Utilizing the Estimate to Establish and Manage Installation Costs

  • Labor cost = (quantity of work / crew productivity rate) × crew hourly cost including burden; productivity rates must match the estimate basis (e.g., square feet per hour).

  • Material cost = net quantity × unit price × (1 + waste factor); waste factors are estimate assumptions, not defaults, and must be documented.

  • Equipment cost = ownership cost (depreciation, interest, insurance, taxes) + operating cost (fuel, repairs, tires) allocated by hourly rate.

  • Overhead and profit are applied as percentages to direct cost; job cost reports must separate direct cost from markup to compare against the estimate.

  • Contingency in the estimate is a risk allowance, not a spending account; any use requires a change order or management approval.

  • The estimate's work breakdown structure (WBS) becomes the cost code structure for tracking actuals; every estimate line must map to a cost code.

  • Unit costs from the estimate are the baseline for quantity-based progress and earned value; deviations trigger a variance analysis.

  • Escalation and market conditions in the estimate are time-sensitive; if procurement occurs later than assumed, the difference is a legitimate cost impact to track.

Quick reference

Planning the Job

  • The project schedule must be resource-loaded: each activity assigned crew size, equipment, and material delivery dates before mobilization.

  • Critical path method (CPM) identifies zero-float activities; any delay to a critical activity delays substantial completion unless mitigated.

  • A site logistics plan defines laydown areas, access routes, temporary utilities, and material staging to prevent rehandling.

  • Pre-installation meetings (pre-task planning) confirm substrate readiness, material availability, and safety hazards before work starts.

  • The baseline schedule is the approved plan against which progress is measured; revisions require formal schedule updates and owner acceptance.

  • Look-ahead schedules (typically 3–6 weeks) convert the master schedule into weekly work assignments and material call-offs.

  • Permits, submittals, and long-lead items must be tracked on a procurement log with required-on-site dates derived from the schedule.

  • Mobilization costs are estimated separately and should be minimized by sequencing trades to avoid multiple mobilizations.

Quick reference

Understanding Contractual Obligations

  • The contract documents hierarchy (e.g., agreement, general conditions, specifications, drawings) governs in a stated order; conflicts are resolved by that order.

  • A change order is a written instrument signed by the owner (and contractor) that modifies the contract scope, price, or time; verbal directives are not change orders until confirmed in writing.

  • Notice provisions require written notice within a specified number of days (often 7–14) for delays, changes, or claims; failure can waive entitlement.

  • Differing site conditions clauses typically distinguish Type I (unknown physical conditions) from Type II (unknown conditions of an unusual nature); both require prompt notice.

  • Liquidated damages are a pre-agreed per-day amount for late completion; they are not a penalty and must be a reasonable forecast of loss.

  • Pay-when-paid clauses make subcontractor payment contingent on owner payment to the contractor; pay-if-paid clauses shift the risk of owner nonpayment to the subcontractor.

  • Substantial completion triggers warranty start, release of retainage (in part), and transfer of risk of loss; it is certified by the architect/engineer.

  • Indemnity and insurance requirements allocate risk; additional insured status and waiver of subrogation must be verified before work begins.

Quick reference

Scheduling and Assigning Resources for Installation

  • Crew size is determined by dividing required daily output by individual productivity, then adjusting for site constraints and supervision ratio.

  • Resource leveling adjusts start/finish dates within float to smooth peaks; resource smoothing does not change the critical path.

  • Productivity is affected by learning curve, weather, overtime, and site congestion; overtime reduces efficiency and increases unit labor cost.

  • Assigning crews to multiple activities requires checking skill match and certification (e.g., welders, equipment operators) before dispatch.

  • The daily work plan (short-interval schedule) assigns specific crews, locations, and quantities; it is the basis for daily cost tracking.

  • Material and equipment deliveries must be scheduled to match crew needs; early delivery creates storage and damage risk, late delivery causes idle time.

  • Supervision span of control typically ranges from 1:8 to 1:12 depending on task complexity; exceeding it reduces safety and quality oversight.

  • Schedule updates must reflect actual start/finish and remaining duration; percent complete alone does not update the CPM network.

Quick reference

Managing On-Site Conditions

  • Daily reports record weather, manpower, equipment, deliveries, visitors, and delays; they are contemporaneous evidence for claims.

  • Site safety orientation and toolbox talks are required before task assignment; OSHA recordkeeping applies to work-related injuries and illnesses.

  • Housekeeping and waste management plans reduce slips, fire load, and rework; debris removal is a direct job cost.

  • Weather delays must be documented with date, time, and impact; only abnormal weather beyond the contract allowance supports a time extension.

  • Coordination drawings (clash detection) prevent rework; field conflicts are resolved by RFI before installation proceeds.

