32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Labor cost formula
Labor cost equals quantity of work divided by crew productivity rate, multiplied by crew hourly cost including burden. Productivity must match the estimate basis.
Waste factor
A percentage added to net material quantity to account for cutting, breakage, and handling loss. It is an estimate assumption that must be documented and tracked.
Cost code structure
The work breakdown structure from the estimate used to track actual costs. Every estimate line must map to a cost code for budget vs. actual comparison.
Contingency
A risk allowance in the estimate for unknown conditions. It is not a spending account; use requires a change order or management approval.
Critical path method
A scheduling technique identifying the longest path of dependent activities with zero float. Any delay on this path delays project completion.
Look-ahead schedule
A short-interval schedule covering typically three to six weeks. It converts the master schedule into weekly work assignments and material call-offs.
Site logistics plan
A plan defining laydown areas, access routes, temporary utilities, and material staging. It prevents rehandling and improves safety and efficiency.
Baseline schedule
The approved project schedule against which progress is measured. Revisions require formal updates and owner acceptance to remain valid.
Change order
A written instrument signed by owner and contractor that modifies contract scope, price, or time. Verbal directives are not change orders until confirmed in writing.
Notice provision
A contract clause requiring written notice within a specified number of days for delays, changes, or claims. Failure to comply can waive entitlement.
Liquidated damages
A pre-agreed per-day amount for late completion. It must be a reasonable forecast of loss, not a penalty, and is enforceable if reasonable.
Substantial completion
The date when work is sufficiently complete for its intended use. It starts warranties, transfers risk of loss, and may release part of retainage.
Resource leveling
Adjusting start and finish dates within float to smooth resource peaks. It may change the critical path if float is consumed.
Crew size calculation
Required daily output divided by individual productivity, adjusted for site constraints and supervision ratio. Determines labor resource assignment.
Short-interval schedule
A daily or weekly work plan assigning specific crews, locations, and quantities. It is the basis for daily cost tracking and progress measurement.
Span of control
The number of workers a supervisor can effectively manage, typically eight to twelve depending on task complexity. Exceeding it reduces safety and quality oversight.
Daily report
A contemporaneous record of weather, manpower, equipment, deliveries, visitors, and delays. It is primary evidence for claims and schedule impacts.
Abnormal weather
Weather conditions beyond the contract allowance that may support a time extension. Must be documented with date, time, and impact.
RFI
Request for Information used to resolve field conflicts or ambiguities before installation. Responses become part of the contract documents.
First-in-place inspection
A quality control check of initial work before proceeding. Passing it prevents rework and establishes the standard for subsequent work.
Material receiving
The process of counting, inspecting, and signing delivery tickets. Discrepancies must be noted on the ticket and reported immediately.
Inventory control
A material log tracking quantities received, installed, and on hand. Reorder points prevent stockouts and support reconciliation.
Just-in-time delivery
Delivering materials as needed to reduce storage costs. It increases risk of delay, so buffer stock is set based on lead time.
SDS
Safety Data Sheet required for hazardous materials. It provides handling, storage, and emergency information and must be accessible on site.
Field work directive
A written authorization to proceed with changed work before a formal change order is priced. It must be confirmed and tracked.
Constructive change
A change arising from owner actions such as defective specifications or acceleration, without a formal directive. It may be claimed if documented.
Change order log
A record tracking number, description, status, and cumulative value of all change orders. It is reconciled monthly against job costs.
Time impact analysis
A separate analysis of schedule impact from a change. A change may entitle time extension even if no cost is allowed.
Cost variance
Budgeted cost minus actual cost. A negative variance indicates an overrun and requires a corrective action plan.
CPI
Cost Performance Index equals earned value divided by actual cost. A value less than one indicates cost inefficiency.
Estimate at completion
EAC equals actual cost plus (budget at completion minus earned value) divided by CPI. It forecasts final cost based on current performance.
Committed cost
Purchase orders and subcontracts awarded but not yet invoiced. It is added to actual cost to determine total cost to date.