and earliest finish (EF) ; backward pass computes latest start (LS) and latest finish (LF) .

329 words, about 2 min
06

Resource Allocation and Leveling

After the logic is set, assign people and equipment to activities. Resource histograms show demand over time; resource calendars show availability.

314 words, about 2 min
07

Project Tracking

Tracking compares actuals to the plan. Percent complete is easy but misleading (90% done for weeks).

617 words, about 3 min