FCICA CIM · Get comfortable with the vocabulary.

Bid vs. Estimate Reconciliation

The process of comparing the original bid amount to the detailed takeoff-based estimate to confirm scope, quantities, and pricing assumptions align before the job is planned and budgeted.

Related: Installation Budget, Cost Code
Installation Budget

The approved dollar amount allocated to labor, materials, equipment, and subcontractors for the installation phase, derived from the estimate and used as the baseline for tracking actual costs.

Related: Bid vs. Estimate Reconciliation, Budget vs. Actual Variance
Cost Code

A numbered label that groups similar work or expense types so labor hours, material purchases, and equipment charges can be collected and compared against the budget line.

Related: Installation Budget, Labor Productivity Rate
Labor Productivity Rate

The expected output per crew hour for a given task, such as square yards of carpet installed per hour, used to convert quantities into labor hours and dollars in the estimate.

Related: Cost Code, Crew Loading
Unit Price

The cost or sell rate assigned to one unit of measure, such as per square foot or per linear foot, multiplied by quantity to build up the estimate line item.

Related: Quantity Takeoff, Installation Budget
Quantity Takeoff

A measured listing of all materials and work items required by the drawings and specifications, forming the basis for pricing, purchasing, and labor-hour calculations on the project.

Related: Unit Price, Waste Factor
Waste Factor

A percentage added to net material quantities to cover cutting loss, damage, pattern matching, and offcuts, ensuring enough product is purchased to complete the installation without shortages.

Related: Quantity Takeoff, Material Delivery Schedule
Scope of Work

The written description of what the contractor is obligated to furnish and install, including inclusions, exclusions, and interfaces with other trades, which anchors both planning and change evaluation.

Related: Work Breakdown Structure, Change Order
Work Breakdown Structure

A hierarchical decomposition of the installation into manageable work packages and tasks, used to assign responsibility, sequence activities, and build the job schedule.

Related: Scope of Work, Critical Path
Critical Path

The longest sequence of dependent activities through the schedule that determines the project's minimum duration; delay to any activity on it delays substantial completion.

Related: Work Breakdown Structure, Look-Ahead Schedule
Look-Ahead Schedule

A short-interval, rolling plan covering the next two to four weeks of work, used to confirm material availability, crew assignments, and readiness of preceding trades before installation begins.

Related: Critical Path, Crew Loading
Crew Loading

The planned number and composition of installers assigned to a work area per day, matched to productivity rates and available floor space so work proceeds without congestion.

Related: Labor Productivity Rate, Look-Ahead Schedule
Mobilization

The organized movement of crews, tools, materials, and equipment to the site at job start or phase start, including staging setup and site access arrangements.

Related: Staging Area, Site Logistics Plan
Contract Documents

The complete set of agreements, drawings, specifications, addenda, and modifications that together define the parties' rights and obligations on the project.

Related: Scope of Work, Notice Provision
Notice Provision

A contract clause setting the time limit and method for informing the owner or general contractor of a condition, delay, or claim; missing the deadline can waive the right to recover.

Related: Contract Documents, Claim
Liquidated Damages

A predetermined sum per day of delay stated in the contract, intended to compensate the owner for late completion rather than to punish the contractor.

Related: Substantial Completion, Time Extension
Pay-When-Paid Clause

A subcontract provision making the subcontractor's right to payment contingent on the owner paying the general contractor, shifting timing risk down the chain.

Related: Progress Payment, Retainage
Retainage

A percentage withheld from each progress payment until the work is accepted, providing the owner leverage to ensure completion and correction of deficiencies.

Related: Progress Payment, Punch List
Progress Payment

A periodic partial payment for work completed and materials stored during a billing period, typically supported by a schedule of values and approved by the owner's representative.

Related: Schedule of Values, Retainage
Schedule of Values

A line-item breakdown allocating the contract sum across portions of the work, used to measure completed value for each application for payment.

Related: Progress Payment, Budget vs. Actual Variance
Budget vs. Actual Variance

The difference between budgeted cost and cost incurred to date for a cost code or the whole job, analyzed to forecast final cost and trigger corrective action early.

Related: Cost Code, Cost-to-Complete
Cost-to-Complete

The forecast of remaining expenditure needed to finish the work, calculated from remaining quantities at current productivity and pricing, plus known commitments.

Related: Budget vs. Actual Variance, Change Order
Change Order

A written, signed modification to the contract that adjusts scope, price, or time, and must be fully documented and priced before or as the changed work is performed.

Related: Field Work Order, Time and Material Ticket
Field Work Order

A site-level authorization directing the crew to perform extra or changed work, later converted into a formal change order, protecting the contractor's right to be paid.

Related: Change Order, Time and Material Ticket
Time and Material Ticket

A daily record of labor hours, material quantities, and equipment time spent on extra work, signed by the owner's representative to substantiate later billing.

Related: Field Work Order, Change Order
Constructive Change

An alteration in scope or cost caused by owner direction, defective drawings, or unreasonable interpretation, treated as a change even without a formal written order.

Related: Claim, Notice Provision
Claim

A formal request for additional money or time based on a disputed condition, differing site condition, delay, or owner act, supported by records and submitted per the contract.

Related: Notice Provision, Time Extension
Time Extension

A contract adjustment moving the completion date to account for excusable delay, shielding the contractor from liquidated damages and preserving the schedule baseline.

Related: Liquidated Damages, Claim
Differing Site Condition

A physical site condition materially different from what the contract documents indicated, such as unexpected substrate moisture or hidden deterioration, which may support a claim.

Related: Claim, Notice Provision
Site Logistics Plan

A drawing and narrative showing material routes, hoisting, staging, dumpster placement, and access restrictions, used to coordinate deliveries and protect finished work.

Related: Staging Area, Mobilization
Staging Area

A designated on-site location for temporary storage and preparation of materials and tools, selected for security, access, and proximity to the work area.

Related: Site Logistics Plan, Material Delivery Schedule
Material Delivery Schedule

A sequenced plan of when products arrive at the site, coordinated with installation sequence and storage capacity so materials are on hand but not exposed unnecessarily.

Related: Waste Factor, Staging Area
Acclimation

The required conditioning of materials, such as flooring, at site temperature and humidity for a specified period before installation, per manufacturer instructions.

Related: Material Delivery Schedule, Manufacturer Instructions
Manufacturer Instructions

The written installation, substrate, and environmental requirements published by the product maker, which govern acceptable practice and affect warranty validity.

Related: Acclimation, Substrate Moisture Test
Substrate Moisture Test

A field measurement of moisture content or emission in the slab or subfloor, performed before installing moisture-sensitive products to confirm the surface is within tolerance.

Related: Manufacturer Instructions, Differing Site Condition
Punch List

A compiled list of incomplete or deficient items identified at substantial completion, tracked to completion and sign-off as a condition of final payment.

Related: Substantial Completion, Retainage
Substantial Completion

The stage at which the work is sufficiently complete for its intended use, triggering owner occupancy, warranty start, and release of most retainage.

Related: Punch List, Liquidated Damages
Closeout Documents

The final submittal package including warranties, attic stock, maintenance instructions, as-built records, and final lien waivers, required to close the contract.

Related: Substantial Completion, Lien Waiver
Lien Waiver

A signed statement by a contractor or supplier relinquishing the right to file a mechanic's lien for work or materials covered by a specified payment.

Related: Progress Payment, Closeout Documents