  • Temporary utilities, lighting, and access must be maintained; failure can cause standby costs that are tracked separately.

  • Quality control inspections (e.g., first-in-place, mock-ups) must be passed before covering work; re-inspection costs are back-charged to the responsible party.

  • Site security and material control prevent theft and loss; inventory records support insurance claims.

Quick reference

Managing Materials on the Jobsite

  • Material receiving requires count, condition inspection, and signed delivery tickets; discrepancies are noted on the ticket and reported immediately.

  • Storage requirements (temperature, humidity, stacking) are specified by manufacturers; noncompliance voids warranties.

  • Inventory control uses a material log with quantities received, installed, and on hand; reorder points prevent stockouts.

  • Waste and theft are tracked through reconciliation of purchased vs. installed quantities; variances indicate loss or inaccurate estimating.

  • Just-in-time delivery reduces storage costs but increases risk of delay; buffer stock is set based on lead time and criticality.

  • Hazardous materials require SDS sheets, labeled storage, and trained handling; incompatible materials are segregated.

  • Owner-furnished materials must be inspected upon receipt; damage or shortage is documented and reported to the owner for replacement.

  • Return of unused materials is governed by contract and supplier restocking fees; credit must be tracked against job cost.

Quick reference

Managing Change Orders On-Site

  • A change order must state the scope change, price adjustment, and time adjustment; it becomes part of the contract when signed.

  • Field work directives (FWD) authorize work before a formal change order is priced; they must be confirmed in writing and tracked.

  • Change order pricing uses the contract's unit rates or a agreed markup on labor, material, and equipment; lack of agreement does not stop the work if directed.

  • Time impacts must be analyzed separately from cost; a change may entitle the contractor to a time extension even if no cost is allowed.

  • Change order log tracks number, description, status (pending, approved, rejected), and cumulative value; it is reconciled monthly.

  • Constructive changes arise from owner actions (e.g., defective specifications, acceleration) and may be claimed even without a formal directive.

  • The cost of preparing a change order proposal is generally not recoverable unless the contract allows it.

  • Unapproved change orders remain a cost risk; they must be accrued in the job cost forecast and pursued through the claims process.

Quick reference

Financial Management: Budget vs. Actual

  • Cost variance = budgeted cost – actual cost; a negative variance is an overrun and requires a corrective action plan.

  • Earned value metrics: CPI = EV / AC; SPI = EV / PV; CPI < 1 indicates cost inefficiency.

  • Estimate at completion (EAC) = AC + (BAC – EV) / CPI; it forecasts final cost based on current performance.

  • Job cost reports must be reconciled to the general ledger monthly; unbilled costs and accruals are included.

  • Committed cost (purchase orders and subcontracts) plus actual cost equals total cost to date; commitments not yet invoiced are accrued.

  • Percent complete for cost should be based on installed quantities or earned value, not on time elapsed.

  • Back charges and credits must be applied to the correct cost code; misapplication distorts variance analysis.

  • Cash flow forecasting uses the schedule and payment terms; retainage and pay-when-paid clauses affect timing.

Quick reference

Handling Claims on the Jobsite

  • A claim is a demand for compensation or time for events not covered by a change order; it requires notice, documentation, and causation.

  • Notice of claim must be given within the contract's time limit (often 7–21 days); late notice may bar the claim.

  • Documentation includes daily reports, correspondence, schedules, cost records, and photographs; contemporaneous records carry the most weight.

  • Delay claims require proof of delay to the critical path, owner responsibility, and resulting damages; concurrent delay can defeat or reduce the claim.

  • Acceleration claims arise when the owner requires faster performance than the contract schedule; costs include overtime, extra crews, and supervision.

  • Differing site conditions claims require showing the condition differed materially from the contract documents and was not foreseeable.

  • Claim presentation should separate entitlement (liability) from quantum (amount); both must be proven.

  • Negotiation and mediation are preferred before litigation; claims can be resolved through the contract's dispute resolution procedure (e.g., architect decision, arbitration).

Quick reference

Closing out the Job

  • Substantial completion is the date when the work is sufficiently complete for its intended use; it starts warranties and reduces retainage.

  • Punch list items must be completed within a specified time; failure can result in owner completing them and back-charging the contractor.

  • Final completion occurs when all punch list items are done and final payment is due; it releases remaining retainage.

  • Closeout documents include as-built drawings, O&M manuals, warranties, spare parts, and attic stock; they are a condition of final payment.

  • Final lien waivers from subcontractors and suppliers are required before final payment to protect the owner from liens.

  • Consent of surety may be required if the contract has a performance bond; it releases the surety from further liability.

  • Final payment application must reconcile all change orders, back charges, and retainage; any disputed amounts are identified.

  • Warranty period typically begins at substantial completion; the contractor must respond to warranty calls within a specified time.